SOVIET ENTERPRISES PARTICIPATE IN CONSTRUCTION OF KUYBYSHEV, STALINGRAD, AND KAKHOVKA GES
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP80-00809A000600380104-4
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
13
Document Creation Date:
December 22, 2016
Document Release Date:
September 12, 2011
Sequence Number:
104
Case Number:
Publication Date:
February 26, 1951
Content Type:
REPORT
File:
Attachment | Size |
---|---|
CIA-RDP80-00809A000600380104-4.pdf | 716.18 KB |
Body:
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
INFORMATION FROM
FOREIGN DOCUMENTS OR FtADlO BROADCASTS CD NO.
DATE OF
INFORMATION 1950
`Numbers in parentheses refer to appended list of sources
The Volga wad the Dnepr hydroelectric projects received considerable
? press coverage from 3 September to 25 November 1950, the period covered in
this report. After the decrees announcing the pro~ecta had been published,
several long articles lauding the undertaking of such enormous tasks appeared,
claiming Soviet peaceful intentions and industrial superiority on the basis
of these projected schemes.
? Space wen then devoted to articles dealing with the effect these projects
would have on local areas, kolkhozes, etc., the accomplishments and tasks of
various organizations, blaL mainly with plants and enterprises which were sup-
plying or pledged to supply the GES,in their construction stages. These arti-
cles dealt with pledges, production, and in some cases, delivery to the con-
struction site. Very often it was announced that 'these plants filled the GES
orders in addition to completing their basic plan so that even though
the GES orders were considered priority projects, they still amounted to "above
plan" production.
Completing their part in this socialistic pro3ect was offered as a chal-
lenge to the workers. Special work brigades and committees for cooperating
with the construction projects were formed in plants, scientific societies,
labor unions, and party organizations. The Academy of Sciences USSR and vari-
ous republic Academies of Sciences, formed committees for cooperating with the
hydroelectric projects. Their work was to coordinate activities of the various
scientific research institutions. Signs advertising the pro~ecta were prominently
displayed in the plants and project-bound material ?tae marked "to Kuybyshev G'ES"
or "to,Stalingrad GES," etc.
'1
Articles dealing with progress at the construction sites spoke mostly of
exploratory work along the cc.nals or dam sites, ezploratory drilling, which was
conducted on a ~nree-s'nift basis, and road and rail bniiaiag to connect the con-
struction sites to existing lines. As early as 29 September, hundreds of drill-
ing outfits were working on a three-shift basis at the Kuybyshev constructlon
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
HOW
1
PUBLISHED Daily newspapers, weekly periodica
WHERE
PUBLISHED USSR
DATE
PUBLISHED 3 Sep - 25 Nov 1950
CLASSIFICATION SECRET
DATE DIST. ab Feb '1951
N0. OF PAGES 13
SUPPLEMENT TO
REPORT N0.
THI ; IS UNEVALUATED INFORMATION
TNIf OOCV^[NT CONTAIN[ IN IDNYATION ATTLCTIND TNL NATIO[AL D[I[NH
Oi TN[ VMIT[0 [TAT[3 VITNIN TML N[AMIND Of [[IIONADI ACT [0
V. [. C.. DI AND DZ. AE AN[ND[D. IT[ T[AN[NI[[IDN O[ TN[ [[V [LATION
Oi ITf CONT[Nl[ IN ANT YAMNL[ TD AN UNAVTNO[IZ[D ILN[ON If IAD?
NI[IT[D [T LALt._ [[I[OOUCTION Of TNI[ 10 [N If I[OMI[IT[D.
