19 November 1969
CIA Headquarters Building, Langley, Virginia
Contract No. - 2839 Construction of Building
Contractor: Charles H. Tompkint;Company and J. A. Jones Construction
Company
Date of Award : March 24, 1959
Amount of Award : $33, 287, 600.00
Final Settlement Date : November 16, 1965
Final Settlement Amount: $36,680,474.00
Contract No. - 2840 Installation of Complete Escalator
Contractor: Otis Elevator Company
Date of Award
: March 24, 1959
Amount of Award
: $34, 157.00
Final Settlement Date
: January 11, 1963
Final Settlement Amount: $34, 715.00
Contract No. - 2841 Installation of Elevator Plants
Contractor: Otis Elevator Company
Date of Award
: March 24, 1959
Amount of Award
: $1,088, 512.00
Final Settlement Date
February 18, 1963
Final Settlement Amount: $1, 090, 855.00
Approved For Release 2002/05/09 : CIA-RDP86-00244R000300020047-1
Approved Fg Release 2002/05/09 : CIA-RDP86-0024AR000300020047-1
Page 2
Contract No. 6669 Grading and Drainage for Roadways, Walks, and
Parking Area
Contractor: North American Construction Corporation
Date of Award : January 17, 1958
Amount of Award : $458, 500.00
There has been no final settlement as yet (in litigation).
The last known amount that has been paid is $516, 575. 42.
Contract No. 6415 Construction (Excavation of Foundation)
Contractor: Roscoe Engineering Corporation and Ajax Construction
Company Incorporated and Associates
Date of Award
: October 9, 1958
Amount of Award
: $2, 309, 162. 62
Final Settlement Date
: September 11, 1962
Final Settlement Amount: $2, 310, 717.22
Contract No. 8510 Telephone System
Contractor: Tompkins - Jones
Date of Award : April 14, 1961
Amount of Award : $31,507,50
Final Settlement Date : May 2, 1962
Final Settlement Amount: $63, 015.00