NPIC DATA SYSTEM DATA AND CONTROL SEGMENT ACQUISITION PHASE APPENDIX C3 WBS DICTIONARY
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP84T00037R000300060001-2
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
120
Document Creation Date:
December 28, 2016
Document Release Date:
July 5, 2007
Sequence Number:
1
Case Number:
Publication Date:
March 31, 1982
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 4.3 MB |
Body:
Approved For Release 20077//007//0055: CIA-RDP84T00037R000300060001-2
/ e(I d
NPIC DATA SYSTEM
DATA AND CONTROL SEGMENT
ACQUISITION PHASE
APPENDIX C3
WBS DICTIONARY
STAT
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
NPIC DATA SYSTEM
DATA AND CONTROL SEGMENT
ACQUISITION PHASE
APPENDIX C3
WBS DICTIONARY
STAT
?
STAT
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
V
WBS
TITLE
Project Management
plus senior level managers for
Provide Project Management
Including NDPO Interface
Provide Project Management
Including NDPO Interface
Provide Project Management
Including NDPO Interface
Monitor, Control and Report
Schedule Status
Includes project management for BOC. This
covers: Project Manager, Deputy Project
Manager and Program Control Manager. It
also includes related administrative/
secretarial support.
Identical to 641100, except this element
covers the FOC phase.
Identical to 641100 except this element
covers the IOC phase.
Covers project control to monitor/control/
report schedule status through BOC. Includes
preparation of CDRL's 101, 103, 107, 110, 111,
113, 114. This element also includes Facility
Planning Support and Data Management for Pro-
ject Control Office and general administrative
support.
Monitor, Control and Report
Schedule Status
WBS
DESCRIPTION
This category includes the project manager
Identical to 641200, except this element covers
the IOC phase.
641202 4.1.2 Monitor, Control and Report
Schedule Status
Identical to 641200, except this element covers
for FOL phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
V
WBS
TITLE
Monitor, Control and Report
Cost Status
Monitor, Control and Report
Cost Status
Monitor, Control and Report
Cost Status
Provide Quality Assurance
Plan
Implement Software Quality
Assurance
Implement Software Quality
Assurance
Implement Software Quality
Assurance
WBS
DESCRIPTION
?
This includes the effort to structure the
contract consistent with 7000.2 require-
ments, program control reviews, monitoring
of subcontracts and overall cost monitor-
ing. This element covers the BOC phase
and preparation of CDRL Items #102 and #109.
Identical to 641203, except this element
covers the IOC phase and preparation of
CDRL #109 only.
Identical to 641203, except this element
covers the FOC phase and preparation of
CDRL #109 only.
Covers the production of the Quality
Assurance Plan (CDRL #108).
This effort includes: QA program management;
document inspection, design, development,
and testing monitoring and control; correc-
tive action monitoring; configuration
assurance; design/code inspections monitor-
ing; and contract adherance. This element
covers the BOC phase.
Identical to 641301, except this element
covers the IOC phase.
Identical to 641301, except this element
covers the FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
0
w
S
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Implement Hardware Quality
Assurance
Implement Hardware Quality
Assurance
WBS
DESCRIPTION
This effort includes: participation in all
reviews (PDR, CDR, etc.), CDRL review and
approval; inspection plan preparation;
procurement support; CCB participation;
coordination with Data Processing Division
on ADPE equipment; safety inspection
coordination; and QA program management.
This element covers the BOC phase.
Identical to 641304, except this element
covers the IOC phase.
641307 4.1.3
Implement Hardware Quality
Assurance
Monitor Subcontractor
Quality Assurance
Monitor Subcontractor
Quality Assurance
Identical to 641304, except this element
covers the FOC phase.
This covers the monitoring subcontractor
Quality Assurance Plan and Program. This
includes monitoring and auditing of the
subcontractors QA program implementation
including periodical visits and review of
all work products. This element also,
covers as required assistance to the sub-
contractor in QA matters. This element
covers the BOC phase.
Identical to 641307, except this element
covers the IOC phase.
Monitor Subcontractor
Quality Assurance
Identical to 641307, except this element
covers the FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
Provide QA Audit Reports
Provide QA Audit Reports
Provide QA Audit Reports
Prepare and Maintain CM
Plan and Procedures and
Documentation
Prepare and Maintain
Engineering Change Notices/
Request and Other CM
Related Documents
Prepare and Maintain
Engineering Change Notices/
Request and Other CM
Related Documents
Prepare and Maintain
Engineering Change Notices/
Request and Other CM
Related Documents
?
WBS
DESCRIPTION
This element covers the preparation of the
QA Audit Reports (CDRL #149) during the BOC
phase. Does not include typist and tech-
nical publications effort associated with
these reports.
Identical to 641310, except this element
covers the IOC phase.
Identical to 641310, except this element
covers the FOC phase.
This element includes the preparation of the
Configuration Management Plan (CDRL #106).
It also includes the administration and
supervision of CM activities including
coordination with subcontractors and the
NDPO. This element covers the BOC phase.
This element includes the preparation and
processing of all change documents (e.g.
ECP/ECN/SCN/ECO/etc.) during the BOC phase.
Identical to 641401, except this element
covers the IOC phase.
Identical to 641401, except this element
covers the FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
w
?
IBM
WBS NO.
RFP
WBS NO.
UI
641408 4.1.4
WBS
TITLE
Perform CM Audits
Perform CM Audits
Provide Master Product
and Document Control
Provide Master Product
and Document Control
Provide Master Product
and Document Control
Prepare and Maintain
Software Version Descrip-
tion Document
Prepare and Maintain
Software Version Descrip-
tion Document
Prepare and Maintain
Software Version Descrip-
tion Document
WBS
DESCRIPTION
This element includes the preparation and
support to functional and physical con-
figuration audits during the BOC phase.
Identical to 641404, except this element
covers the IOC phase.
Identical to 641404, except this element
covers the FOC phase.
This includes the CM library activity in
maintaining baseline products, specifica-
tions, and the processing and distribution
of SCN during the BOC phase.
Identical to 641407, except this element
covers the IOC phase.
Identical to 641407, except this element
covers the FOC phase.
This includes the preparation and mainte-
nance of the software version Description
Document (CDRL #152) during the BOC phase.
Identical to 641410, except this element
covers the IOC phase.
Identical to 641410, except this element
covers the FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
w
?
IBM
WBS NO.
RFP
WBS NO.
rn
641417 4.1.4
WBS
TITLE
Administer the Contractor
CCB
Administer the Contractor
CCB
Administer the Contractor
CCB
Provide Change Status
Accounting
Provide Change Status
Accounting
Provide Change Status
Accounting
Prepare Project Security
Plan and Security Procedures
Implement Security
Procedures
WBS
DESCRIPTION
This element includes the administration of
Project Configuration Control Board. This
effort includes preparation of agendas,
minutes, etc. for the BOC phase.
Identical to 641413, except this element
covers the IOC phase.
Identical to 641413, except this element
covers the FOC phase.
This element covers the processing of the
monthly system accounting for ECP and
baseline management during the BOC phase.
Identical to 641416, except this element
covers the IOC phase.
Identical to 641416, except this element
covers the FOC phase.
Covers the preparation of the Security Plan
(CDRL #105) during the BOC phase.
This element covers the implementation and
monitoring of special security requirements
mandated by the Government. This includes:
document control, clearance, physical
security, personnel briefings, visitor
control, computer security, etc. This
element covers the BOC phase.
Implement Security
Procedures
Identical to 641501, except this element
covers the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
Implement Security
Procedures
Provide Monthly Status
Reviews
Provide Monthly Status
Reviews
Provide Monthly Status
Reviews
Provide Management Control
and Visibility to Cost
Schedule
Provide Management Control
and Visibility to Cost
Provide Management Control
and Visibility to Cost
Provide Management, Control
and Visibility to Cost
Schedule
Provide Management, Control
and Visibility to Cost
Schedule
WBS
DESCRIPTION
Identical to 641501, except this element
covers the FOC phase.
Coordination and preparation of monthly
Status Reviews (CDRL #112) during the BOC
phase.
Identical to 641600, except this element
covers the IOC phase.
Identical to 641600, except this element
covers the FOC phase.
This covers the subcontract management
coordination of
during the BOC phase.
Identical to 641700, except this element
covers the IOC phase.
Identical to 641700, except this element
covers the FOC phase.
This covers the subcontract management
coordination of the during the
BOC phase.
Identical to 641703, except this element
covers the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
STAT
STAT
SIAI
STAT
STAT
STAT
STAT
STAT
?
IBM
WBS NO.
RFP
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
Provide Management, Control
and Visibility to Cost
Schedule
Provide Management, Control
and Visibility to Cost
Schedule of
Provide Management, Control
and Visibility to Cost
Provide Management, Control
and Visibility to Cost
STAT
STAT
STAT
STAT
STAT
STAT
Provide Publication, Main-
tenance and Control of All
Project Documentation
Provide Publication, Main-
tenance and Control of All
Project Documentation
Provide Publication, Main-
tenance and Control of All
Project Documentation
WBS
DESCRIPTION
Identical to 641703, except this element
covers the FOC phase.
This covers the subcontract management
coordination of
during the BOC p~.
Identical to 641706, except this element
covers the IOC phase.
Identical to 641706, except this element
covers the FOC phase.
?
This covers the publication, maintenance and
control of all project documents including
the Accession List (CDRL #156) and PDR, CDR,
and quarterly review during the BOC phase.
This covers the publication, maintenance and
control of all project documents including
the Accession List (CDRL #156) and CDR and
quarterly reviews during the IOC phase.
This covers the publication, maintenance and
control of all project documents including
the Accession List (CDRL #156) and CDR and
quarterly reviews during the FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
Prepare and Administer
Document Management Plan
System Engineering
Provide Technical Manage-
ment of Project
Provide Technical Manage-
ment of Project
Provide Technical Manage-
ment of Project
Provide/Enforce Software-
Opns-Hardware Interface
Standards
Provide/Enforce Software-
Opns-Hardware Interface
Standards
WBS
DESCRIPTION
?
This covers the preparation and administra-
tive of the Document Management Plan during
the BOC phase.
This category includes system level engineers
and programmer analysts engaged in: system
engineering management, analysis, operations
engineering and development, design, transi-
tion and integration planning and support,
test support, CM support and technical
reviews.
This covers the technical management of the
system engineering effort by a senior level
manager during the BOC phase. Administra-
tive support is included.
Identical to 642100, except this element
covers the IOC phase.
Identical to 642100, except this element
covers the FOC phase.
This covers the preparation and administra-
tion of standards to control interface
designs between SW, Opr and HW elements
(CDRL #118). Preparation follows parent
document developed by SI. This element
covers the BOC phase.
Identical to 642103, except this element
covers the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Provide/Enforce Software-
Opns-Hardware Interface
Standards
Prepare Segment Development
Plan
Provide Requirements
Analysis and Traceability
Provide Requirements
Analysis and Traceability
Provide Requirements
Analysis and Traceability
Provide Performance
Analysis
Provide Performance
Analysis
WBS
DESCRIPTION
Identical to 642103, except this element
covers the FOC phase.
This covers the development and preparation
of the Segment Development Plan (CDRL #104)
during the BOC phase.
This covers the development and preparation
of the Requirements Traceability and Verifi-
cation Matrix (CDRL #119) during the BOC
phase.
Identical to 642200, except this element
covers the IOC phase.
Identical to 642200, except this element
covers the FOC phase.
This covers the technical performance
measurement activities and the relevant
document (CDRL #155) during the BOC phase.
Identical to 642203, except this element
covers the IOC phase.
Provide Performance
Analysis
Provide RMA Analysis
Identical to 642203, except this element
covers the FOC phase.
Covers reliability/maintainability/
availability analysis, preparation of inputs
to PDR, CDR documents, review of subcon-
tractor RMA analysis. This element covers
the BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/0 5: Cl
A-RDP84T00037R000300060001-2
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Provide RMA Analysis
Provide RMA Analysis
Prepare Segment Design
Analysis Report
Prepare Segment Design
Analysis Report
Prepare Segment Design
Analysis Report
Accomplish Trade Studies
Accomplish Trade Studies
Accomplish Trade Studies
Provide Engineering
Specialties
Provide Support to
Intersegment Interface
Definition and Require-
ments Determination
WBS
DESCRIPTION
This element repeats the activities of
642206 and includes review of RMA pre-
dictions for possible changes. This
element covers the IOC phase.