SOVIET ENTERPRISES PARTICIPATE IN CONSTRIICTION
OF KUYBYSHEV, STALINGRAD, AND KAKHOVKA GES
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
1
site and scientific and technical groups were exploring the dam and reservoir
area.(1) It had been reported earlier that the Kuybyshev Engineex?ing and Con-
struction Institute imeni A. I. Mikoyan was setting up a laboratory fo: test-
ing construction materials on the site; a hydraulic laboratory for testing ac-
tual models of the dam was also being set up.(2) Laboratories of the "Gidro-
proyekt" have built a model of the proSected Kuybyshev GES 1340 actual size,
which, even at this reduced size occupied 600 square meters.(3) It was an-
nounced on 15 November that the All-Union "Teploelektroproyekt" Trust mean-
while had explored the projected route of electric transmission lines Prom
Kuybyshev GES to Moscow and was then exploring the projected transmission line
route from Stalingrad GES to Moscow.(4) At the Kuybyshev construction site,
prefabricated houses had arrived, and the workers' villages were well under
way.(5)
As reported by I. V. Komzin, chief of "Kuybyshevgidrostroy" through a
press correspondent on 5 November, most of the exploratory work on the Kuy-
byshev construction site has been completed.(6)
In addition to the drilling and exploratory work being done at the site
of the Stalingrad GES, much work of an exploratory nature was being done in
Astrakhan' Oblast. The Union office of the "Lenvodproyekt" sent an expedi-
tion of Leningrad specialists into the oblast to work on problems connected
with this immense area which will be irrigated by the Stalingrad GES. Hy-
draulic technicians, geologists, topographers, and soil scientists were among
those scientists included in the expedition. The "Lenvodproyekt" maintained
close contact with the Academy of Sciences' Committee for Cooperating With
the New Hydroelectric Stations, Canals, and Irrigation Systems.(7)
A large group of engineers and technical workers of Dneprostroy under
direction of Medvedev, Dneprostroy chief engineer, did exploratory work in
the region of the projected Kakhovka GES to determine the dam site. Prob-
lems concerninP railroad sidings and bringing in electric transmission lines
from DneproGES were also aired.(8)
The All-Union "Gidroenergoproyekt" and its Leningrad and Ukraine divisions
were reported active in the Kakhovka area. According to the same report, they
are to complete in 2 or 3 months exploratory work which would ordinarily take
2 or 3 years.(9)
Geologists and hydraulic engineers from the Ukraine division of the "Gidro-
energoproyekt" were exploring the banks of the Dnepr near the site of the pro-
jected hydroelectric center and test drilling there was being conducted on a three-
shift basis.(10) However, all preliminary geological, hydrological gad topograph-
ical work in the area from the village of Kozatskoye to Lyubimovka wen reported
completed on 29 September.(11)
The "Ukrvodproyekt" Trust has sent out three expeditions along the projected
route of the South Uk-sine and North Crimean Canals. They are to stud;/ geologi-
cal conditions and define the course of the canals.(12) It was reported on 5 No-
vember that five exploratory expeditions and four drilling units were already work-
ing along the canals.(13)
More space than usual was devoted to advertisements requesting technical per-
sonnel for the projects. Among those requested were hydraulic Engineers and tech-
nicians, industrial and civil engineers and technicians, autc~notive and construc-
tion engineers and technicians, power engineers and technicians, economists, plan-
ners, and accountants. Nontechnical personnel apparently are recruited mainly
from kolkhozes. Over 4,000 voluntary workers from the kolkhozes of Kuybyshev
Oblast (14), including 1,000 from 30 of 40 kolkhozes in Stavropol'skiy Rayon
have been sent to the Kuybyshev GES to build a paved road to the construction
srea.(l~S In adP~tioa, this r?yon .,..nt over 200 drivers and tractor cpcratc~~
..,
(15); 1,000 voluntarry workers from Ulyanovsk Oblast also took part in the con-
struction.(14)
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
sE~R~T
set by their neighbors and their members were engaged in building a railroad
to the construction site.(15) This railroad was reported completed on 5 Fo-
vember 1950.(6) Many other kolkhozes furnished workers or expressed their
desire to do so. Fifteen thousand young kolkhoz workers of Rovao Obleat in-
dicated their desire to work on the Kakhovka GFS and South Ukraine Canal pro~-
ects. Komsomol organizations were also very active in recruiting workers.(17)
earmarked for the Volga and Dnepr GESs might be delivered to other,
was within the yearly norms or not.
interesting speculation as to whether the work on GES material
metallurgical, machiilery, construction material, and other
plants responded?to the nation-wide drive to contribute ma-
terials to these projects.
