INSTALLATION OF(Sanitized) COMPANY PLOTTER
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP78B04747A001600020022-9
Release Decision:
RIPPUB
Original Classification:
C
Document Page Count:
3
Document Creation Date:
December 28, 2016
Document Release Date:
April 18, 2000
Sequence Number:
22
Case Number:
Publication Date:
June 26, 1964
Content Type:
MFR
File:
Attachment | Size |
---|---|
CIA-RDP78B04747A001600020022-9.pdf | 153.74 KB |
Body:
4O3 Ti
~3
'Approved For Rele ?@ 200-OtO6/07 : CIA-RDP78B04,747A001600020022-9
.oa-
DECLASSIFICATION REVIEW BY NIMA /
DoD
26 June 1964
MEMORANDUM FOR: The Record
SUBJECT: Installation of Plotter
25 June 1964 -.Meeting Attended by Following Persons:
25X1A
25X1A
25X1A
25X1A
25X14m
25X1A
25X1A
25X1A
25X1A
25X1A
25X1A
(f)
1. A meeting was called,to review and appro',ire engineering drawings
prepared by Region 3, C&D, (2) to discuss the feasibility of having the
Agency procure some of the installation components rather than GSA in order
to save time and, (3) the possibility of justification for negotiated
contract.
2. A discussion was held, The present design embodies the high
pressure concept. In order to resolve the confusion as to whether it
should be high pressure or low pressure, the drawings will be forwarded
to on Monday for their review and approval prior
to commencing the installation work, of GSA maintains that
he understood to specify high-pressure
cooling air; but subsequently stated that he believed Mr.
must have misunderstood him that low pressure air as originally
contemplated would suffice.) approved the diameter of the
holes to be cored through the floor of to accommodate' the
air ducts for the plotter and stipulated, further, once the installation
of this duct work had begun the work could not be stopped until the area
had been filled in completely with concrete.
4. Regarding the cost of this installation, stated that
it now appears the total installation post might run as high as $30,000
to $33,000, The estimate given originally by of Region 3 had
been 20,000, There have not been any changes made in the installation
concept which would account for this increase,
FOP9ii,' 1
Excledc l iron aalcnna;l;
rAWUMM Oft Mft -7
Approved For R
9;;1[P78B04747A001600020022-9
'Approved For Relea 2015b106107 : CIA-RDP78B04 7
47A001600020022-9
oaax r A.?
loilax,
25X1A
5. of GSA raised the question of whether or not th
e
Agency could submit to GSA a justification which would permit them to
negotiate the contract for this work. It was estimated that as much as
six weeks in time might be saved by this approach. felt
preparing such a justification would be no problem. Further discussion
25X1 A brought up the possibility that this contract might be handled as a
change order to the basic alteration contract which has been awarded
to Construction Company of Alexandria for the partitioning and.
25X1 A associated work on the first, second, third, and sixth floors. Mr.
of GSA thought there was a very good chance of following through
on this approach.
25X1 A 6. of GSA is going to check into the availability and
lead time required for the procurement of certain key components for
the installation, the object being to determine whether the purchase of
these items could be done more quickly by the Agency, by GSA, or by the
eventual contractor.
7. In discussing the target date for completing the installation of
the plotter, it was concluded that the completion of the installation can,
not be expected anytime sooner than 60 days after the award of contract,
which would appear to move the target date back from the first of August
to somewhere around the first of October, This information will be passed
on to the IPD.
25X1A
25X1A
25X1A
25X1A
8. role as the Agency's engineering coordinator on
this project was re-emphasized, agreed that he understood
that he was to monitor all engineering aspects of this job, In turn,
NPIC will work through him in its dealings with GSA on engineering
matters,
9. At the conclusion of the meeting. the ni a.n of an+-t^n o,,d -A .,,
a. GSA, Region 3, C&D '1 submit installation
drawings on Monday to for review and approval,
25X1A
b. Region 3 will pre are a revised, firm cost estimate and
25X1 A notify us, through of RECD/OL,
25X1 A c, Region 3 will notify us through of its find-
ings regarding availability, cost, and lead time of key mechanical
components, If these items are not readily available, it may be
necessary for the Agency to issue a DOD priority in order to reduce
the lead time.
Approved For ReleasC b6'tCIA-RDP78B04747A001600020022-9
25X1A
Approved For Release 2000/06/07 : CIA-RDP78B04747A001600020022-9
d. Messrs. will together explore the
possibility of handling the installation work by means of a change
order to the Company contract. (If this can be done, a justi-
fication for negotiation of this contract would not be required).
25X1A
25X1A
Chief, Building Services Section, LB/SS
25X1 A LB/SS
Orig. & 1 - LB/SS
1 - LSD/OL
1 - RECD/OL
1 - IPD
1 - P&DS
:2623:(26 June 196+)