Identical to 642207, except this element
covers the FOC phase.
This covers the development and preparation
of the Segment Design Analysis Report (CDRL
#122) during the BOC phase.
Identical to 642209, except this element
covers the IOC phase.
Identical to 642209, except this element
covers the FOC phase.
This covers the performance of trade studies
during the BOC phase.
Identical to 642212, except this element
covers the IOC phase.
Identical to 642212, except this element
covers the FOC phase.
Provides for engineers engaged in integrated
logistics support and human factors design
during the BOC phase.
This covers the development of interface
control specifications and participation in
the Interface Control Working Group (ICWG)
to assure compatability between the D/C
Segment, other segments and external inter-
faces during the BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Provide Support to
Intersegment Interface
Definition and Require-
ments Determination
Provide Support to
Intersegment Interface
Definition and Require-
ments Determination
Prepare Engineering
Technical Notes
Prepar Engineering
Technical Notes
Prepar Engineering
Technical Notes
Develop Segment Operation,
Concepts, Procedures, and
Specifications, Including
Human Factors Engineering
WBS
DESCRIPTION
Identical to 642218, except this element
covers the IOC phase.
Identical to 642218, except this element
covers the FOC phase.
Covers preparation of Engineering Technical
Notes (CDRL #120) during the BOC phase.
Identical to 642221, except this element
covers the IOC phase.
Identical to 642221, except this element
covers the FOC phase.
This element covers the development and
preparation of the Segment Operations
Specification (CDRL #133) during the BOC
phase.
Develop Segment Operations,
Concepts, Procedures and
Specification, Including
Human Factor Engineering
This covers the effort required to revise
the Segment Operation Concept (CDRL #116)
and the Segment Operations Specification
(CDRL #133) during the IOC phase.
Develop Segment Operations,
Concepts, Procedures, and
Specifications, Including
Human Factor Engineering
Identical to 642301, except this element
covers the FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Develop User Manuals
Develop User Manuals
Develop User Manuals
Develop Segment/Systems
Operation Manuals
Develop Segment/System
Operation Manuals
Develop Segment/System
Operation Manuals
WBS
DESCRIPTION
Covers the development of User Manuals
(CDRL #135) that provide all necessary
information and procedures for qualified
users to access and interact with the
system during the BOC phase.
Identical to 642303, except this element
covers the IOC phase.
Identical to 642303, except this element
covers the FOC phase.
Covers the development of Operators Manuals
(CDRL #136) which provide computer opera-
tions personnel with a detailed operational
description of the system and operating
instructions. This element covers the BOC
phase.
Identical to 642306, except this element
covers the IOC phase.
Identical to 642306, except this element
covers the FOC phase.
Conduct Productivity
Enhancement Studies
This element provides for the performance of
productivity enhancement studies that focus
on making system operations more efficient.
This element covers the BOC phase.
642310 4.2.3 Conduct Productivity
Enhancement Studies
Identical to 642309, except this element
covers the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Conduct Productivity
Enhancement Studies
Prepare O&M Plan
Prepare O&M Plan
Prepare O&M Plan
Prepare Maintenance and
Logistics Plan
Prepare Maintenance and
and Logistics Plan
WBS
DESCRIPTION
Identical to 642309, except this element
covers the FOC phase.
Covers the preparation of the O&M Plan
(CDRL #123) which details the types and
numbers of positionings, responsibilities,
organization, etc., for performance of O&M
during the BOC phase.
Covers the effort required to revise the O&M
Plan (CDRL #123) during the IOC phase.
Identical to 642313, except this element
covers the FOC phase.
Covers the preparation of the Maintenance
and Logistics Plan (CDRL #124) which defines
the activities to be performed to ensure
the availability of the required maintenance
and logistics resources. Also includes
monitoring the technical performance of the
subcontractor. This element covers the
BOC phase.
Includes the effort required to revise the
Maintenance and Logistics Plan (CDRL #124)
during the IOC phase.
Prepare Maintenance and
Logistics Plan
Identical to 642316, except this element
covers the FOC phase.
Prepare Segment Design
Specification Including
Requirements Allocation
Includes the preparation of the Segment
Design Specification (CDRL #117) during
the BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
V
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Provide Data Base
Specification
Provide Engineering
Specialties Design
Provide SW-Opns-HW
Interface Design
Provide SW-Opns-HW
Interface Design
Provide SW-Opns-HW
Interface Design
Develop Segment Transition
and Integration Plan
Develop Segment Transition
and Integration Plan
WBS
DESCRIPTION
Covers the preparation of the Data Base
Specification (CDRL #125) which details
the relationship of the data base storage
requirement of all CPCI's in the segment to
the storage capability of the segment.
This element covers the BOC phase.
Covers the engineering specification design
effort performed in the BOC phase.
Effort to development the Operations/
Software, Operations/Hardware, Hardware/
Software and Software/Software Interface
Specs CDRL's 126, 127, 128 and 129 respec-
tively. Covers BOC phase.
Identical to 642405, except this covers IOC
phase.
Identical to 642405, except this covers FOC
phase.
Covers the preparation of the Segment
Transition/Integration Plan (CDRL #115)
during the BOC phase.
Identical to 642500, accept their element
covers the IOC phase.
Develop Segment Transition
and Integration Plan
Support Facility Planning
Installation and Checkout
Identical to 642500, accept their element
covers the FOC phase.
Includes the effort by system engineers
to support the facility planning task and
the installation and checkout task during
the BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Support Facility Planning
Installation and Checkout
Support Facility Planning'
Installation and Checkout
Support Transition of New
Capability Into the Oper-
ational Environment
Support Transition of New
Capability Into the Oper-
ational Environment
Support Transition of New
Capability Into the Oper-
ational Environment
Prepare Segment Verifica-
tion Plan
Prepare Segment Verifica-
tion Plan
Prepare Segment Verifica-
tion Plan
WBS
DESCRIPTION
Identical to 642503, except this element
covers the IOC phase.
Identical to 642503, except this element
covers the FOC phase.
Covers the effort by system engineers to
support the transition of new capability
into the operational environment during
the BOC phase.
Identical to 642506, except this element
covers the IOC phase.
Identical to 642506, except this element
covers the FOC phase.
Covers the preparation of the Segment Veri-
fication Plan (CDRL #121) during the BOC
phase.
Identical to 642600, except this element
covers the IOC phase.
Identical to 642600, except this element
covers the FOC phase.
Prepare Segment Test Plan
Covers the preparation of the Segment
Test Plan (CDRL #130) during the BOC phase.
642604 4.2.6 Prepare Segment Test Plan
Identical to 642603, except this element
covers the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Segment Test Plan
Support the Execution and
Evaluation of Tests
Support the Execution and
Evaluation of Test
Support the Execution and
Evaluation of Test
Evaluate Proposed Changes
and Provide Change Request
Impact Analysis Including
Interface Control
Evaluate Proposed Changes
and Provide Change Request
Impact Analysis Including
Interface Control
Evaluate Proposed Changes
and Provide Change Request
Impact Analysis Including
Interface Control
WBS
DESCRIPTION
Identical to 642603, except this element
covers the FOC phase.
Provide support to execution and evaluation
of tests during the BOC phase.
Identical to 642606, except this element
covers the IOC phase.
Identical to 642606, except this element
covers the FOC phase.
Covers the effort required to evaluate
proposed changes and provide change request
impact analysis including interface
control during the BOC phase.
Identical to 642700, except this element
covers the IOC phase.
Identical to 642700, except this element
covers the FOC phase.
Covers the effort required to prepare for
and participate in the PDR technical review
during the BOC phase.
Covers the effort to prepare for and
participate in the PDR technical update
review during the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
CDR Technical Review
CDR Technical Review
CDR Technical Review
SDR Technical Review
Conduct Technical Audits/
Misc. Reviews
Conduct Technical Audits/
Misc. Reviews
Conduct Technical Audits/
Misc. Reviews
WBS
DESCRIPTION
Covers the effort required to perform the
CDR Technical Review during the BOC phase.
Identical to 642803, except this element
covers the IOC phase.
Identical to 642803, except this element
covers the FOC phase.
Cover the effort required to perform the
SDR technical review during the BOC phase.
This element includes the effort required
to conduct the technical audits and mis-
cellaneous reviews as required. This ele-
ment covers the BOC phase.
Identical to 642809, except this element
covers the IOC phase.
Identical to 642809, except this element
covers the FOC phase.
Software Development (BOC)
Manage All SW Development
Activities
This covers the software development effort
during the BOC phase and includes the fol-
lowing functions: management, preliminary
design, critical design, development, test
and documentation.
This covers the efforts of second and third
level management functions required to man-
age the SW development tasks in the BOC
phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
643002
4.3.1
643003
4.3.1
643004
4.3.1
643005
4.3.1
643007
4.3.1
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS WBS
TITLE DESCRIPTION
NPIC Specific SW Training
SW Tool Development
SW Architecture
?
This covers the purchase of the commercial
training course needed to train programmer
personnel associated with the UNIVAC System
and the COBOL programming language during
the BOC phase.
Includes the development and/or assembly
of specific tools required for D/C Segment
SW development such as: Add COBOL to STI,
provide o UNIVAC download capability
for test. This element covers the BOC
phase.
Covers the effort required to ensure SW
architectural integrity during the BOC
phase.
Technical Support to Covers the software development effort
Subcontract Management required to support Subcontract Management
to ensure technical oversight during the
phase.
Segment PPS&C Covers the effort required to produce the
Segment Programming, Practices, Standards
and Convention (CDRL #132) during the BOC
phase. This is prepared to be compatable
with the System Integrators PPS&C.
Covers the purchase of COBOL code conversion
services during the BOC phase to convert
unmodified code from the UNIVAC to
processor.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
STAT
STAT
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
643009
4.3.1
643010
4.3.1
643011
4.3.1
643012
4.3.1
643014
4.3.1
643015
4.3.1
WBS WBS
TITLE DESCRIPTION
Library Control Covers the performance of routine source
library maintenance/control activities
during the BOC phase.
SW Builds and Releases
Perform software builds and maintain soft-
ware version control/documentation. Main-
tain hard copy control. This element covers
the BOC phase.
Provide Inputs to Segment Prepare and maintain the software section
Development Plan of the Segment Development Plan during the
BOC phase.
DMS 1100 Level 6 to Level 8 Covers the conversion of DMS 1100 from
Conversion Level 6 to Level 8. This includes planning
design, implementation, and test. This
element covers the BOC phase.
Data Base Conversion Covers the conversion of the data base needed
Design, Implementation, for BOC from DMS 1100 base to M204 base.
Verification Included are planning, design, conversion
utility creation, file conversion, and
verification. This element covers the BOC
phase.
Data Base Package This covers the preparation of the Data
Base Package (CDRL #151) which defines the
actual entries to be used for initializing
each data base item. This element covers
the BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
643016
4.3.1
Data Base Support to
Development and Test and
Verification
643017
4.3.2.1
Requirements Analysis and
Allocation
643018
4.3.2.1
Prepare (Prelim.) Design
Part I Specs. and Conduct
Internal Design Reviews
643019
4.3.2.1
Prepare Data Dictionary
643020
4.3.2.1
Prepare (Prelim) Part II
Specs.
WBS
DESCRIPTION
This effort includes the Data Base Admin-
istration function and production of the
final version of the Data Base Administra-
tion Manual (CDRL #137) during the BOC
phase.
This covers the CPCI BEPPRE during the BOC
phase and includes the design effort which
provides for analysis of Segment Design
specification functions and their alloca-
tions to individual CPCI's (and CI's). This
effort occurs after completion of the Design
Concept Review and leads to the generation
of the CPCI Part I specs. for PDR.
preliminary CPCI Part II specification
(CDRL #142).
This covers the CPCI BEPPRE during the BOC
phase and includes the preparation of the
CPCI preliminary Part I specification (CDRL
#141) and participation in internal design
reviews. This effort is performed by the
System Engineering group and augmented by
the SW Development group which supports
requirements allocation and development of
the Part I specs.