The following list names the Soviet industrial enterprises
wiai:.h have been reported as producing for the Volga and Dnepr
projects. It also gives an indication of the extent to which
Enterprise
Magnitogorsk Metallurgical
Combine
Dneprodzerzhinsk Metallurgical
Plant imeni Dzerzhinsk
Uzbek Metallurgical Plant in
Begovat
Kuznetsk Metallurgical Combine
Zaporozh'ye Zaporozhstal' Metal-,
lurgic~.l Plant
Azovstal' Metallurgical Pant
in Zhdanov
Remarks
Shipped thousands of tons of rolled iron
and steel to Volga projects.(18)
Shipped first consignment of rolled iron
to Kuybyshev GES by 27 September.(19)
Shipped rolled iron to Volga GES.(20)
Shipped consignment of steel girders to
Stalingrad GES and filled an order
the Volga GES:(21)
Received order for 460 tons of sheet
steel which will be used in the
fabrication of Freight loading ma-
~chines for Kuybyshev GES.(22)
Producing steel girders for Volgs GES
projects to be shipred in September.(33)
Fhipped consignment of rails to Kuyby-
shev GES.(24)
Produced hundreds of tons of rail fastea-
inge for Kuybyshev GES ahead, of sched-
ule.(24)
Shipped narrow-gauge rails for use in con-
struction of Stalingrad ~:ES.(25)
Sanitized Copy Approved for Release 2011/09/14 .CIA-RDP80-00809A000600380104-4
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
Enterprise
Novo-Tagil Metallurgical Plant
Nlzhne-Tagil Metallurgical Plant
imeni Kuybyshev
Moscow "Serp i Molot"
Metallurgical Plant
Makeyevka Pipe Plant imeni
Kuybyshev
~? Odessa Cable Ylant
Leningrad Krasnyy Pyborzhets
Plant
Slavyansk Insulator and Fixtures
Plant imeni Artem
Riga Electric Machine Plant of
"Glavsel'elektro"
Sverdlovsk "IIralelektroapparat"
Plant
SE~REI
Completed order Yor special girders for
Volga GES.(26) Rolling mills will
deliver rails, girders, and beams to
Volga pro3ects.(23)
Shipped 2 carloads of roofing tin to a
Volga GES.(23)
Will produce rails, girders, and beams
for Volga pro~ects.(23)
Shipped large quantities of round and cor-
ner iron to "Kuybyshevgidrostroy."(21)
Shipped 3 tons of a 7-ton order of steel
cable for freight-lifting machines for
Kuybyshev GES.(27)
Shipped band, circular, and mill saws to
Volga construction pro3ects ahead of
schedule.(21)
Producing pipe for Kuybyshev GES.(8)
Shipped 75 tons of driving pipe to Kuy-
byshev GES on 18 September, 3 days
ahead of schedule.(28)
Shipped excavator cable, high-voltage
cable, and other material to Volga
GES.(29)
Producing steel cable for construction
of Kuybyshev GES.(3O)
Shipped condenser tubing, copper strips,
and rolled nonferrous metals to Len-
ingrad enterprises which are produc-
ing for nev GES pro~ects.(31)
The wire drawing and pressing 'shops re-
ceived an order from Kuybyshev GES
for telegraph wire and nails.(32)
Will make models of meth fixtures, in-
sulators, an3 special appliances for
Volga GES.(33)
Will supply electrical fixtures to thou-
s5,nds of kolkhozes which will receive
electric power from Volga end Dnepr
rivers.(3~)
Completed an order from Kuybyshev GES
for 2 large oil circuit-breakere.(35)
Will make excavating pumps, electric
motors.(36)
. - ~ -
SECRET
SEcRF~
- ~. .
