MONTHLY NARRATIVE SUMMARY REPORT - JULY 1976

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78-02820A001400090005-1
Release Decision: 
RIPPUB
Original Classification: 
C
Document Page Count: 
6
Document Creation Date: 
December 20, 2016
Document Release Date: 
June 4, 2003
Sequence Number: 
5
Case Number: 
Publication Date: 
September 3, 1999
Content Type: 
PERRPT
File: 
AttachmentSize
PDF icon CIA-RDP78-02820A001400090005-1.pdf319.02 KB
Body: 
Approved For Release 2007/10/23: CIA-RDP78-02820A001400090005-1 OPTIONAL. RARM NO. 10 E 1 ~ ~ ~ ~ ~~ ~ ~ ~~~ MAY IBa2 EDITION yV,$Vi G3A FPMR (41 CFR~ f01 d 1.6 ~~ UNITED STATES GOVERNMENT Memorandum FROM Chief, Communications Engineering SUBJECT: Monthly Narrative Summary Report--July 1976 OCE-M76-339 DATE: 6 August 1976 1. Mr.~~ accompanied by Messrs. attended meetings at on 30 June an u y to review t e status of t e - program. 0 demonstrated the digital version of the Laserfax to .be used for the ITS-W terminals and con- firmed that a test link, using digital Laserfax, will be installed between Qand Headquarters by 20 October 1976. 2. On 30 June, a contract in the amount of $553,249 was awarded to Raytheon Data Systems Company, Norwood, Massachusetts, for procurement of the first two wideband digital microwave links of the Headquarters Area Transmission System (HATS). These links will interconnect Head uarters and NPIC via a repeater site at Included in the contract price was an optional training package. System delivery is scheduled for June 1977. 3. Plans and specifications for installation of a secure voice and data grid at the Building were completed this month and forwarded to GSA for implementation. 4. The first running of the CDS Pre-Acceptance Test (PAT) was completed. This run-through of the PAT was an effort on the part of Oto correct problem areas prior to the formal PAT beginning. In a meeting with Representatives on 29 July, we were informed there were 18 outstanding software problems. The first CDS VDU operator course began on 6 July. The series of VDU training courses will continue until early September. Q reported an additional schedule slippage with final acceptance now scheduled for approximately 1 November, 5. The AFT project moved along the first stages of soft- ware design and system integration durin the month. the AFT programmer, is at the acility in working with their personnel on the initial system esign. An Optical Character Reader OCR) and M-40 Teletype equipment were shipped to and technical discussions were held on the equipment features and interfacing requirements. 25X1 25X1 25X1 25X1 Buy U.S. Savings Bonds Regularly an the Payroll Savings Flan Approved For Release 2007/10/23: CIA-RDP78-02820A001400090005-1 Approved For Release 2007/10/23: CIA-RDP78-02820A001400090005-1 SUBJECT: Monthly Narrative Summary Report--July 1976 Several M-40 KDP technical and documentation problems surfaced during the discussions which hopefully will be resolved during a joint Otrip to 6. On 20 July, the tandem switch preacceptance tests were resumed at the Company plant in Dallas, Texas. On 24 July, the tests were stopped Juler meetingsof 30 problems were i and were held with the _ _ _1 d. 1,1.1111 V L~+~ 411w .. __ ants to provide a switch that functions h e w and stated that properly. He added that an eight-point action plan will be implemented to provide a systems analysis, the hiring of a telephone consultant and a full-time systems analyst, the addition of two fixed head discs to the system, restructuring of the interdata computer operating system and disc driver, the development of a "s ecific performance" test procedure, monitoring of the bulk core development, and the submission of bimont y sta us reports. A total of 5 3/4 months will be needed to complete these eight points. On 29 July, a letter containing the above mentioned points and a new schedule was received from and accepted. 7. The Headquarters shielded enclosure installation team arrived on site in0 22 July, and the installation for l osure is progressing smoothly. The new shielded enc is in shipping channels. 8. Difficulties have arisen in obtaining a couriered _ _ ,r _ __ iL ,. -- -- 5nl~u~eti4 vi 1,11 ...,.. ~~..~.,____ - enclosure in ~ We are investigating methods of alter- native means for s spping, with appropriate inspection, when the door arrives on site. 9. The contractor is progressing on the finish work for the new 0 T-Site: Headquarters power engineers are scheduled to arrive on site in early August to install the power bus duct and complete the installation of the new generators and switchgear. If all goes well, the plant will be fully operational in September. 10. Ma'or items of equipment have been ordered out for shipment to~for the eventual installation of a RTTY on-line station in the new Approved For Release 2007/10/23: CIA-RDP78-02820A001400090005-1 Approved For Release 2007/10/23: CIA-RDP78-02820A001400090005-1 ~~J[~~I~~~~i i l~l,. SUBJECT: Monthly Narrative Summary Report--July 1976 11. The satellite again performed bilit poorly with several spin-ups and periods of insta _ _ ~ _ ~_~~L. /''?+_rviror to t~'1A - scazLeif'iu 4111V1.L~ilvw~. r+... ... ..--____ satellite commenced at 08002, 19 July. By the end of the h ~ h e t month, there were 14 terminals operating wit which naa previuu~ly ~~~11 ~r?~w?~.-a with the a e lite. Several Atlantic terminals must continue to operate with the ailing atellite since they are too far out of the satellite antenna pattern to receive a useful signal level. 