FAMILY DAY
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP89-00244R000701420004-9
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
2
Document Creation Date:
December 22, 2016
Document Release Date:
March 13, 2009
Sequence Number:
4
Case Number:
Publication Date:
April 9, 1984
Content Type:
MEMO
File:
Attachment | Size |
---|---|
CIA-RDP89-00244R000701420004-9.pdf | 70.51 KB |
Body:
Approved For Release 2009/03/13: CIA-RDP89-00244R000701420004-9
09 APR 1984
MEMORANDUM FOR: Deputy Chief, Space Maintenance & Facilities
Branch, LSD/OL
New Building Project Office, OL
SUBJECT: Family Day
1. Per your request concerning a New Building display for
Family Day, we need to have the following done:
a. Prints need to be made of the attached five slides
and dry mounted on 20"x30" foamcore.
b. The existing model located at Ames Building needs to
be relocated to Headquarters Building.
2. Attached is a copy of Mr. Fitzwater's memorandum for all
employees that was part of the last display. Please call me on
extension~if you need any additional assistance.
STAT
STAT
STAT
Attachments:
As Stated
STAT
Orig - Adse (w/atts)
1 - OL/NBPO (w/o atts)
Approved For Release 2009/03/13: CIA-RDP89-00244R000701420004-9
Approved For Release 2009/03/13: CIA-RDP89-00244R000701420004-9
ADt 1 STRATIVE - INTERNAL USE (' .. t -
3 NOV 1983
MEMORANDUM FOR: All Employees
FROM: Harry E. Fitzwater
Deputy Director for Administration
SUBJECT: New Headquarters Building
1. The renderings of the new building shown here reflect the
current design concepts as we move into the final design stages.
The building facade will be a tinted glass wall that is detailed
in a pattern that will echo the patterns of the existing
building. This produces a feeling of compatibility even though
the two structures are significantly different in form and
material. The base of the new building is composed of precast
concrete panels selected to closely match the base of the
existing building so that there is a strong unifying element
common to both buildings.
2. Entering the building from the west, employees will
transit a skylit entry hall that terminates on the fourth level
of the building at the atrium facing the courtyard. At this
level, there will be an impressive view of the courtyard and
existing building. The ground level of the atrium will look out
into the courtyard. This level is bein desi ned to contain
expanded emplo ee services such as the
3. Additional food service area will be provided by
expanding within the existing building around the existing
kitchen into areas vacated by components such as the Credit
Union. Tentative plans are to add variety as well as space in
the addition so that features such as the Rendevous Room can be
re-created.
4. The current schedule calls for start of construction in
the spring of 1984, rather than August as previously stated.
This schedule should result in beneficial occupancy beginning in
the summer of 1987.
STAT
STAT
ADMINISTRATIVE - INTERNAL USE ONLY