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
7
3ECRE~'
Remarks
Produced 4 experimental sets of equipment.
for super powerful walking-drag-line
excavators for Kuybyshev and Stalin-
grad GES.(37) Will eventually make
electric equipment for controlling
the giant sluices and other equipment
for the new proJects.(38)
Moscow "Dinamo" Plant imeni
Kirov
Leningrad Proletariya Insulation
Plant
Cheboksary Electrical Equipment
Plant ,
Moscow Transformer Plant imeni
Kuybyshev
Yerevan Electric-Machine Building
Plant
Leningrad Metal Plant imeni
Stalin
Leningrad "Elektrosila" Plant
imeni Kirov
Kharkov Turbogenerator Plant
imeni Kirov
Barachinak Electric Machine
Plant imeni Kalinin
Experimented with porcelain for super-
high-voltage dischargers and circuit
breakers.(39)
D:aking various equipment for Volga GES.(41)
~.
Producing water-measuring apparatus for
Kuybyshev GES. Has already filled an
order for 6 rotary vanes, ~+ bathometers,
and 3 depth gages.(~+2)
Shipped first order of electric measuring
instruments to Stalingrad GES.(26)y
Received order from Kuybyshev GES for?'
power transformers with capacity of
over 100,000 kva-(~+3)
Shipped first consignment of transformers
to Kuybyshev GES.(!F4)
Will produce powerful hydroturbines for r
Stalingrad and Kuybyshev GES.(46)
Working on draft for superpowerful hy-
drogenerators for Volga GES. Gen-
erator division pledged to complete
rough draft of a i;eavy generator bear-
ing for the Kuybyshev GES by 7 Octo-
ber.(47) Completed 2 do motors 6
days ahead of time.(26) One shop is
to profiuce 2 do motors in December.(32)
Producing turbogenerators for construc-
tion of Volga GES; first machines will
be ready in October.(49)
Producing *ydroturbines, turbine pumps,
compressors, and other electrical
equipment for Volga GES.(50)
Completed the first 3 electric units for
excavators to be sent to Vohs GES.(2)
Filled Stalingrad GES order for electric
motors up to 100-kw capacity before
1 October beside completing ite basic
Flan-(51) Sent first _onY; ant ^f
_o..m.
electric motors to Stalingrad GES.(52)
Complet^d order for electric motors for
Kuybyshev GES ahead of schedule.(53)
SECRET
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
1
SECR~~
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
Tambov Revolyutsionyy Trod
Plant
Zagorozh'ye International Metal
Products Plant
Novo-Kramatorsk Machine Building
Plant imeni Stalin
Tyumen' Construction Machinery
Plant
Voronezh Excavator Plant imeni
Komintern
Shipped portable electric power plants,
motors, and rail cutters to Volga
pro~ects.(38)
Shipped 25 1~ of cable to Kuybyshev GES.