This covers the CPCI BEPPRE during the BOC
phase and includes the preparation of the
Data Dictionary (CDRL #145). The Data
Dictionary contains a description of every
data item in D/C Segment file.
This covers the CPCI BEPPRE during the BOC
phase and includes the preparation of the
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare CPCI Test Plan
(Prelim.)-Appendix for
BEPPRE
Prepare Build-to Part II
Specs. and Conduct Internal
Design Review
Prepare (Prelim.) Programmers
Manual
Prepare CPCI Test Plan
(Final)-Appendix for BEPPRE
WBS
DESCRIPTION
This covers the CPCI BEPPRE during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDRL #131).
This covers the CPCI BEPPRE during the BOC
phase and includes the preparation of the
CPCI Part II Specification or the "build-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BEPPRE during the BOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BEPPRE during the BOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BEPPRE during the BOC
phase and includes the development of source
code at the module level, its unit test
and debug.
Integrate and Test to CPC
Level
Test at the CPC and CPCI
Levels
This covers the CPCI BEPPRE during the BOC
phase and includes the SW development acti-
vities to integrate and test modules up to
CPC level.
This covers the CPCI BEPPRE during the BOC
phase and includes the formal testing by the
T&V group. This testing consists of PQT
testing of CPC/Strings and FQT testing of
complete CPCI's and their interfaces with
other CPCI's.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
643028
4.3.2.4
643029
4.3.2.4
643030
4.3.2.4
643031
4.3.2.5
643032
4.3.2.5
643034
4.3.2.5
WBS WBS
TITLE DESCRIPTION
Develop SW Test Procedures This covers the CPCI BEPPRE during the BOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps, environment
and data to be collected.
Support Test and This covers the CPCI BEPPRE during the BOC
Verification phase and includes the activities of the SW
Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and error
corrections.
Prepare Test Reports This covers the CPCI BEPPRE during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
Prepare Inputs to User, This covers the CPCI BEPPRE during the BOC
Operator and Data Base phase and includes the preparation of inputs
Administration Manuals to Users Manual (CDRL #135), Operator Manual
(CDRL #136), and Data Base Administrators
Manual (CDRL #137).
CPCI Listings As-built This covers the CPCI BEPPRE during the BOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
Prepare Programmers This covers the CPCI BEPPRE during the BOC
Manual (Final) phase and includes the preparation of final
version of the Programmers Manual (CDRL
#138).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
. Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
RFP
WBS
WBS NO.
WBS NO.
TITLE
643035
4.3.2.5
Prepare Inputs to Training
Manuals
643036
4.3.2.5
Prepare As-Built Part II
Specs.
643037
4.3.2.1
Requirements Analysis
and Allocation
WBS
DESCRIPTION
This covers the CPCI BEPPRE during the BOC
phase and includes the preparation inputs
to the various training manuals.
This covers the CPCI BEPPRE during the BOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
provides for analysis of Segment Design
specification functions and their alloca-
tions to individual CPCI's (and CI's).
This effort occurs after completion of the
Design Concept Review and leads to the
generation of the CPCI Part I specs. for
PDR.
This covers the CPCI BEMGMT during the BOC
phase and includes the design effort which
643038 4.3.2.1 Prepare (Prelim.) Design This covers the CPCI BEMGMT during the BOC
Part I Specs. and Conduct phase and includes the preparation of the
Internal Design Reviews CPCI preliminary Part I specifications
(CDRL #141) and participation in internal
design reviews. This effort is performed
by the System Engineering group and aug-
mented by the SW Development group which
supports requirements allocation and
development of the Part I specs.
643039 4.3.2.1 Prepare Data Dictionary This covers-the CPCI BEMGMT during the BOC
phase and includes the preparation of the
Data Dictionary (CDRL #145). The Data
Dictionary contains a description of every
data item in D/C Segment file.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare (Prelim.) Part II
Specs.
Prepare CPCI Test Plan
(Prelim.) Appendix for
BEMGMT
Prepare Build-to Part II
Specs. and Conduct Internal
Design Review
Prepare (Prelim.) Programmers
Manual
Prepare CPCI Test Plan
(Final) - Appendix for
BEMGMT
WBS
DESCRIPTION
This covers the CPCI BEMGMT during the BOC
phase and includes the preparation of the
preliminary CPCI Part II specifications
(CDRL #142).
This covers the CPCI BEMGMT during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDRL #131).
This covers the CPCI BEMGMT during the BOC
phase and includes the preparation of the
CPCI Part II Specification or the "build-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BEMGMT during the BOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BEMGMT during the BOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
Integrate and Test to
CPC Level
This covers the CPCI BEMGMT during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI BEMGMT during the BOC
phase and includes the SW development
activities to integrate and test modules
up to CPC level.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
643047
4.3.2.4
643048
4.3.2.4
643049
4.3.2.4
643050
4.3.2.4
643051
4.3.2.5
643052
4.3.2.5
WBS WBS
TITLE DESCRIPTION
Test at the CPC and CPCI This covers the CPCI BEMGMT during the BOC
Levels phase and includes the formal testing by the
T&V group. This testing consists of PQT
testing of CPC/Strings and FQT testing of
complete CPCIs and its interface with other
CPCIs.
Develop SW Test Procedures This covers the CPCI BEMGMT during the BOC
phase and includes procedures describing test
cases and acceptance criteria. Also includes
detailed testing steps and environment data
to be collected.
Support Test and Verification This covers the CPCI BEMGMT during the BOC
phase and includes the activities of the SW
Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
Prepare Test Reports This covers the CPCI BEGMGT during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
the results of PQT/FQT testing.
Prepare Inputs to User, This covers the CPCI BEGMGT during the BOC
Operator, and Data Base phase and includes the preparation of inputs
Administration Manuals to User Manual (CDRL #135), Operators Manual
(CDRL #136), and Data Base Administrators
Manual (CDRL #137).
CPCI Listings As-Built This covers the CPCI BEMGMT during the BOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
643053
4.3.2.5
643054
4.3.2.5
643055
4.3.2.5
643056
4.3.2.1
WBS WBS
TITLE DESCRIPTION
Prepare Programmers Manual This covers the CPCI BEMGMT during the BOC
(Final) phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
Prepare Inputs to Training This covers the CPCI BEMGMT during the BOC
Manuals phase and includes the preparation inputs to
the various training manuals.
Prepare As-Built Part II Specs. This covers the CPCI BEMGMT during the BOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II specs
(CDRL #142). The "as-built" version defines
the exact configuration of accepted computer
programs.
Requirements Analysis and This covers the CPCI BERESU during the BOC
Allocation phase and includes the design effort which
provides for analysis of Segment Design
specification functions and their alloca-
tions to individual CPCIs (and CIs). This
effort occurs after completion of the Design
Concept Review and leads to the generation
of the CPCI Part I specs. for PDR.
643057 4.3.2.1 Prepare (Prelim.) Design This covers the CPCI BERESU during the BOC
Part I Specs. and Conduct phase and includes the preparation of the
Internal Design Reviews CPCI preliminary Part I specification (CDRL
#141) and participation in internal design
reviews. This effort is performed by the
System Engineering group and augmented by
the SW Development group which supports
requirements allocation and development of
the Part I specs.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Data Dictionary
Prepare (Prelim.) Part II
Specs.
Prepare CPCI Test Plan
(Prelim.) Appendix for
BERESU
Prepare Build-to Part II
Specs. and Conduct Internal
Design Review
Prepare (Prelim.) Programmers
Manual
WBS
DESCRIPTION
This covers the CPCI BERESU during the BOC
phase and includes the preparation of the
Data Dictionary (CDRL #145). The Data
Dictionary contains a description of every
data item in D/C Segment file.
This covers the CPCI BERESU during the BOC
phase and includes the preparation of the
preliminary CPCI Part II specification
(CDRL #142).
This covers the CPCI BERESU during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDRL #131).
This covers the CPCI BERESU during the BOC
phase and includes the preparation of the
CPCI Part II specification or the "build-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BERESU during the BOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
Prepare CPCI Test Plan (Final)
Appendix for BERESO
This covers the CPCI BERESU during the BOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BERESU during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
643065
643066
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
RFP
WBS
WBS
WBS NO.
TITLE
DESCRIPTION
4.3.2.3
Integrate and Test to
CPC Level
This
phase
ties
covers the CPCI BERESU during the BOC
and includes the SW development activi-
to integrate and test modules up to
CPC level.
4.3.2.4
Test at the CPC and
CPCI Levels
This covers the CPCI BERESU during the BOC
phase and includes the formal testing by the
T&V group. This testing consists of PQT
testing of CPC/strings and FQT testing of
complete CPCIs and its interface with other
CPCIs.
643067 4.3.2.4 Develop SW Test Procedures This covers the CPCI BERESU during the BOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and envi-
ronment data to be collected.
643068 4.3.2.4 Support Test Verification This covers the CPCI BERESU during the BOC
phase and includes the activities of the SW
Development group to support all formal tests
by the T&V group up to acceptance. Also
includes all problem analysis and error
correction.
643069 4.3.2.4 Prepare Test Reports This covers the CPCI BERESU during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
643071 4.3.2.5 CPCI Listings As-built This covers the CPCI BERESU during the
BOC phase and includes the listing of
source instruction. Statements and ob-
ject code for all CPC forming the CPCI
(CDRL #150).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
RFP
WBS
WBS NO.
WBS NO.
TITLE
643074
4.3.2.5
Prepare As-Built Part
# Specs.
643094
4.3.2.1
Requirements Analysis and
Allocation
WBS
DESCRIPTION
This covers the CPCI BERESU during the
BOC phase and includes the preparation
of the "as-built" version of the CPCI
Part II specs. (CDRL #142). The "as-
built" version defines the exact con-
figuration of accepted computer pro-
grams.
provides for analysis of Segment Design
specification functions and their alloca-
tions to individual CPCI's (and CI's).
This effort occurs after completion of
the Design Concept Review and leads to
the generation of the CPCI Part I specs.
for PDR.
This covers the CPCI BMANIP during the BOC
phase and includes the design effort which
643301 4.3.2.1 Prepare (Prelim.) Design This covers the CPCI BMANIP during the
Part I Specs. and Conduct BOC phase and includes the preparation
Internal Design Reviews of the CPCI preliminary Part I specifi-
cation (CDRL #141) and participation in
internal design reviews. This effort is
preformed by the System Engineering group
and augmented by the SW Development group
which supports requirements allocation and
development of the Part I specs.
643095 4.3.2.1 Prepare Data Dictionary This covers the CPCI BMANIP during the
BOC phase and includes the preparation
of the Data Dictionary (CDRL #145). The
Data Dictionary contains a description of
every data item in D/C Segment file.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare (Prelim.) Part II
Specs.
Prepare CPCI Test Plan
(Prelim.) - Appendix for
BMANIP
Prepare Built-to Part II
Specs. and Conduct Internal
Design Review
Prepare (Prelim.) Programmers
Manual
Prepare CPCI Test Plan
(Final) - Appendix for
BMANIP
WBS
DESCRIPTION
This covers the CPCI BMANIP during the
BOC phase and includes the preparation of
the preliminary CPCI Part II specifica-
tion (CDRL #142).
This covers the CPCI BMANIP during
the BOC phase and includes the
preparation of the preliminary
CPCI Test Plan (CDR #131).
This covers the CPCI BMANIP during the BOC
phase and includes the preparation of the
CPCI Part II specification or the "Built-to"
specification (CDRL #142) and participa-
tion in internal design reviews.
This covers the CPCI BMANIP during the BOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BMANIP during the BOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
Integrate and Test to
CPC Level
This covers the CPCI BMANIP during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI BMANIP during the BOC
phase and includes the SW development
activities to integrate and test modules up
to CPC level.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
643103
4.3.2.4
Test at the CPC and CPCI
643104
4.3.2.4
Levels
Develop SW Test Procedures
rw
643105
4.3.2.4
Support Test and Verification
643106
4.3.2.4
Prepare Test Reports
643107
4.3.2.5
Prepare Inputs to User,
643108
4.3.2.5
Operator and Data Base
Administration Manuals
CPCI Listings As-built
WBS
DESCRIPTION
This covers the CPCI BMANIP during the BOC
phase and includes the formal testing by
the T&V group. This testing consist of
PQT testing of CPC/Strings and FQT testing
of complete CPCI's and its interface with
other CPCI's.
