MONTHLY PROGRESS REPORT, CONTRACT (Sanitized)

Document Type: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78B04747A001600020094-0
Release Decision: 
RIPPUB
Original Classification: 
K
Document Page Count: 
6
Document Creation Date: 
December 28, 2016
Document Release Date: 
April 19, 2000
Sequence Number: 
94
Case Number: 
Publication Date: 
January 31, 1964
Content Type: 
MEMO
File: 
AttachmentSize
PDF icon CIA-RDP78B04747A001600020094-0.pdf138.47 KB
Body: 
1M5oc&rtse, 0/06/07: CIA-RDP78B0*F47A00160002 Memo No: STATOTHR TO: FROM: SUBJECT: DATE: General Declass Review, NIMAIDoD Contracting Officer j/ Project Engineer, E80 STATOTHR Monthly Progress Report, Contract 31 January 1964 The progress report is separated into several sections, the first of which is a percentage >ummary of the schedule. This is followed by a statement on the progress and remarks on work completed, work in process and planned work effort. Finally a table showin,: each task and the percentage complete is supplied. B. Schedule Percent Required Major Project Tasks Percent Complete By Project Schedule I System Engineering 100% 100% II Subsystem Design 75% 75% III Construction and/or Purchasing and Assembly 15% 20% IV Testing and Debugging 0% 0% V Final Inspection 0% 0% As indicated in the project completion percentages, the project is progressing according to schedule with the exception of the task identified in the listing in Table 1. It is expected that this will be advanced in February. , C. Summary of Progress 1. Electronic Control The major effort this month has been centered around the design of the special Electronic circuits for controlling the system clock frequency. Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020094-0 MenAp QMed7For. lease 2000/06/07 : CIA-RDP78904747AO01600020094-0 Page 2 2. Coor'+natograph The table and related castings are under fabrication and two pictures of some castings are enclosed. The table itself is in the heat treating stage. D. Planned Work Effort The general schedule is as follows: February 1. Complete cabinetry design 2. Specify temperature sensing system W 3. Assemble servo `test apparatus 4. Wire electronic racks 5. Begin Testing electronic racks March 1. Test servo apporr tus 2. Test cooling systems 3. Test electronic racks April l 1. Assemble and wire coordinotograph 2. System test Detailed Progress Report Detailed estimates of progress on all project tasks are listed in Table I. The following is an explanation of the progress approximations listed. 0% Tasks not started 10% Tasks started but not 25% accomplished 25% Tasks over 25% accomplished but less than 50?%o accomplished 50% Tasks over 508 accomplished but less than 75% accomplished 75% Tasks over 75% accomplished but less than 100`'i,, accomplished 100% Tasks completed Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020094-0 Approved For Re1edse 2000/06/07 : CIA-RDP78B0 7A001600020094-0 Progress Report on Project Tasks Project Tasks Labor Effort Percent Complete IV. Testing and Debugging A. Coordinatograph 1. Structure a. b. c. Support and Table Gantry and Carriage Vacuum Platen 2. Drive System a. b. c. d. Power Control Power Supply Tost Apparatus Cooling System 3. Human Engineering a. b. Manual Controls Cabinetry 4. Paper Feed Subsystem 5. Writing Head B. Electronic Control 1. Logic Circuits 2. Axis Instrumentation Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020094-0 Approved For to Nraogre2l~epoO on royjc - 78B94747A001600020094-0 Project Tasks Labor Effort Percent Complete Ill. Construction and/or Purchasing and Assembly A. Coordinotograph 1. Structure a. Support and Table A b. Gantry and Carriage c. Vacuum Platen 2. Drive System a. Power Control b. Power Supply c. Servo System Test Apparatus d. Temperature Sensors 3. Human Engineering 25 25 25 10 0 0 0 a. Manual Controls 50 b. Cabinetry 0 4. Paper Feed Subsystem 5. Writing Head B. Electronic Control 1. Standard Logic Board Fabrication 2. Special Logic Board Fabrication 3. Intra-rack Wiring 4. Inter Rack wiring 5. Axis Instrumentation 100 Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020094-0 Approved For RQpase 2000/06/07 : CJA-R[ 17860 47AO01600020094-0 Progress Report on rojec ..s Project Tasks II. Subsystem Design A. Coordinatogrnph 1. Structure as Support and Table b. Gantry and Carriage co Vacuum Platen 2. Drive System a. Power Control b. Power Supply c. Test Apparatus d. Heat Load Calculations 3. Human Engineering as Manual Controls b. Cabinetry 4. Paper Feed Subsystem 5. Writing Head B. Electronic Control 1. Detailed Logic 2. Special Circuit Design 3. Rack and Cable Allotment 4. Axis Instrumentation 5. Heat Load Calculation Labor Effort Percent Complt 100 100 100 100 50 100 100 50 75 50 100 75 75 25 100 100 Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020094-0 Approved For Rease 2000/06//AOILESIA-RDP78BO4W47A001600020094-0 Progress Report on Project Tasks Project Tasks Labor Effort Percent Complete 1. System Engineering - Develop Subassembly Specifications A. Coordinatograph 1. Structure 100 2. Drive System 75 3. Human Engineering 100 4. Paper Feed Subsystem 100 5. Writing Head 100 B. Electronics Control 100 Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020094-0