COST ESTIMATE FOR (Sanitized)
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP86-00800R000100240024-6
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
1
Document Creation Date:
December 12, 2016
Document Release Date:
August 31, 2001
Sequence Number:
24
Case Number:
Content Type:
LIST
File:
Attachment | Size |
---|---|
![]() | 21.76 KB |
Body:
Approved For Release 2002/01/08 : CIA-RDP86-00800 000100240024-6
STATINTL
Office addition, 5,200 SF
$250,000
Miscelleaeous renovations in Bldg.
6,000
STATINTL
'Vault
15,000
Parking area, curbing, & road-
4,000
Contingency, 10%
27,500
Construction cost less OH & P & A-E
$302,500
.$302,500
Mech. work in Room #21, chilled
water systems, and IIVAC mod.
192,000
Contingency & miscellaneous, 20%
38,000
Construction cost less OH ~, P ~ A-E
$230,000
$230,000
532,500
OH ~ P C25%)
133,000
Total estimated construction cost
less A-E
$665,500
A-E fee plus Title II
53,000
Total cost of project
$718,500
Say $720,000
Approved For Release 2002/01/08 : CIA-RDP86-0080OR000100240024-6