This covers the CPCI BMANIP during the BOC
phase and includes procedures describing test
cases and acceptance criteria. Also includes
detailed testing steps and environment data
to be collected.
This covers the CPCI BMANIP during the BOC
phase and includes the activities of the SW
Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
This covers the CPCI BMANIP during the
BOC phase and includes activities by the
T&V group to prepare formal test reports
on results of PQT/FQT testing.
This covers the CPCI BMANIP during the BOC
phase and includes the preparation ofinputs
to Users Manual (CDRL #135), Operator
Manual (CDRL #136), and Data Base Admini-
strators Manual (CDRL #137).
This covers the CPCI BMANIP during the BOC
phase and includes the listing of source in-
struction statements and object code for all
CPC forming the CPCI (CDRL #150).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
643109
4.3.2.5
643110
4.3.2.5
643111
4.3.2.5
643112
4.3.2.1
WBS WBS
TITLE DESCRIPTION
Prepare Programmers Manual This covers the CPCI BMANIP during the BOC
(Final) phase and includes the preparation of
final version of the Programmers Manual
(CDRL #138).
Prepare Inputs to Training This covers the CPCI BMANIP during the BOC
Manuals phase and includes the preparation inputs
to the various training manuals.
Prepare As-Built Part II This covers the CPCI BMANIP during the BOC
Specifications phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL x/142). The "as-built" version
defines the exact configuration of accepted
computer programs.
Requirements Analysis and This covers the CPCI BSTATR during the BOC
Allocation phase and includes the design effort which
provides for analysis of Segment Design
specification functions and their allocations
to individual CPCI's (and CI's). This effort
occurs after completion of the Design Con-
cept Review and leads to the generation of
CPCI Part I specs. for PDR.
643113 4.3.2.1 Prepare (Prelim.) Design This covers the CPCI BSTATR during the
Part I Specs. and Conduct phase and includes the preparation of
Internal Design Reviews the CPCI preliminary Part I specifica-
tion (CDRL #141) and participation in
internal design reviews. This effort is
performed by the System Engineering group
and augmented by the SW development group
which supports requirements allocation
and development of the Part I specs.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Data Dictionary
Prepare (Prelim.) Part II
Specs.
Prepare CPCI Test Plan
(Prelim.) - Appendix for
BSTATR
Prepare Built-to Part II
Specs. and Conduct Internal
Design Review
Prepare (Prelim.)
Programmers Manual
WBS
DESCRIPTION
This covers the CPCI BSTATR during the
BOC phase and includes the preparation
of the Data Dictionary (CDRL #145).
The Data Dictionary contains a descrip-
tion of every data item in D/C Segment
file.
This covers the'CPCI BSTATR during the BOC
phase and includes the preparation of the
preliminary CPCI Part II specification
(CDRL #142).
This covers the CPCI BSTATR during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDR #131).
This covers the CPCI BSTATR during the BOC
phase and includes the preparation of the
CPCI Part II specification or the "build-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BSTATR during the BOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
643120 4.3.2.3
Prepare CPCI Test Plan
(Final) - Appendix for
BSTATR
This covers the CPCI BSTATR during the BOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BSTATR during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 is
V
IBM
WBS NO.
RFP
WBS NO.
643121
4.3.2.3
643122
4.3.2.4
643123
4.3.2.4
643124
4.3.2.4
643125
4.3.2.4
643127
4.3.2.5
WBS WBS
TITLE DESCRIPTION
Integrate and Test to CPC This covers the CPCI BSTATR during the BOC
Level phase and includes the SW development
activities to integrate and test modules
up to CPC level.
Test at the CPC and CPCI This covers the CPCI BSTATR during the BOC
Levels phase and includes the formal testing by the
T&V group. This testing consist of PQT
testing of CPC/Strings and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test Procedures This covers the CPCI BSTATR during the BOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps, environ-
ment and data to be collected.
Support Test and This covers the CPCI BSTATR during the BOC
Verification phase and includes the activities of the
SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
Prepare Test Reports This covers the CPCI BSTATR during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
CPCI Listings As-built This covers the CPCI BSTATR during the BOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL ##150).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
RFP
WBS
WBS NO.
WBS NO.
TITLE
643130
4.3.2.5
Prepare As-Built Part
II Specs.
643149
4.3.2.1
Requirements Analysis and
Allocation
WBS
DESCRIPTION
This covers the CPCI BSTATR during the BOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built"
version defines the exact configura-
tion of accepted computer programs.
This covers the CPCI BMMGMT during the BOC
phase and includes the design effort which
provides for analysis of Segment Design
specification functions and their alloca-
tions to individual CPCI's (and CI's).
This effort occurs after completion of
the Design Concept Review and leads to
the generation of the CPCI Part I specs.
for PDR.
643150 4.3.2.1 Prepare (Prelim.) Design This covers the CPCI BMMGMT during the BOC
Part I Specs. and Conduct phase and includes the preparation of the
Internal Design Reviews CPCI preliminary Part I specification
(CDRL #141) and participation in internal
design reviews. This effort is preformed
by the System Engineering group and
augmented by the SW Development group
which supports requirements allocation
and development of the Part I specs.
643151 4.3.2.1 Prepare Data Dictionary This covers the CPCI BMMGMT during the BOC
phase and includes the preparation of the
Data Dictionary (CDRL #145). The Data
Dictionary contains a description of
every data item in D/C Segment file.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare CPCI Test Plan
(Prelim.)- Appendix for
BMMGMT
Prepare CPCI Test Plan
(Final) - Appendix for
BMMGMT
Integrate and Test to
CPC Level
Test at the CPC and CPCI
Levels
WBS
DESCRIPTION
This covers the CPCI BMMGMT during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDR #131).
This covers the CPCI BMMGMT during the BOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BMMGMT during the BOC
phase and includes the SW development
activities to integrate and test modules
up to CPC level.
This covers the CPCI BMMGMT during the BOC
phase and includes the formal testing by
the T&V group. This testing consist of PQT
testing of CPC/Strings and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test Procedures
Support Test and
Verification
This covers the CPCI BMMGMT during the BOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps, environ-
ment and data to be collected.
This covers the CPCI BMMGMT during the BOC
phase and includes the activities of the
SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
RFP
WBS
WBS NO.
WBS NO.
TITLE
643162
4.3.2.4
Prepare Test Reports
643163
4.3.2.5
CPCI Listings As-built
643167
4.3.2.1
Requirements Analysis and
Allocation
WBS
DESCRIPTION
This covers the CPCI BMMGMT during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
This covers the CPCI BMMGMT during the BOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
This covers the CPCI BCCNTR during the BOC
phase and includes the design effort which
provides for analysis of Segment Design
specification functions and their alloca-
tions to individual CPCI's (and Cl's).
This effort occurs after completion of
the Design Concept Review and leads to the
generation of the CPCI Part I specs. for
PDR.
643168 4.3.2.1 Prepare (Prelim.) Design This covers the CPCI BCCNTR during the BOC
Part I Specs. and Conduct phase and includes the preparation of the
Internal Design Reviews CPCI preliminary Part I specification
(CDRL #141) and participation in internal
design reviews. This effort is performed
by the System Engineering group and aug-
mented by the SW Development group which
supports requirements allocation and
development of the Part I Specs.
643169 4.3.2.1 Prepare Data Dictionary This covers the CPCI BCCNTR during the
BOC phase and includes the preparation
of the Data Dictionary (CDRL #145).
The Data Dictionary contains a description
of every data item in D/C Segment file.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
643170
RFP
WBS NO.
WBS
TITLE
Prepare (Prelim.) Part
II Specs.
Prepare CPCI Test Plan
(Prelim.) - Appendix for
BCCNTR
Prepare Built-to Part II
Specs. and Conduct Internal
Design Review
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test Plan
(Final) - Appendix for
BCCNTR
WBS
DESCRIPTION
This covers the CPCI BCCNTR during the BOC
phase and includes the preparation of the
preliminary CPCI Part II specification
(CDRL #142).
This covers the CPCI BCCNTR during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDR #131).
This covers the CPCI BCCNTR during the BOC
phase and includes the preparation of the
CPCI Part II specification or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BCCNTR during the BOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BCCNTR during the BOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
Integrate and Test to
CPC Level
This covers the CPCI BCCNTR during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI BCCNTR during the BOC
phase and includes the SW development
activities to integrate and test modules up
to CPC level.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
643177
4.3.2.4
643178
4.3.2.4
643179
4.3.2.4
643180
4.3.2.4
643182
4.3.2.5
WBS WBS
TITLE DESCRIPTION
Test at the CPC and CPCI This covers the CPCI BCCNTR during the BOC
Levels phase and includes the formal testing by
the T&V group. This testing consist of PQT
testing of CPC/Strings and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test Procedure This covers the CPCI BCCNTR during the BOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps, environ-
ment and data to be collected.
Support Test and This covers the CPCI BCCNTR during the BOC
Verification phase and includes the activities of the
SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
Prepare Test Reports This covers the CPCI BCCNTR during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
CPCI Listings As-built This covers the CPCI BCCNTR during the BOC
phase and includes the listing of source
instruction, statements and object code
for all CPC forming the CPCI (CDRL #150).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
V
IBM
RFP
WBS NO.
WBS NO.
643186
4.3.2.1
643187
4.3.2.1
643188
4.3.2.1
643189
4.3.2.1
643190
4.3.2.1
WBS WBS
TITLE DESCRIPTION
Requirements Analysis and This covers the CPCI BQUERY during the
Allocation phase and includes the design effort
which provides for analysis of Segment
Design specification functions and their
allocations to individual CPCI's (and CI's).
This effort occurs after completition of the
Design Concept Review and leads to the
generation of the CPCI Part I specs. for
PDR.
Prepare (Prelim.) Design This covers the CPCI BQUERY during the BOC
Part I Specs. and Conduct phase and includes the preparation of the
Internal Design Reviews preliminary Part I specification (CDRL #141)
and participation in internal design reviews.
This effort is performed by the System
Engineering group and augmented by the SW
Development group which supports require-
ments allocation and development of the
Part I specs.
Prepare Data Dictionary This covers the CPCI BQUERY during the BOC
phase and includes the preparation of the
Data Dictionary (CDRL #145). The Data
Dictionary contains a description of
every data item in D/C Segment file.
Prepare (Prelim.) Part II This covers the CPCI BQUERY during the BOC
Specs. phase and includes the preparation of the
preliminary CPCI Part II specification
(CDRL #142).
Prepare CPCI Test Plan This covers the CPCI BQUERY during the BOC
(Prelim.) - Appendix for phase and includes the preparation of the
BQUERY preliminary CPCI Test Plan (CDR #131).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
643191
4.3.2.2
643192
4.3.2.2
643193
4.3.2.3
643194
4.3.2.3
643195
4.3.2.4
643196
4.3.2.4
WBS WBS
TITLE DESCRIPTION
Prepare Built-to Part II This covers the CPCI BQUERY during the BOC
Specs. and Conduct Internal phase and includes the preparation of the
Design Review CPCI Part II specification or the "built-
to" specification (CDRL #142) and participa-
tion in internal design reviews.
Prepare CPCI Test Plan This covers the CPCI BQUERY during the
(Final) - Appendix for BOC phase and includes the preparation
BQUERY of the final CPCI Test Plan (CDRL #131).
Code and Unit Test This covers the CPCI BQUERY during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
Integrate and Test to This covers the CPCI BQUERY during the BOC
CPC Level phase and includes the SW development
activities to integrate and test modules
up to CPC level.
Test at the CPC and This covers the CPCI BQUERY during the BOC
CPCI Levels phase and includes the formal testing by
the T&V group. This testing consist of
PQT testing of CPC/Strings and FQT testing
of complete CPCI's and its interface with
other CPCI's.
Develop SW Test Procedure This covers the CPCI BQUERY during the BOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and environ-
ment data to be collected.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
IBM
WBS NO.
RFP
WBS NO.