To make 70 km of cable in ~1th quarter
1950.(22) '
Shipped first consignment of control
cable'to Volga GES.(54)
Shipped 18 km of wiring and 8 oil cir-
cuit breakers to Stalingrad GES; re-
ceived order from Stalingrad GES for
18 drums of cable.(55)
Producing cable for Kuybyshev and Stalin-
grad GES. Completed its first order
for "Kuybyshevgidroetroy" for quarter.(19)
Shipped cable and other equipment to Volga
GES.(56)
Received order for hundreds of tons of
steel castings for turbines for Volga
GES projects; weight of each casting
is to exceed 200 tons.(57) Is making
drilling tools for Volga GES; some
augers weighing 1 ton and extending
3 meters in length have already been
forged.(58) Completed testing a 15-
cu m superpowerful excavator powered
by kj electric motors; this machine
will be sent to Volga construction
sites. Ten 4-cu m wallsing drag line
excavators have already been sent to
Stalingrad pro~ect.(59)
Shipped first consignment of construc-
tion machines to Kuybyshev GES con-
struction site.(60)
Produced 2 excavators above plan and
shiFrrd one each to Kuybyshev and
Stalingrad GES.(61)
Shipped first 3 of an order for ex-
cavators to new hydroelectric pro~-
ects.(~5)
Shipped 8 "Leninets" belt conveyers to
Kuybyshev GES on 8 September and will
complete order on 9 September.(58)
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
Kharkov Stroymashina Plant
Kharkov Krasnyy Oktrabr' Plant
Kharkov Elektroinstrument Plant
Plants of "Yuzhstroymekhan-
izataiya" (Southern Con-
struction Machinery Truat)
ftovocherkassk Plant imeni
ftikol'skiy
Chelyabinsk Road Building Ma-
chinery Ylant imeni xoly-
ushchenko
Ufa Telephone Equipment Plant
Molotov Telephone Plant
Shcherbakov Road-Building
Machinery Plant
Bryansk Road-Building Machlnery
Plant
Vil't~yus State Machinery Plant
Odessa Plant imeni Yanvarskoye
Voataniye
Grsk Construction Machinery
Plant
ftovosibirsk Construction
Machinery Plant
SF~REj
Developing for Volga projects powerful
tractor-drawn scrapers which will be
5 times more productive than bull-
dozers and cranes.(62)
Shipped scrapers, conveyers, autocranes,
aggregates for making slag bricks, and
other machines to Volga GES pro3ects.(62)
Will ship 10 scraper loaders for Kuybyshev
GES by beginning of October.(63)
Already shipped 3 large bulldozers and one
a ^~~ ~~~~ Produci^~
new order for diesel-powered excavating
machines.(21)
Shipped first telephone exchange of 100
telephones to Stalingrad GES and readied
first shipment of telephone equipment.(65)
Producing telephone equipment for Stalin-
grad GES.(66)
Shipped first order of telephones to Stalin-
grad GES construction site.(, 63)
Shipped first consignment of power-driven
rollers to "Stalingradgidroatroy" and
'~Kuyby~hevgidrostroy."(67)
Received order for graders and automatic
loaders from Volga GES, to be shipped
in 4th quarter 1950.(68)
Pledged to make 250 hoists Yor Volga G&S
projects; 30 of these will be made
this year.(69)
Shipped to Kuybyshev GES; an automatic
crane Yor loading and unloading work;
other cranes in production.(70)
'1
Shipped before 10 October the YYzst 2 of
an order for hoists to Stalingrad GES.(7~
Completed its postwar Five-Year Plan; now
making hoists for Kuybyshev GES.(72)
Shipped a consignment of large hoists to
the Kuybyshev GES.(73) Shipped second
group of heavy hoists to Volga GES.(20)
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
SECRET
Enterprise Remarks
Sverdlovsk Uralmas3 Plant imeni Shipped 2 superpowerful waL'~ing excavators
S. Ordzhonikidze to Volga GES; 2 more machines will be
sent in mid-September.(18)
Chelyabinsk Tractor Plant Shipped over 100."Stalinets 80" caterpillar
bulldozers to Volga GES.(18)
