HEADQUARTERS OPERATIONS, MAINTENANCE AND ENGINEERING DIVISION, OL WEEKLY REPORT PERIOD ENDING 29 AUGUST 1984
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP87-00352R000100200006-0
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
5
Document Creation Date:
December 22, 2016
Document Release Date:
May 4, 2009
Sequence Number:
6
Case Number:
Publication Date:
August 29, 1984
Content Type:
REPORT
File:
Attachment | Size |
---|---|
CIA-RDP87-00352R000100200006-0.pdf | 228.52 KB |
Body:
Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0
STAT
HEADQUARTERS OPERATIONS, MAINTENANCE
AND ENGINEERING DIVISION, OL
WEEKLY REPORT PERIOD ENDING 29 AUGUST 1984
I. Progress Report on Tasks Assigned by DCI/DDCI:
No tasks assigned during this reporting period.
II. Items/Events of Major Interest:
a. H draulic Barricades: The steel posts and hydraulic
units have been installed at the Route 123 Entrance to the
Headquarters Compound, and the hydraulic units are in place at
the George Washington Memorial Parkway Entrance. Delta
Scientif-i,c Corporaton expects the barricades for the entrance
STAT to the(DIC garage to arrive this week.
b.- Drawings and Specifications: Drawings for
renovations to the Directorate of Science and Technology
Conference Room (6E60, Headquarters Building) were completed
and given to the Engineering and Construction Division (E$CB),
HOME/OL, for contracting.
\p. The specification package for the renovations to Room
,\\ 1H39, Headquarters Building, for the Office of Central
Reference are being prepared.
STAT
c. Transportation: Limousine service was provided to
the European Division from 23 through 26 August 1984.
d. Accident Report: On 15 August 1984, while delivering
STAT metal furniture up the stairs , the men lost
STAT their grip on a freshly waxed es s a result,
left leg was pinned against the steps by the desk. He
taken to Fairfax Hospital where he received five stitches in
his leg. He reported back to work on 27 August and is now
doing fine.
e. Carpet Tiles for Office of Soviet Analysis: On
24 August 1984 the carpet work was started in the offices in
! the 4E Corridor of Headquarters Building for SOVA.
I '' Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0
Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0
STAT
h. Backlog of Classified Trash: The Classified Disposal
Unit has a ac log o about pounds of "burn only"
classified trash. This figure includes the 7S bags that were
shipped from the National Photographic Interpretation Center
this week. Due to its size, the incinerator can burn only
about 250 to 275 pounds per hour.
i. Street Lighting. The contractor was contacted on
24 August 1 and asked to schedule the bushing repair work on
the Circuit #4 transformer within two weeks. The work on the
transformer will not interfere with construction by George
Hyman Construction Company.
j. Headquarters Compound Domestic Water Test: A test of
the domestic water system on the Headquarters Compound was
completed as scheduled on 22 August 1984 by representatives
from Smith, Hinchmann, and Grylls Associates, Inc. (SH$G),
Safety Staff, and EF,CB. The majority of the system was tested
as scheduled. However, an inaccessible valve precluded testing
of those sections running behind the cafeteria and around the
north end of the Headquarters Building. The test of these
sections will be completed by Safety Staff and E&CB upon
completion of corrective action on the valve by General
Services Administration (GSA).
SHjG indicated that preliminary test results
confirmed their earlier conclusions that the site domestic
water lines are restricted. Upon receipt of the final SH$G
report and conclusions, any corrective actions required will be
taken.
No site domestic water problems resulting from the
test were reported.
k. Office of Communication's Watch Office: A precon-
struction meeting for the new Office of Communications (OC)
/ Watch Office to be located in Room 1B39-43 area was held on
? , , Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0
Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0
27 August 1984. Representatives from E$CB, Security, and OC
were present. Under the current 120 calendar day construction
time from this area work is scheduled to be completed circa
12 December 1984. Once work in the area has been completed,
the new world map installation in this same area can begin.
The contractor is scheduled to begin demolition work on
Tuesday, 5 September 1984.