643197
4.3.2.4
643198
4.3.2.4
643200
4.3.2.5
643203
4.3.2.5
643204
4.3.2.1
WBS WBS
TITLE DESCRIPTION
Support Test and Verification This covers the CPCI BQUERY during the BOC
phase and includes the activities of the
SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
Prepare Test Reports
CPCI Listings As-built
Prepare As-Built Part
II Specs.
This covers the CPCI BQUERY during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
This covers the CPCI BQUERY during the BOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL ##150).
This covers the CPCI BQUERY during the BOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL ##142). The "as-built" version
defines the exact configuration of accepted
computer programs.
Requirements Analysis and This covers the CPCI BAPPLS during the BOC
Allocation phase and includes the design effort which
provides for analysis of Segment Design
specification functions and their alloca-
tions to individual CPCI's (and CI's).
This effort occurs after completion of the
Design Concept Review and leads to the gen-
eration of the CPCI Part I specs. for PDR.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
643205
4.3.2.1
643206
4.3.2.1
643207
4.3.2.1
643208
4.3.2.1
643209
4.3.2.2
643210
4.3.2.2
WBS
TITLE
Prepare (Prelim.) Design Part
I Specs. and Conduct Internal
Design Reviews
WBS
DESCRIPTION
This covers the CPCI BAPPLS during the BOC
phase and includes the preparation of the
CPCI preliminary Part I specification
(CDRL #141) and participation in internal
design reviews. This effort is performed
by the System Engineering group and aug-
mented by the SW Development group which
supports requirements allocation and develop-
ment of the Part I specs.
Prepare Data Dictionary This covers the CPCI BAPPLS during the BOC
phase and includes the preparation of the
Data Dictionary (CDRL #145). The Data
Dictionary contains a description of every
data item in D/C Segment file.
Prepare (Prelim.) Part This covers the CPCI BAPPLS during the BOC
II Specs. phase and includes the preparation of the
preliminary CPCI Part II specification
(CDRL # 142).
Prepare CPCI Test Plan (Prelim.) This covers the CPCI BAPPLS during the BOC
- Appendix for BAPPLS phase and includes the preparation of the
preliminary CPCI Test Plan (CDR #131).
Prepare Built-to Part II This covers the CPCI BAPPLS during the BOC
Specs and Conduct Internal phase and includes the preparation of the
Design Review CPCI Part II specification or the "build-to"
specification (CDRL #142) and participa-
tion in internal design reviews.
Prepare (Prelim.) This covers the CPCI BAPPLS during the BOC
Programmers Manual and includes the preparation of the pre-
liminary Programmers Manual (CDRL #138).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
IBM
WBS NO.
RFP
WBS NO.
643211
4.3.2.2
643212
4.3.2.3
643213
4.3.2.3
643214
4.3.2.4
643215
4.3.2.4
643216
4.3.2.4
WBS WBS
TITLE DESCRIPTION
Prepare CPCI Test Plan This covers the CPCI BAPPLS during the BOC
(Final) - Appendix for phase and includes the preparation of the
BAPPLS of the final CPCI Test Plan (CDRL #131).
Code and Unit Test This covers the CPCI BAPPLS during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
Integrate and Test to CPC This covers the CPCI BAPPLS during the BOC
Level phase and includes the SW development activ-
ities to integrate and test modules up to
CPC level.
Test at the CPC and CPCI This covers the CPCI BAPPLS during the BOC
Levels phase and includes the formal testing by
the T&V group. This testing consist of
PQT testing of CPC/Strings and FQT testing
of complete CPCI's and its interface with
other CPCI's.
Develop SW Test Procedures This covers the CPCI BAPPLS during the BOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and environ-
ment data to be collected.
Support Test and This covers the CPCI BAPPLS during the BOC
Verification phase and includes the activities of the SW
Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: A-RDP84T00037R000300060001-2 is
IBM
WBS NO.
RFP
WBS NO.
643217
4.3.2.4
643219
4.3.2.5
643220
4.3.2.5
643221
4.3.2.5
643222
4.3.2.5
643223
4.3.2.1
WBS WBS
TITLE DESCRIPTION
Prepare Test Reports This covers the CPCI BAPPLS during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
CPCI Listings as-built This covers the CPCI BAPPLS during the BOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
Prepare Programmers This covers the CPCI BAPPLS during the BOC
Manual (Final) phase and includes the preparation of
final version of the Programmers Manual
(CDRL #138).
Prepare Inputs to This covers the CPCI BAPPLS during the BOC
Training Manuals phase and includes the preparation inputs
to the various training manuals.
Prepare As-Built Part This covers the CPCI BAPPLS during the BOC
II Specs. phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
Requirements Analysis and This covers the CPCI BDMAPS during the BOC
Allocation phase and includes the design effort which
provides for analysis of Segment Design
specification functions and their alloca-
tions to individual CPCI's (and CI's).
This effort occurs after completion of
the Design Concept Review and leads to
the generation of the CPCI Part I specs,
for PDR.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare (Prelim.) Design
Part I Specs. and Conduct
Internal Design Reviews
Prepare Data Dictionary
Prepare (Prelim.) Part II
Specs.
Prepare CPCI Test Plan
(Prelim.) - Appendix for
BDMAPS
Prepare Built-to Part
II Specs. and Conduct
Internal Design Review
?
WBS
DESCRIPTION
This covers the CPCI BDMAPS during the BOC
phase and includes the preparation of the CPCI
(CDRL #141) and participation in internal
design reviews. This effort is performed
by the System Engineering group and aug-
mented by the SW Development group, which
supports requirement's allocation and
development of the Part I specs.
This covers the CPCI BDMAPS during the BOC
phase and includes the preparation of the
Data Dictionary (CDRL #145). The Data
Dictionary contains a description of every
data item in D/C Segment file.
This covers the CPCI BDMAPS during the BOC
phase and includes the preparation of the
preliminary CPCI Part II specification (CDRL
#142).
This covers the CPCI BDMAPS during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDR #131).
This covers the CPCI BDMAPS during the BOC
phase and includes the preparation of the
CPCI Part II specification or the "build-
to" specification (CDRL #142) and partici-
pation in internal design reviews.
643229 4.3.2.2 Prepare (Prelim.) This covers the CPCI BDMAPS during the BOC
Programmers Manual phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
IBM
WBS NO.
RFP
WBS NO.
643230
4.3.2.2
643231
4.3.2.3
643232
4.3.2.3
643233
4.3.2.4
643234
4.3.2.4
643235
4.3.2.4
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
WBS
DESCRIPTION
?
Prepare CPCI Test Plan This covers the CPCI BDMAPS during the BOC
(Final) - Appendix for phase and includes the preparation of the
BDMAPS final CPCI Test Plan (CDRL #131).
Code and Unit Test This covers the CPCI BDMAPS during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
Integrate and Test This covers the CPCI BDMAPS during the BOC
to CPC Level phase and includes the SW development
activities to integrate and test modules
up to CPC level.
Test at the CPC and This covers the CPCI BDMAPS during the BOC
CPCI Levels phase and includes the formal testing by the
T&V group. This testing consist of PQT
testing of CPC/Strings and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test This covers the CPCI BDMAPS during the BOC
Procedures phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps, environ-
ment and data to be collected.
Verification phase and includes the activities of the SW
Development group to support all formal
tests by the TO group up to acceptance.
Also includes all problem analysis and
error correction.
Support Test and This covers the CPCI BDMAPS during the BOC
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
IBM
WBS NO.
RFP
WBS NO.
643236
4.3.2.4
643238
4.3.2.5
643241
4.3.2.5
643242
4.3.2.1
WBS
TITLE
Prepare Test Reports
CPCI Listings As-built
Prepare As-Built Part
II Specs.
is
WBS
DESCRIPTION
This covers the CPCI BDMAPS during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
This covers the CPCI BDMAPS during the BOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
This covers the CPCI BDMAPS during the BOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
Requirements Analysis This covers the CPCI BTTDEV during the BOC
and Allocation phase and includes the design effort which
provides for analysis of Segment Design
specification functions and their alloca-
tions to individual CPCI's (and CI's).
This effort occurs after completion of the
Design Concept Review and leads to the gen-
eration of the CPCI Part I specs. for PDR.
643243 4.3.2.1 Prepare (Prelim.) Design This covers the CPCI BTTDEV during the BOC
Part I Specs. and Conduct phase and includes the preparation of the
Internal Design Reviews CPCI preliminary Part I specification (CDRL
#141) and participation in internal design
reviews. This effort is performed by the
System Engineering group and augmented by
the SW Development group which supports
requirements allocation and development of
the Part I specs.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
IBM
WBS NO.
643244
RFP
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
Prepare Data Dictionary
Prepare (Prelim.)
Part II Specs.
Prepare CPCI Test Plan
(Prelim.) - Appendix
for BTTDEV
Prepare Built-to Part
II Specs. and Conduct
Internal Design Review
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test Plan
(Final) - Appendix for
BTTDEV
?
WBS
DESCRIPTION
This covers the CPCI BTTDEV during the BOC
phase and includes the preparation of the
Data Dictionary (CDRL #145). The Data
Dictionary contains a description of every
data item in D/C Segment file.
This covers the CPCI BTTDEV during the BOC
phase and includes the preparation of the
preliminary CPCI Part II specification
(CDRL#142).
This covers the CPCI BTTDEV during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDR #131).
This covers the CPCI BTTDEV during the BOC
phase and includes the preparation of the
CPCI Part II specification or the "build-
to" specification (CDRL #142) and partici-
pation in internal design reviews.
This covers the CPCI BTTDEV during the BOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BTTDEV during BOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BTTDEV during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/0 5: CIA
-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
643251
4.3.2.3
643252
4.3.2.4
643253
4.3.2.4
643254
4.3.2.4
643255
4.3.2.4
643256
4.3.2.5
WBS WBS
TITLE DESCRIPTION
Integrate and Test This covers the CPCI BTTDEV during the BOC
to CPC Level phase and includes the SW development activi-
ties to integrate and test modules up to CPC
level.
Test at the CPC and This covers the CPCI BTTDEV during the BOC
CPCI Levels phase and includes the formal testing by
the T&V group. This testing consist of
PQT testing of CPC/Strings and FQT testing
of complete CPCI's and its interface with
other CPCI's.
Develop SW Test This covers the CPCI BTTDEV during the BOC
Procedures phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and environ-
ment data to be collected.
Support Test and This covers the CPCI BTTDEV during the BOC
Verification phase and includes the activities of the SW
Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
Prepare Test Reports This covers the CPCI BTTDEV during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
Prepare Inputs to User, This covers the CPCI BTTDEV during the BOC
Operator and Data Base phase and includes the preparation of in-
Administration Manuals puts to Users Manual (CDRL #135), Operators
Manual (CDRL #136), and Data Base Admini-
strators Manual (CDRL #137).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
643257
4.3.2.5
643258
4.3.2.5
643259
4.3.2.5
643260
4.3.2.5
643261
4.3.2.1
WBS WBS
TITLE DESCRIPTION
CPCI Listings As-built This covers the CPCI BTTDEV during the BOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
Prepare Programmers This covers the CPCI BTTDEV during the BOC
Manual (Final) phase and includes the preparation of final
version of the Programmers Manual (CDRL
#138).
Prepare Inputs to This covers the CPCI BTTDEV during the BOC
Training Manuals phase and includes the preparation inputs
to the various training manuals.
Prepare As-Built Part This covers the CPCI BTTDEV during the BOC
II Specs. phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" ver-
sion defines the exact configuration of
accepted computer programs.
Requirements Analysis This covers the CPCI WAPPLS during the BOC
and Allocation phase and includes the design effort which
provides for analysis of Segment Design spec-
ification functions and their allocations
to individual CPCI's (and Cl's). This effort
occurs after completion of the Design Con-
cept Review and leads to the generation of
the CPCI Part I specs. for PDR.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/0 IA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare (Prelim.) Design
Part I Specs. and Conduct
Internal Design Reviews
Prepare Data Dictionary
Prepare (Prelim.) Part
II Specs.