Tuapse Machinery Plant Pledged to produce 2 large floating pile
drivers above plan for Volga GES pro~-
ects.(67)
Korosten' Oktryabr'skays Pledged to have experimental machines for
Kuznitsa Road-Machinery the new hydroelectric and irrigation
Constr~!ction Plant coal pro~eGts ready for testing by
7 November. ('i~)
Kharkov Road-Machinery Plant Shipped a load of tractor trailers to Kuy-
Kutaisi "Gornyak" Machiae-
Building Plant
byshev GES.(26)
Shipped first consignment of "ATN-10"
artesian turbine pampa to Stali~3rad
GES.(75) The pumps will: be able to
lift water from a depth of 80 meters.(63)
Novosibirsk Burovaya Tekpnika Started assembly of water-lifting units
Plant for Kuybyshev GES; these units will
be able to lift subsurface water 100
meters.(76)
Chelyabinsk Machinery Plant Produced 4 excavation pumps end 5 float-
of Ministry of Electric ing cranes above plan for Volga GES;
Power Stations USSR began production of new machines,
large excavation pumps, railroad and
automotive lifting cranes.(77)
Moscow Pump Plant imeni M. I. Shipped first order of large excavation
Kalinin pampa to Volga GES pro~ects.(78)
Moscow Rostokinskiy Construe- Producing for Volga GES concrete pumps
tioa Machinery Plant and vibrator feeders which will lower
concrete into 15-18 meter trenches.(79)
Pumps will handle 2G cu m per hour.(78)
Sverdlovsk Ural Chemical Machine [dill produce electric excavation pampa
Building Plant for Volga GES projects; pumps will
handle nearly 1,000 cu m of earth per
hour.(80)
Leningrad Ekonomayzer Plant Produced a month ahead of schedules 5th
turbopump for Stalingrad GES; working
on 5 more such machines for Stalingrad
GES.(81)
Kataysk Pump and Compressor Producing portable compressors icr Volga
Plant GES; 11 machines will be shipped by
1 October.(82)
Alma-Ata Beavy Machine Buiid- iv produce drilling machines for Stelin-
ing Plc.nt grad and Kuybyshev GES.(25)
SECRF.l
Sanitized Copy Approved for Releas ,~~ --- - `?nM
e 2011/09/14 :CIA-RC
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
Tula Boiler and Ventilator
Plant
Kalingrad Railroad Car Building
Plant
Voroshilovgrad Locomotive Con-
struction Plant imeni Oktyabr'-
skaye,Revolyutsiya
Tbilisi Machine-Tool Plant
imeni Kirov
Leningrad Machine Tool Plant
imeni Sverdlov
Kharkov Machine Tool Plant imeni
Molotov
Berislav Machine Plant (Kherson
Oblast)
Leningrad Znafgya Trudy Machine
Plant
Gomel' Machine-Tool Plant imeni
Kirov
Yerevan "Avtodetal'" Plant
Moscow Automobile Plant imeni
Stalin
s?ECREr
Received an order to make stationary
asphalt boilers for Volga GFS.(83)
Shipped 4 heating boilers to Kuyby-
shev GES and pledged to produce 10
boilers and ventilators above plan by
7 November.(84)
Producing all-metal self-dumping cars
Yor "Kuybyahevgidrostroy"; several
tens of cars have been sent to Volga
^~ES pro,~ects.(85)
Received order to make 4 "SO" locomo-
tives for Volga GES.(86)
Shipped first order of thread-cutting
machines to "Kuybyshevgidre3troy."(87)
Shipped orders for taps, dies, and cutteis
to Kuybyshev and Stalingrad GES con-
struction pro,jects.(88)
Producing machine tools for Kuybyshev
GrS.(89) Shipped a "DIP-3M" lathe
to gonstruction site on 12 September.(90)
Completed assembly of universal boring-
mnchiac tools which are destined for
the Leningrad Metal Plant imeni Stalin
and will be used for boring turbine
parts for Volga pro~ects.(91)
Produced 2 grinding machines for "Kuyby-
. shevgidrostroy."(92)
Produced drilling points, pipe threaders,
and other instruments for Kakhovka
GES construction pro~ect.(19)
To produce various equipment for assem-
b11ng steam pipes in Volga construc-
tion pro~ects.(93)
Producing for the new hydroelectric
pro~ects.(6)
,S1Mpped 3,030 units of 8 truck peu"ts to