1. Northside Utilit Lines: GSA indicated that the
contractor responded to GSA's "slow cause" for terminaton of
the contract letter by claiming that the leakage problems being
experienced with the new underground chilled water lines were
not his fault and that further corrective actions would be
completed "under protest." However, according to GSA, the
contractor has begun excavation of the remaining underground
chilled water line joints to test for leads on an expedited
basis and, at this point, plans to uncover all remaining joints
if necessary. Additional leaks had been discovered the week of
20 August 1984.
m. Minor Work Orders: Cobb and del Castillo, Ltd., was
selected to survey 120 offices and design electrical
modifications for the Headquarters Building. The A-E support
was necessary to reduce the backlog of small work orders that
had reached 120 requests. Survey effort by Cobb and del
Castillo has been hampered by the unavailability of escort
services when needed.
An additonal 114 work order requests reached this
office after the A-E was tasked with the original 120.
n. Message Handling Facilities: Contract documents to
install a new electrical feeder in support of the Message
Np Handling Facilities in Room 1B27 were mailed on 24 August 1984
1 for contractors to bid on the modification project. Bid
opening date is scheduled for 13 September 1984 at 2:00 p.m.
o. Printing $ Photography Laserite, Gym HVAC, and ODP
Renovations: The construction contract for the installation of
the Li-s'erite Printer in the Printing $ Photography (P&P)
Building, the computer interfacing between Rooms GC03 and GE04,
0 and the installation of an air handling unit was awarded to BCM
/ Corporation. During the preconstruction meeting held on
f 15 August 1984, BCM representatives were made aware of the
urgency to connect the new Laserite Printer to preserve a
delicate part of the equipment that deteriorated while in
storage.
With the help of P&P personnel, the new Laserite
Printer was installed in its final psoition. A temporary
? , Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0
Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0
hookup of the equipment shall be completed by 30 August. This
temporary connection will preserve the operational integrity of
the new printer. All the work in support of the Laser Printers
is scheduled to be completed by 28 September 1984.
p. A-E for Design Support: The contract with Dicon has
been awarded and three engineers are on board to initiate work
toward the development of the facilities design specifications.
q. Replacement of VEPCO #4 Transformer: Work continues
to progress satisfactorily on the relacement of VEPCO #4 trans-
former, rated 84 MVA-230/34.5 kV. As per schedule, the failed
unit has been removed from the substation, and the replacement
/ transformer of the same rating is on the foundation and in the
process of assembly. As of this date, under favorable weather
conditions, most of the major components have been installed,
and barring catastrophic weather interference, the planned
service date of 7 September should be met.
r. Relocation of #1 Transformer: The work of moving and
reconnecting the #1 transformer, rate 3,750 kVA-13.s/4.16 kV
continues to go well. The transformer is on its new
\, foundation, and the present activity includes demolition of the
old foundation and tying new cable ducts into the remains of
the old ducts in preparation for recabling. Meeting the
13 September 1984 completion date is somewhat in doubt, but is
not impossible.
STAT
s. Renovations for return of SOVA:
4E Renovations: New construction is 85 percent
complete base on West Group's work only. Upon receipt of the
contract from the legal staff, it will be forwarded to the
contractor for signature. The expected completion date (West
Group only) has slipped from 29 August 1984 to 7 September 1984.
SE Renovations: The contractor is continuing
demolition as space becomes available. Upon receipt of the
contract from legal staff, it will be forwarded to the
contractor for signature.
t. Other Renovations at Headquarters: The GSA Electric
comp a e.
Shop worked overtime t is past weekend to install critical
power for the security alarm syqtam i Room 1E4846 for the
This project is now
I f, Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0
Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0
The removal of all ceiling lights, ceiling tiles and
grid, along with the removal of the ductwork in Room GE13 for
the Office of Communications has been delayed because GSA
management refused the Agency's request for ovetime for the
necessary shops to perform the tasks.
The GSA Electric Shop completed their portion of
renovations in Room GG10 for the Career Management Staff, DO.
The Carpenter Shop is waiting for the go-ahead from GSA or CMS
to proceed.
III. Significant Events Anticipated During the Coming Week:
No significant events antici.nated at this time
Headquarters Operations, Maintenance
and Engineering Division, OL
Approved For Release 2009/05/04: CIA-RDP87-00352R000100200006-0