Prepare CPCI Test Plan
(Prelim.) - Appendix for
WAPPLS
Prepare Built-to Part
II Specs. and Conduct
Internal Design Review
WBS
DESCRIPTION
This covers the CPCI WAPPLS during the BOC
phase and includes the preparation of the
CPCI preliminary Part I specification
(CDRL #141) and participation in internal
design reviews. This effort is performed
by the System Engineering group and aug-
mented by the SW Development group which
supports requirements allocation and develop-
ment of the Part I specs.
This covers the CPCI WAPPLS during the BOC
phase and includes the preparation of the
Data Dictionary (CDRL # 145). The Data
Dictionary contains a description of
every data item in D/C Segment file.
This covers the CPCI WAPPLS during the BOC
phase and includes the preparation of the
preliminary CPCI Part II specification
(CDRL #142).
This covers the CPCI WAPPLS during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDR #131).
This covers the CPCI WAPPLS during the BOC
phase and includes the preparation of the
CPCI Part II specification or the "build-
to" specification (CDRL #142) and partici-
pation in internal design reviews.
643267 4.3.2.2 Prepare (Prelim.) This covers the CPCI WAPPLS during the BOC
Programmers Manual phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
V
IBM
WBS NO.
RFP
WBS NO.
643268
4.3.2.2
643269
4.3.2.3
643270
4.3.2.3
643271
4.3.2.4
643272
4.3.2.4
643273
4.3.2.4
WBS WBS
TITLE DESCRIPTION
Prepare CPCI Test Plan This covers the CPCI WAPPLS during the BOC
(Final) - Appendix for phase and includes the preparation of the
WAPPLS final CPCI Test Plan (CDRL #131).
Code and Unit Test This covers the CPCI WAPPLS during the
BOC phase and includes the development of
source code at the module level, its unit
test and debug.
Integrate and Test to This covers the CPCI WAPPLS during the BOC
CPC Level phase and includes the SW development activi-
ties to integrate and test modules up to CPC
level.
Test at the CPC and This covers the CPCI WAPPLS during the BOC
CPCI Levels phase and includes the formal testing by
the T&V group. This testing consists of
PQT testing of CPC/Strings and FQT testing
of complete CPCI's and its interface with
other CPCI's.
Develop SW Test This covers the CPCI WAPPLS during the BOC
Procedures phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps, environ-
ment and data to be collected.
Support Test and This covers the CPCI WAPPLS during the
Verification BOC phase and includes the activities of
of the SW Development group to support all
formal tests by the T&V group up to
acceptance. Also includes all problem
analysis and error correction.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 is
V
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Test
Reports
Prepare Inputs to User,
Operator and Data Base
Administration Manuals
CPCI Listings
As-built
Prepare Programmers
Manual (Final)
WBS
DESCRIPTION
This covers the CPCI WAPPLS during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
This covers the CPCI WAPPLS during the
BOC phase and includes the preparation
of inputs to Users Manual (CDRL #135),
Operator Manual (CDRL #136), and Data
Base Adminstrators Manual (CDRL #137).
This covers the CPCI WAPPLS during the BOC
phase and includes the listing of source
instruction statements and object code
for all CPC forming the CPCI (CDRL #150).
This covers the CPCI WAPPLS during the BOC
phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
Prepare Inputs to
Training Manuals
Prepare As-Built
Part II Specs.
This covers the CPCI WAPPLS during the BOC
phase and includes the preparation on inputs
to the various training manuals.
This covers the CPCI WAPPLS during th BOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II specs.
(CDRL #142). The "as-built" version defines
the exact configuration of accepted computer
programs.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/0 IA-RDP84T00037R000300060001-2 ?
IBM
RFP
WBS
WBS NO.
WBS NO.
TITLE
643280
4.3.2.1
Requirements Analysis
and Allocation
643281
4.3.2.1
Prepare (Prelim.)
Design Part I Specs.
and Conduct Internal
Design Reviews
643282
4.3.2.1
Prepare Data Dictionary
643284
4.3.2.1
Prepare (Prelim.) Part
II Specs.
643285
4.3.2.1
Prepare CPCI Test Plan
(Prelim)-Appendix for
BEXSUP
provides for analysis of Segment Design
specification functions and their allocations
to individual CPCI's (and CI's). This effort
occurs after completion of the Design Concept
Review and leader to the generation of the
CPCI Part I spec. for PDR.
WBS
DESCRIPTION
This covers the CPCI BEXSUP during the BOC
phase and includes the design effort which
This covers the CPCI BEXSUP during the BOC
phase and includes the preparation of the
CPCI preliminary Part I specification
(CDRL #141) and participation in internal
design reviews. This effort is performed
by the System Engineering group and aug-
umented by the SW Development group which
supports requirements allocation and
development of the Part I Specs.
This covers the CPCI BEXSUP during the
BOC phase and includes the preparation
of the Data Dictionary (CDRL #145). The
Data Dictionary contains a description
of every data item in D/C Segment file.
This covers the CPCI BEXSUP during the
BOC phase and includes the preparation of
the preliminary CPCI Part II specification
(CDRL #142).
This covers the CPCI BEXSUP during the BOC
phase and includes the preparation of the
preliminary CPCI Test Plan (CDR #131).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Built-to Part
II Specs. and Conduct
Internal Design Review
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test
Plan (Final) - Appendix
for BEXSUP
Integrate and Test to
CPC level
WBS
DESCRIPTION
This covers the CPCI BEXSUP during the BOC
phase and includes the preparation of the
CPCI Part II specification or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BEXSUP during the BOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BEXSUP during the BOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BEXSUP during the BOC
phase and includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI BEXSUP during the BOC phase
and includes the SW development activities to
integrate and test modules up to CPC level.
Test at the CPC and
CPCI Levels
Develop SW Test
Procedures
This covers the CPCI BEXSUP during the BOC
phase and includes the formal testing by
the T&V group. This testing consists of
PQT testing CPC/Strings and FQT testing
of complete CPCI's and its interface
with other CPCI's.
This covers the CPCI BEXSUP during the BOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps, environ-
ment, and data to be collected.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/0 5: C
IA-RDP84T00037R000300060001-2
IBM
WBS NO.
RFP
WBS NO.
643293
4.3.2.4
643294
4.3.2.4
643295
4.3.2.5
643296
4.3.2.5
643298
4.3.2.5
643299
4.3.2.5
WBS WBS
TITLE DESCRIPTION
Support Test and This covers the CPCI BEXSUP during the BOC
Verification phase and includes the activities of the SW
Development group to support all formal tests
by the T&V group up to acceptance. Also
includes all problem analysis and error
correction.
Prepare Test Reports This covers the CPCI BEXSUP during the BOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
Prepare Inputs to This covers the CPCI BEXSUP during the BOC
User, Operator and phase and includes the preparation of inputs
Data Base Administration to Users Manual (CDRL #135), Operators Manual
Manuals (CDRL #136), and Data Base Administrators
Manual (CDRL #137).
CPCI Listings This covers the CPCI BEXSUP during the BOC
As-built phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
Prepare Programmers This covers the CPCI BEXSUP during the BOC
Manual (Final) phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
Prepare Inputs to This covers the CPCI BEXSUP during the BOC
Training Manuals phase and includes the preparation inputs
to the various training manuals.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
IBM
RFP
WBS
WBS NO.
WBS NO.
TITLE
643300
4.3.2.5
Prepare As-Built
Part II Specs.
244000
4.4
Software Development
(IOC)
644001
4.4.1
Manage all SW Development
Activities
?
WBS
DESCRIPTION
This covers the CPCI BEXSUP during the IOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II specs.
(CDRL #142). The "as-built" version defines
the exact configuration of accepted computer
programs.
This covers the software development effort
during the IOC phase and includes the
following functions: management, preliminary
design, critical design, development, test,
and documentation.
phase.
This covers the efforts of second and third
level management functions required to
manage the SW development tasks in the IOC
Covers the effort required to ensure SW
architectural integrity during the IOC
phase.
6440006 4.4.1 Technical Support to Covers the Software development effort
Subcontract Management required to support Subcontract Management
to ensure technical oversight during the
IOC phase.
unmodified code from the UNIVAC
processor.
Covers the Purchase of COBOL code conversion
services during the IOC phase, to convert
644008 4.4.1 Library Control Covers the performance of routine source
library maintenance/control activities
during the IOC phase.
STAT
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: C
A-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
644009
4.4.1
644010
4.4.1
644012
4.4.1
644013
4.4.1
644014
4.4.1
644015
4.4.2.2
WBS WBS
TITLE DESCRIPTION
SW Builds and Releases
Perform software builder and maintain
software version control/documentation.
Maintain hard copy control. This element
cover the IOC phase.
Provide Inputs to Segment Prepare and maintains the software section
Development Plan of the Segment Development Plan during the
IOC phase.
Data Base Conversion Covers the conversion of the data base need
Design, Implementation, for BOC from DMS 1100 base to M204 base.
Verification Included are planning, design, conversion
utility creation, file conversion, and
verification. This element covers the IOC
phase.
Data Base Package This covers the preparation of the Data Base
Package (CDRL #151) which defines the actual
entries to be used for initializing each
data base item. This element covers the
IOC phase.
Data Base Support to This effort includes the Data Base
Development and Test Adminstration function and production of
and Verification the final version of the Data Base Admin-
stration Manual (CDRL #137) during the
IOC phase.
Prepare Built-to This covers the CPCI BEPPRE during the IOC
Part II Specs. and phase and includes the preparation of the
Conduct Internal CPCI Part II specification or the "build-to"
Design Review specification (CDRL #142) and participation
in internal design reviews.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
RFP
WBS NO.
WBS
TITLE
WBS
DESCRIPTION
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test Plan
(Final) - Appendix
for BEPPRE
Integrate and Test to
CPC level
Test at the CPC and
CPCI Levels
Develop SW Test
Procedures
This covers the CPCI BEPPRE during the IOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BEPPRE during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BEPPRE during the IOC
phase and includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI BEPPRE during the IOC
phase and includes the SW development
activities to integrate and test modules
up to CPC level.
This covers the CPCI BEPPRE during the IOC
phase and includes the formal testing by the
T&V group. This testing consist of PQT
testing of CPC/Strings and FQT testing of
complete CPCI's and its interface with other
CPCI.
This covers the CPCI BEPPRE during the IOC
phase and include procedures describing test
cases and acceptance criteria. Also in-
cludes detailed testing setups and environ-
ment data to be collected.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/0 5: Cl
A-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
644022
4.4.2.4
644023
4.4.2.4
644025
4.4.2.5
644026
4.4.2.5
644028
4.4.2.5
644029
4.4.2.2
WBS WBS
TITLE DESCRIPTION
Support Test and This covers the CPCI BEPPRE during the IOC
Verification phase and includes the activities of the
SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
Prepare Test Reports This covers the CPCI BEPPRE during the IOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
CPCI Listings As-built This covers the CPCI BEPPRE during the IOC
phase and includes the-listing of source
instruction statements and object code
for all CPC forming the CPCI (CDRL #150).
Prepare Programmers This covers the CPCI BEPPRE during the IOC
Manual (Final) phase includes the preparation of final
version of the Programmers Manual (CDRL
#138).
Prepare As-Built Part This covers the CPCI BEPPRE during the IOC
II Specs. phase and includes the preparation of the
"as-built" version of the CPCI Part II specs.
(CDRL #142). The "as-built" version defines
the exact configuration of accepted computer
programs.
Prepare Built-to Part This covers the CPCI BEMGMT during the IOC
II Specs. and Conduct phase and includes the preparation of the
Internal Design Review CPCI Part II specification or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test
Plan (Final) - Appendix
for BEMGMT
Integrate and Test
to CPC Level
WBS
DESCRIPTION
This covers the CPCI BEMGMT during the IOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BEMGMT during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BEMGMT during the IOC
phase and includes the development of source
code at the module level, its unit test
and debug.
This covers the CPCI BEMGMT during the IOC
phase and includes the SW development
activities to integrate and test modules
up to CPC level..
Test at the CPC
and CPCI Levels
Develop SW Test
Procedures
This covers the CPCI BEMGMT during the IOC
phase and includes the formal testing by
the T&V group. This testing consists of
PQT testing of CPC/Strings and FQT testing
of complete CPCI's and its interface with
other CPCI's.