Kuybyshev GETS on 20 October.? Sent
Stalingrad GF5 4,032 units of 10 parts.(94)
Shipped 15 trucks, part of an order for 125
vehicles, to "Stalingradgidrostroy."(37)
Shipped a large order of ZIS-150 trucks
to Kuybyshev GE;S on 5 Oatober.(95)
Producing automobile tires for Volga con-
struction pro,~ects.(2)
-9-
sscRET
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
SECRET
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
SECRET
Enterprise
Stalingrad Tractor Plant
Leningrad "Russkiy Dizel"
Plant
Gor'kiy Autombile Plant imeni
Molotov
Stalingrad "itrasnyy Metallist"
Plant '
Plants of "Stroitel"' Combine
of Kazan' and the "Volgo-
prom~" Krasnyy Izvestnyak"
and "Volzhskiy Gormyak" in-
dustrial artels
Gor'kiy Glass Plant imeni Gor'kiy
Murom Ruberoid Plant
Novorossiysk "Kommunar"
Slate Plant
Sebryakov Cement Plant
Riga Wood Block Factory
Bologovo "Kuznets" Industrial
Artel
Volgoda "Severnyy Kommunar" Plant
Kaunas Woodworking Combine
Vitebsk House Construction
Combine '~-
Letnerechensk Prefabricated House
Plant
Remarks
Pledged to produce tens of diesel trac-
tors above plan, to build and equip
2 portable repair shops, to produce
50 tons of forged pieces and 50 tons
of castings, and to train a considera-
ble number of operators, electricians,
and workers of various specialties for
"Sta,lingradgidrostroy."(95)
Will make diesel motors for Sebryakov Ce-
ment Plant which makes cement for
Stalingrad GES.(38)
Started shipping trucks, vehicles to Volga
GES.(97)
Pledged to give 100 tons of steel castings
to Stalingrad pro~ects.(95)
Producing bric'xs, tvGi tile, and high-
quality lime for Kuybyshev GES. Eight
barges with construction gipsum, lime
and bricks already have been shipped.(25)
Shipped 15,000 sq m of glass to Kuybyshev
GES; remainder of order for glass will
be shipped on 16 September.{64)
Filling order for 10,000 rolls. of roofing
mate_ials for the new construction pro~-
ects.l,20)
Shipped first consignment of slate to Kuy-
byshev GES.(98)
Will produce cement for Stalingrad GES.(38)
Shipped second consignment of carpentry
tools (15,000) to Stalingrad and Kuyby-
shev GES.(98)
Shipped the 'first 20,000 industrial fasten-
ings (stroytek'nykh skob) of an order for
100,000 to the Kuybyshev.(100)
Produced s8w frames for Kuybyshev GES.(26)
Shipped first order of prefabricated houses
to Kuybyshev GES.(101)
Shipped prefabricated. houses to Kuybyshev
GES construction site.(6)
Shipped 5 eight-apartment buildings to Kuy-
byshev GES.(102)
Completed 30 mortising machines fdr'~Kuyby-
shevgidrostroy" on 28 October.l102)
' SECRET
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
. "'~
Enterprise
Gor'klesosplav Trust Delivered 675,000 cu m of lumber to Kuy-
byshev GES.f'9)
Kuybyshev Woodworking Combine Shipped 1,000 cu m of sawn lumber to con-
struction projects; at present working
on order for 5,000 sq ft of wood prod-
ucts such as doors, window frames,
etc.(5)
Udmurt ASSR
Kama Basin
SECRET
Shipped 250 tons of dry plaster to Kuy-
byshev GES on 27 October, another 250
tone on 28 October.(104)
Shipped more than 30 carloads of ties and
4 caravans of timber rafts to Kuybyshev
GES. Nearly 50,000 cu ft of lumber have
been sent to Stalingradgidrostroy."(105)
Shipped 28,000 cum of construction timber
and oaw iJ~o to Fu{yuyeiuev unS; anoiner
raft of 20,500 cu m will be sent at a
later date.(106)
Western Urals Sent 139,000 cu m of lumber to Kuybyshev
GES.(107)
1.
2.
3?
4.
5?
6.
7?
8.
9?
10.
11.
12.
13.
14.
15.
16.
17.
1P.
i9.
20.
21.
22.
23.
24.
25.
26.
27~
28.
- 11 -
SECRET
SECRET
Sanitized Copy Approved for Release 2011/09/14 :CIA-RDP80-00809A000600380104-4
Moscow Krasnaya Zvezda, 29 Sep 50
Yerevan, Kommunist, 23 .?