OL/NBPO WEEKLY REPORT - PERIOD ENDING 6 JANUARY 1988
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP90-00078R000100010007-1
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
2
Document Creation Date:
December 27, 2016
Document Release Date:
February 13, 2013
Sequence Number:
7
Case Number:
Content Type:
MISC
File:
Attachment | Size |
---|---|
CIA-RDP90-00078R000100010007-1.pdf | 81.96 KB |
Body:
Declassified in Part - Sanitized Copy Approved for Release 2013/02/13: CIA-RDP90-00078R000100010007-1
STAT
RG
STAT/
ft\tr)
STAT
STAT
STAT
STAT
1g 0
OL/NBPO WEEKLY REPORT - PERIOD ENDING 6 JANUARY 1988
1. Progress Reports on Tasks Assigned by or of Interest to Senior
Management:
None.
2. Major Events that Have Occurred During the Preceding Week:
a. All eight roll-up doors have been installed at the new South
Loading Dock. Additional concrete paving work at the dock has been delayed
due to the cold weather. Work is in progress setting up the formwork for
the curved concrete retaining wall in the Snufh nnck Area adiacent to the
New Headquarters Building South Tower.
f4 The south building-to-building filter room in the New
Headquarters Building is scheduled for completion by the Bid Package 2
contractor the week of 11 January 1988. Facilities Management Division,
CL, will then modify the area in order to meet the specific reauirements
ont the Office of Information Technology.
c. On 4 January 1988, testing began on the last of eight UPS
systems in the New Headquarters Building. This testing was delayed until
defective parts were replaced by Exide Electronics.
d. On 5 January 1988, Office of Information Technology
subcontractors resumed modifying conduit and installing telephone trunk
lines in the South Tower of the New Headquarters Building. This work is
being closely coordinated with the General Services Administration since
these work areas have not been accepted from the construction contractor.
3. Upcoming Events:
Facilities Management Division, OL, has made arrangements to have a
testing company come on site on 9 January 1988 in an effort to locate a
suspected major leak in the south side chilled water line. The New
Building Project Office, OL, has requested that the General Services
Administration have the Bid Package 1 excavating contractor on site on that
date to dig for the leak if found by the testing company.
4. Management Activities and Concerns:
The New Building Project Office, OL, is working with Facilities
Management Division, OL, and the Office of Information Technology in an
effort to move the General Services Administration (GSA) Project Manager
and his staff of inspectors into an area of the New Headquarters Building
Declassified in Part - Sanitized Copy Approved for Release 2013/02/13: CIA-RDP90-00078R000100010007-1
Declassified in Part - Sanitized Copy Approved for Release 2013/02/13: CIA-RDP90-00078R000100010007-1
--.
on the first floor of the South Tower. This will allow removal of the GSA
construction trailers and will address a complaint voiced by some of the
inspectors about having to spend another winter in cold, damp trailers.
STAT Target time frame for relocation is the end of January.
STAT
D/OL
C/FMD/OL
Chief, New Building Project Office
Declassified in Part - Sanitized Copy Approved for Release 2013/02/13: CIA-RDP90-00078R000100010007-1