This covers the CPCI BEMGMT during the IOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
IBM
WBS NO.
644036
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
RFP
WBS NO.
WBS
TITLE
WBS
DESCRIPTION
Support Test and
Verification
Prepare Test Reports
CPCI Listings As-built
Prepare Programmers
Manual (Final)
Prepare Inputs to
Training Manuals
Prepare As-Built Part
II Specs.
This covers the CPCI BEMGMT during the IOC
phase and includes the activities of the
SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
This covers the CPCI BEMGMT during the IOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
This covers the CPCI BEMGMT during the
IOC phase and includes the listing of
source instruction statements and object
code for all CPC forming the CPCI (CDRL #150).
This covers the CPCI BEMGMT during the IOC
phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
This covers the CPCI BEMGMT during the IOC
phase and includes the preparation inputs
to the various training manuals.
This covers the CPCI BEMGMT during the IOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
I-
? Approved For Release 2007/07/0 A-RDP84T00037R000300060001-2
5: Cl
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Built-to
Part II Specs. and
Conduct Internal
Design Review
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test
Plan (Final) - Appendix
for BERESU
Integrate and Test
to CPC Level
Test at the CPC
and CPCI Levels
WBS
DESCRIPTION
This covers the CPCI BERESU during the IOC
phase and includes the preparation of the
CPCI Part II specification or the "build-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BERESU during the IOC
phase and includes the preparation of the
preliminary programmers Manual (CDRL #138).
This covers the CPCI BERESU during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BERESU during the IOC
phase and includes the development of
source code at the module level, its unit
test and debug.
This covers the CPCI BERESU during the IOC
phase and includes the SW development
activities to integrate and test modules
up to CPC level.
This covers the CPCI BERESU during the IOC
phase and includes the formal testing by
the T&V group. This testing consist of
PQT testing of CPC/Strings and FQT testing
of complete CPCI's and its interface with
other CPCI's.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05 CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Develop SW Test
Procedures
Support Test and
Verification
Prepare Test Reports
Prepare Build-to
Part II specs. and
Conduct Internal Design
Review
WBS
DESCRIPTION
This covers the CPCI BERESU during the IOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
This covers the CPCI BERESU during the IOC
phase and includes the activities of the SW
Development group to support all formal tests
by the T&V group up to acceptance. Also
includes all problem analysis and error
correction.
This covers the CPCI BERESU during the IOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
This covers the CPCI BMANIP during the IOC
phase and includes the preparation of the
CPCI Part II specification or the "build-to"
specification (CDRL #142) and participation
in internal design reviews.
Prepare (Prelim.)
Programmers Manual
This covers the CPCI BMANIP during the IOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
Prepare CPCI Test
Plan (Final) - Appendix
for BMANIP
This covers the CPCI BMANIP during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05 CIA-RDP84T00037R000300060001-2 ?
w
IBM
RFP
WBS NO.
WBS NO.
644060
4.4.2.3
644061
4.4.2.3
644062
4.4.2.4
644063
4.4.2.4
644064
4.4.2.4
644065
4.4.2.4
WBS WBS
TITLE DESCRIPTION
Code and Unit Test This covers the CPCI BMANIP during the IOC
phase and includes the development of source
code at the module level, its unit test and
debug.
Integrate and Test This covers the CPCI BMANIP during the IOC
to CPC level phase and includes the SW development
activities to integrate and test module
up to CPC level.
Test at the CPC This covers the CPCI BMANIP during the IOC
and CPCI Levels phase and includes the formal testing by the
T&V group. The testing consists of PQT testing
of CPC/Strings and FQT testing of complete
CPCI's and its interface with other CPCI's.
Develop SW Test This covers the CPCI BMANIP during the IOC
Procedures phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Support Test and This covers the CPCI BMANIP during the IOC
Verification phase and includes the activities of the
SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error and correction.
Prepare Test Reports This covers the CPCI BMANIP during the IOC
phase and includes activities by the TO
group to prepare formal test reports on
results of PQT/FQT testing.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
0 Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
CPCI Listings As-built -
Prepare Programmers
Manual (Final)
Prepare As-Built
Part II Specs.
Prepare Built-to Part
II Specs. and Conduct
Internal Design Review
Prepare (Prelim.)
Programmers Manual
WBS
DESCRIPTION
This covers the CPCI BMANIP during the IOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
This covers the CPCI BMANIP during the IOC
phase and includes the preparation of final
version of the Programmers Manual (CDRL #138)
This covers the CPCI BMANIP during the IOC
phase and includes the presentation of the
"as-built" version of the CPCI Part II specs.
(CDRL #142). The "as-built" version defines
the exact configuration of accepted computer
programs.
This covers the CPCI BSTATR during the IOC
phase and includes the preparation of the
CPCI Part II specification or the "build-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BSTATR during the IOC
phases and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
Prepare CPCI Test
Plan (Final) - Appendix
for BSTATR
This covers the CPCI BSTATR during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BSTATR during the IOC
phase and includes the development of source
code at the module level, its unit test and
debug.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
V
IBM
WBS NO.
RFP
WBS NO.
644075
4.4.2.3
644076
4.4.2.4
644077
4.4.2.4
644078
4.4.2.4
644079
4.4.2.4
644082
4.4.2.5
WBS WBS
TITLE DESCRIPTION
Integrate and Test to This covers the CPCI BSTATR during the IOC
CPC Level phase and includes the SW development
activities to integrate and test module up
to CPC level.
Test at the CPC and This covers the CPCI BSTATR during the IOC
CPCI Levels phase and includes the formal testing by
the T&V group. This testing consist of
PQT testing of CPC/Strings and FQT testing
of complete CPCI's and its interface
with other CPCI's.
Develop SW Test This covers the CPCI BSTATR during the IOC
Procedures phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing setups and
environment data to be collected.
Support Test and This covers the CPCI BSTATR during the IOC
Verification phase and includes the activities of the
the SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and error
correction.
Prepare Test Reports This covers the CPI BSTATR during the IOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
CPCI Listings As-built This covers the CPCI BSTATR during the IOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Programmers
Manual (Final)
Prepare As-Built Part
II Specs.
Prepare Build-to
Part II Specs, and
Conduct Internal
Design Review
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test
Plan (Final) - Appendix
for BMMGMT
WBS
DESCRIPTION
This covers the CPCI BSTATR during the IOC
phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
This covers the CPCI BSTATR during the IOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL ##142). The "as-built" version
defines the exact configuration of accepted
computer programs.
This covers the CPCI BMMGMT during the IOC
phase and includes the preparation of the
CPCI Part II specification or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BMMGMT during the IOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138)
This covers the CPCI BMMGMT during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
Integrate and Test to
CPC Level
This covers the CPCI BMMGMT during the IOC
phase and includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI BMMGMT during the IOC
phase and includes the SW development
activities to integrate and test modules
up to CPC level.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
IBM
WBS NO.
RFP
WBS NO.
644105
4.4.2.4
644106
4.4.2.4
644107
4.4.2.4
644108
4.4.2.4
644110
4.4.2.5
644114
4.4.2.2
WBS WBS
TITLE DESCRIPTION
Test at the CPC and This covers the CPCI BMMGMT during the IOC
CPCI Levels phase and includes the formal testing by
the T&V group. This testing consists of PQT
testing of CPC/Strings and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test This covers the CPCI BMMGMT during the IOC
Procedures phase and includes procedures describing test
cases and acceptance criteria. Also includes
detailed testing steps and environment
data to be collected.
Support Test and This covers the CPCI BMMGMT during the IOC
Verification phase and includes the activities of the SW
Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and error
correction.
Prepare Test Reports This covers the CPCI BMMGMT during the IOC
phase and includes activities by the
T&V group to prepare formal test reports on
results of PQT/FQT testing.
CPCI Listings As-built This cover the CPCI BMMGMT during the IOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
Prepare Build-to This covers the CPCI BCCNTR during the IOC
Part II Specs. and phases and includes the preparation of the
Conduct Internal Design CPCI Part II specification or the "build-to"
Reviews specification (CDRL #142) and participation
in internal design reviews.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test
Plan (Final) - Appendix
for BCCNTR
Integrate and Test to
CPC Level
WBS
DESCRIPTION
This covers the CPCI BCCNTR during the IOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BCCNTR during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BCCNTR during the
IOC phase and includes the development
of source code at the module level,
its unit test and debug.
This covers the CPCI BCCNTR during the IOC
phase and includes the SW development
activities to integrate and test modules up
to CPC level.
Test at the CPC and
CPCI Levels
Develop SW Test
Procedures
This covers the CPCI BCCNTR during the IOC
phase and includes the formal testing by
the T&V group. This testing consists of
PQT testing of CPC/Strings and FQT testing
of complete CPCI's and its interface
with other CPCI's.
This covers the CPCI BCCNTR during the IOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
644121
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
RFP
WBS
WBS
WBS NO.
TITLE
DESCRIPTION
4.4.2.4
Support Test and
This covers the CPCI BCCNTR during the IOC
Verification
phase and includes the activities of the
SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and
error correction.
644122 4.4.2.4 Prepare Test Reports This covers the CPCI BCCNTR during-the IOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
644123 4.4.2.5 Prepare Inputs to User, This covers the CPCI BCCNTR during the IOC
Operator, and Data Base phase and includes the preparation of inputs
Administration Manuals to Users Manual (CDRL #135), Operators
Manual (CDRL #136), and Data Base
Administrators Manual (CDRL #137).
644124 4.4.2.5 CPCI Listings As-built This covers the CPCI BCCNTR during the IOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
644126 4.4.2.5 Prepare Inputs to This covers the CPCI BCCNTR during the IOC
Training Manuals phase and includes the preparation inputs
to the various training manuals.
644127 4.4.2.5 Prepare As-Built Part This covers the CPCI BCCNTR during the IOC
II Specs. phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Build-to
Part II Specs. and
Conduct Internal
Design Review
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test
Plan (Final) - Appendix
for BQEURY
Integrate and Test to
CPC Level
WBS
DESCRIPTION
This covers the CPCI BQUERY during the IOC
phase and includes the preparation of the
CPCI Part II specification or the "build-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BQEURY during the IOC
phases and includes the preparation of the
preliminary programmers Manual (CDRL #138).
This-covers the CPCI BQUERY during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BQEURY during the IOC
phase and. includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI BQUERY during, the IOC
phase and includes the SW development
activities to integrate and test modules up to
CPC level.
Test at the CPC and
CPCI Levels
Develop SW Test
Procedures
This covers the CPCI BQUERY during the IOC
phase and includes the formal testing by the
T&V group. This testing consists of PQT testing
of CPC/Strings and FQT testing of complete CPCI's
and its interface with other CPCI's.
This covers the CPCI BQEURY during the IOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
0 Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
644135
4.4.2.4
644136
4.4.2.4
644137
4.4.2.5
644138
4.4.2.5
644139
4.4.2.5
644140
4.4.2.5
WBS WBS
TITLE DESCRIPTION
Support Test and This covers the CPCI BQEURY during the IOC
Verification phase and includes the activitives of the
SW Development group to support all formal
tests by the T&V group up to acceptance.
Also includes all problem analysis and error
correction.
Prepare Test Reports This covers the CPCI BQUERY during the IOC
phase and include's activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
Prepare Inputs to User, This covers the CPCI BQUERY during the IOC
Operato,r and Data Base phase and includes the preparation of inputs
Administration Manuals to Users Manual (CDRL #135), Operators Manual
(CDRL #136), and Data Base Administrators
Manual (CDRL #137).
CPCI Listings This covers the CPCI BQUERY during the IOC
As-built phase and includes the listing of source
instuction statements and object code for
all CPC forming the CPCI (CDRL #150).
Prepare Programmers This covers the CPCI BQUERY during the IOC
Manual (Final) phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
Prepare Inputs to This covers the CPCI BQUERY during the IOC
Training Manuals phase and includes preparation inputs to
the various training manuals.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 is
V
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare As-Built
Part II Specs.