12. SC-lA terminals and #0047 were tested and acce ted for delivery from The installation of an SC-1A termina was s ed 14. 0 -The MUX units were received at TAI and rejected. After some design changes, in-plant tests indicate the units now meet specifications. One complete system has been received at TF~I and will be checked immediately following the 15. 0 -The vendor delivered the units one week behind schedule. The COTR ran in-plant checks before ship- ment and the units performed satisfactorily. Detailed tests at TAI will be performed during the first week of August. 16. SKYMUX--Six MX-113's were received at TAI, four of which have been accepted. One of these will be installed at during August. The first ,article wiringVhaYne~srhonanPls S 1r1A- 11 J J rv w.~ were received from ADC. After TF~I they will be shipped to Quanta Systems completing the GFE for six first article RR-113 SKYMUX racks. 17. A sample PC card which provides keep-alive capability for the 6515-1 was received. The field was informed that Collins has converted to LED readouts on all new 6515-1's. A11 old units in our system will be modified for LED's, and we are 25X1 25X1 Approved For Release 2007/10/23: CIA-RDP78-02820A001400090005-1 Approved For Release 2007/10/23: CIA-RDP78-02820A001400090005-1 ~~~~i~~?~ ~ iAl~ SUBJECT: Monthly Narrative Summary Report--July 1976 examining the possibility of converting all units to the new keep-alive circuit as well. 18. The audio lease between was checked and did not meet specifications. The phone company is working on this problem. 19. Thirty-eight modified TLC-1's have been received from CED. They are being tested at and will be shipped to the field. 20. Mr. returned from his survey of radiation levels in South America. 21. Covert Engineering Division, Requirements Support Branch, realigned its personnel and changed its procedure for handling both .operational and engineering projects. The objective is to increase their capability to respond more readily to operational requirements and to reduce the impact of operational requirements on each of the engineers. 22. July was an extremely busy month for operational requirements. terminals and forty-eight pieces of ancillary equipment were shipped compared to 0 and 120 respectively for the entire third quarter of last calendar year. Thirty-nine SOR's and cables were completed in July compared to a total of 70 for the entire quarter of last year. The overdues on the suspense list hit a new low with two overdues out of 35 operational requirements and one over- due out of twelve non-operational requirements. 23. Two internal production projects were initiated this month. Eleven CU-108 Control Units were requested, and 40 TA-7 alignment tools were produced. Additionally, two working models of a miniature version of the SV-8 are being prepared and an RS-200 microphone headset is being interfaced to the SV-8. A preliminary action plan for the CU (X)-37 universal control unit was prepared. 24. The Class A evaluation of the SOUTHCOM SC-130 tactical transceiver was completed in July. The evaluation report is being prepared for forwarding to COD. 25. Preliminary preparation of bid packages for external production of 75 RT-59A units was started in late July. The first 50 RT-59A units are being produced in-house. ~ Y~~p - _ a a a 1 6i G~._ Approved For Release 2007/10/23 :wCIA-RDP78-02820A001400090005-1 Approved For Release 2007/10/23: CIA-RDP78-02820A001400090005-1 ~~~ ~~~.~~~~1~L SUBJECT: Monthly Narrative Summary Report--July 1976 26. was provided with four GFE items for a CY/K-3 contract. 27. SKYLINK Terminals were shipped to 0 and - - --- for shipment to ~ during August. MSB and TSB personnel are in the rocess of assembling seven SKYLINK Installation Kits at the 28. Mr. reported to MSB on 26 July to replace Mr. who will re ort to OL on 9 August for reassignment. Ms. OL careerist, reported on 26 July for one-month OJT. Mr. was assigned to TSB for training in the Repair 29. Requisitions for the first month of the TQ are below average. Only 45 requisitions have been processed for direct procurement and stock replenishment. There have been 181 field requisitions processed and 128 Headquarters- initiated requisitions for field stations have been processed. 30. TSB welcomed their first COOP student this month, Mr. who was assigned to the Repair ~ Return Maintenance Section. 31. There was an increase in TECHREQ traffic and RJR transactions this month with a total of 484 TECHREQS and 1,460 RJR transactions. Part of the RJR increase can be attributed to the 0 crisis which accounted for six PRIORITY TECHREQS for SKYLINK. support. 32. The SG-75 A to B modification program was implemented this month with the shipment of six modified units, four to 25X1 25X1 33. Mr. Engineering Tech, was trained as an alternate TECHREQ Terminal Operator. The terminal is now manned eight hours a day vice six with Mr. Q providing 25X1 coverage from 1430 to 1630 hours. Approved For Release 2007/10/23: CIA-RDP78-02820A001400090005-1 Approved For Release 2007/10/23 :CIA-RDP78-02820A001400090005-1 r,~rr ~~i~ID~~31AL` SUBJECT: Monthly Narrative Summary Report--July 1976 Distribution: Origin - D/CQ; DD/CQ; OC-EXA; OC-PCB; OC-IC (Archives) 1 - OC-0; OC-0/D 1 - OC-S; OC-CS ~~~ 8 ~~~# Approved For Release 2007/10/23 :CIA-RDP78-02820A001400090005-1