Prepare Build-to
Part II Specs. and
Conduct Internal
Design Review
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test
Plan (Final) -
Appendix for BAPPLS
WBS
DESCRIPTION
This covers the CPCI BQUERY during the IOC
phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
This covers the CPCI BAPPLS during the IOC
phase and includes the preparation of the
CPCI Part II specification or the "build-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BAPPLS during the IOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BAPPLS during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
Integrate and Test to
CPC Level
This covers the CPCI BAPPLS during the IOC
phase and includes the development of
source code at the module level, its unit
test and debug.
This covers the CPCI BAPPLS during the IOC
phase and includes the SW development
activities to integrate and test modules up
to CPC level.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
IBM
WBS NO.
RFP
WBS NO.
644147
4.4.2.4
644148
4.4.2.4
644149
4.4.2.4
644150
4.4.2.4
644152
4.4.2.5
644153
4.4.2.5
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
WBS
DESCRIPTION
?
Test at the CPC and This covers the CPCI BAPPLS during the IOC
CPCI Levels phase and includes the formal testing by the
T&V group. This testing consists of PQT
testing of CPC/Strings and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test This covers the CPCI BAPPLS during the IOC
Procedures phase and includes procedures describing
test cases and acceptance criteria.
Also includes detailed testing steps
and environment data to be collected.
Support Test and This covers the CPCI BAPPLS during the IOC
Manual (Final) phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
phase and includes the activities of the SW
Development group to support all formal tests
by the T&V group up to acceptance. Also
includes all problem analysis and error
correction.
Prepare Test Reports This covers the CPCI BAPPLS during the IOC
phase and includes activities by the TO
group to prepare formal test reports on
results of PQT/FQT testing.
CPCI Listings As-built This covers the CPCI BAPPLS during the IOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150)
Prepare Programmers This covers the CPCI BAPPLS during the IOC
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05 CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Inputs to
Training Manuals
Prepare As-Built Part
II Specs.
Prepare Build-to
Part II Specs. and
Conduct Internal
Reviews
Prepare (Prelim.)
Programmers Manual
Prepare CPCI Test Plan
(Final) - Appendix
for BDMAPS
WBS
DESCRIPTION
This covers the CPCI BAPPLS during the'IOC
phase and includes the preparation inputs
to various training manuals.
This covers the CPCI BAPPLS during the IOC
phase and includes the preparation of the
the "as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
This covers the CPCI BDMAPS during the IOC
phase and includes the preparation of the
CPCI Part II specification or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BDMAPS during the IOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BDMAPS during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
Integrate and Test
to CPC Level
This covers the CPCI BDMAPS during the IOC
phase and includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI BDMAPS during the IOC
phase and includes the SW development
activities to integrate and test modules.
up to CPC level.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
RFP
WBS NO.
WBS NO.
644161
4.4.2.4
644162
4.4.2.4
644163
4.4.2.4
644164
4.4.2.4
644166
4.4.2.5
644167
4.4.2.5
WBS WBS
TITLE DESCRIPTION
Test at the CPC and This covers the CPCI BDMAPS duirng the IOC
CPCI Levels phase and includes the formal testing by the
T&V group. This testing consist of PQT
testing of CPC/Ships and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test This covers the CPCI BDMAPS duringthe IOC
Procedure phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Support Test and This covers the CPCI BDMAPS duirng the IOC
Verification phase and includes the activities of the SW
Development group to support all formal tests
by the T&V group up to acceptance. Also
includes all problem analysis and error
correction.
Prepare Test Reports This covers the CPCI BDMAPS durin gthe IOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
CPCI Listings As-built This covers the CPCI BDMAPS during the IOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150)
Prepare Programmers This covers the CPCI BDMAPS during the IOC
Manual (Final) phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Inputs to
Training Manuals
Prepare As-Built Part
II Specs.
Prepare Build-to
Part II Specs. and
Conduct Internal
Reviews
Prepare (Prelim)
Programmers Manual
Prepare CPCI Test Plan
(Final) - Appendix
for BTTDEV
WBS
DESCRIPTION
This covers the CPCI BDMAPS during the IOC
phase and includes the preparation inputs
to various training manuals.
This covers the CPCI BAPPLS during the IOC
phase and includes the preparation of the
the "as-built" version of the CPCI Part II
specs (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
This covers the CPCI BTTDEV during the IOC
phase and includes the preparation of the
CPCI Part II Specification or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BTTDEV during the IOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI BTTDEV during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
Integrate and Test
to CPC Level
This covers the CPCI BTTDEV during the IOC
phase and includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI BTTDEV during the IOC
phase and includes the SW development
activities to integrate and test modules
up to CPC level.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 is
w
IBM
RFP
WBS NO.
WBS NO.
644175
4.4.2.4
644176
4.4.2.4
644177
4.4.2.4
644178
4.4.2.4
644180
4.4.2.5
644181
4.4.2.5
WBS WBS
TITLE DESCRIPTION
Test at the CPC and This covers the CPCI BTTDEV during the IOC
CPCI Levels phase and includes the formal testing by the
T&V group. This testing consist of PQT
testing of CPC/Ships and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test This covers the CPCI BTTDEV during the IOC
Procedure phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Support Test and This covers the CPCI BTTDEV during the IOC
Manual (Final)
Prepare Test Reports
CPCI Listings As-built
Prepare Programmers
phase and includes the activities of the SW
Development group to support all formal tests
by the T&V group up to acceptance. Also
includes all problem analysis and error
correction.
This covers the CPCI BTTDEV during the IOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
This covers the CPCI BTTDEV during the IOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150)
This covers the CPCI BTTDEV during the IOC
phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
4.4.2.2
WBS
TITLE
Prepare Inputs to
Training Manuals
Prepare As-Built Part
II Specs.
Prepare Build-to
Part II Specs. and
Conduct Internal
Reviews
Prepare (Prelim)
Programmers Manual
Prepare CPCI Test Plan
(Final) - Appendix
for WAPPLS
Integrate and Test
to CPC Level
WBS
DESCRIPTION
This covers the CPCI BTTDEV during the IOC
phase and includes the preparation inputs
to various training manuals.
This covers the CPCI BTTDEV during the IOC
phase and includes the preparation of the
the "as-built" version of the CPCI Part II
specs (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
This covers the CPCI WAPPLS during the IOC
phase and includes the preparation of the
CPCI Part II Specification or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI WAPPLS during the IOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
This covers the CPCI WAPPLS during the IOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI WAPPLS.during the IOC
phase and includes the development of source
code at the module level, its unit test and
debug.
This covers the CPCI WAPPLS during the IOC
phase and includes the SW development
activities to integrate and test modules
up to CPC level.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 is
w
IBM
RFP
WBS NO.
WBS NO.
644189
4.4.2.4
644190
4.4.2.4
644191
4.4.2.4
644192
4.4.2.4
644193
4.4.2.5
644194
4.4.2.5
WBS WBS
TITLE DESCRIPTION
Test at the CPC and This covers the CPCI WAPPLS during the IOC
CPCI Levels phase and includes the formal testing by the
T&V group. This testing consist of PQT
testing of CPC/Ships and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test This covers the CPCI WAPPLS during the IOC
Procedure phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Support Test and
Verification
This covers the CPCI WAPPLS during the IOC
phase and includes the activities of the SW
Development group to support all formal tests
by the T&V group up to acceptance. Also
includes all problem analysis and error
correction.
Prepare Test Reports This covers the CPCI WAPPLS during the IOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing...
Prepare Inputs to user, This covers the CPCI WAOOKS during the IOC
Operator and Data Base phase and includes the preparation of inputs
Administration Manuals to Users Manual (CDRL #135), Operators
Manual (CDRL #136), and Data Base
Adminstrator Manual (CDRL #137).
CPCI Listings As-built This covers the CPCI WAPPLS during the IOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI.(CDRL #150)
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
V
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Prepare Programmers
Manual (Final)
Prepare Inputs to
Training Manuals
Prepare As-Built Part
II Specs.
Test at the CPC and
CPCI Levels
WBS
DESCRIPTION
This covers the CPCI WAPPLS during the IOC
phase and includes the preparation of final
version of the Programmers Manual (CDRL #138).
This covers the CPCI WAPPLS during the IOC
phase and includes the preparation inputs
to various training manuals.
This covers the CPCI WAPPLS during the IOC
phase and includes the preparation of the
the "as-built" version of the CPCI Part II
specs (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
This covers the CPCI BEXSUP during the IOC
phase and includes-the formal testing by the
T&V group. This testing consist of PQT
testing of CPC/Ships and FQT testing of
complete CPCI's and its interface with
other CPCI's.
Develop SW Test
Procedure
Support Test and
Verification
This covers the CPCI BEXSUP during the IOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
This covers the CPCI BEXSUP during the IOC
phase and includes the activities of the SW
Development group to support all formal tests
by the T&V group up to acceptance. Also
includes all problem analysis and error
correction.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
RFP
WBS NO.
WBS NO.
644206
4.4.2.4
245000
4.5
645001
4.5.1
645004
4.5.1
645005
4.5.1
645008
4.5.1
WBS WBS
TITLE DESCRIPTION
Prepare Test Reports
Software Development (FOC)
Manage All SW Development
SW Architecture
This covers the CPCI BEXSUP during the IOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
This covers the software development effort
during the FOC phase and includes the follow-
ing functions: management, preliminary
design, critical design, development, test,
and documentation.
This covers the efforts of record and
third level management functions required
to manage the SW development tasks in the
FOC phase.
Covers the effort required to ensure SW
architectural integrity during the FOC
phase.
Technical Support to Sub- Covers the software development effort
contract Management required to support Subcontract Manage-
ment to ensure technical oversight during
the FOC phase.
Library Control Covers the performance of routine source
library maintenance/control activities
during the FOC phase.
Perform software builds and maintains
software version control/documentation.
Maintain hard copy control. This element
covers the FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 .
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Provide Inputs to Segment
Development Plan
Data Base Package
Data Base Support to
Development and Test and
Verification
Prepare Built-to Part II
Specs. and Conduct Internal
Design Review
Prepare (Prelim.)
Programmers Manual
WBS
DESCRIPTION
Prepares and maintains the software section
of the Segment Development Plan during the
FOC phase.
This covers the preparation of the Data Base
Package (CDRL #151) which defines the actual
entries to be used for initializing each data
base item. This element covers the FOC phase.
This effort includes the Data Base Admin-
istration function and production of the
final version of the Data Base Administra-
tion Manual (CDRL #137) during the FOC base.
This covers the CPCI BMMGMT during the FOC
phase and includes the preparation of the
CPCI Part II specification or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
This covers the CPCI BMMGMT during the FOC
phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
Prepare CPCI Test Plan
(Final) - Appendix for
BMMGMT
This covers the CPCI BMMGMT during the FOC
phase and includes the preparation of the
final CPCI Test Plan (CDRL #131).
This covers the CPCI BMMGMT during the FOC
phase and includes the development of
source code at the module level, its unit
test and debug.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
RFP
WBS NO.
WBS NO.
645019
4.5.2.3
645020
4.5.2.4
645021
4.5.2.4
645022
4.5.2.4
645023
4.5.2.4
645024
4.5.2.5
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS WBS
TITLE DESCRIPTION
Integrate and Test to CPC This covers the CPCI BMMGMT during the FOC
Level phase and includes the SW development
activities to integrate and test modules
up to CPC level.
Test at the CPC and CPCI This covers BMMGMT during the FOC phase
Levels and includes the formal testing by the T&V
group. This testing consist of PQT testing
of CPC/String and FQT testing of complete
CPCI's and its interface with other CPCI's.
Develop SW Test Procedures
This covers the CPCI BMMGMT during the FOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Support Test and Verification
This covers the CPCI BMMGMT during
the FOC phase and includes the activities
of the SW Development group to support all
formal tests by the T&V group up to accept-
ance. Also includes all problem analysis
and error correction.
Prepare Test Reports This covers the CPCI BMMGMT during the FOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
Prepare Inputs to User, This covers the CPCI BMMGMT during the FOC
Operator and Data Base phase and includes the preparation of inputs
Administration Manuals to Users Manual (CDRL #135), Operators
Manual (CDRL #136), and Data Base Admin-
istrators Manual (CDRL #137).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
RFP
WBS NO.
WBS NO.
645025
4.5.2.5
645026
4.5.2.5
645027
4.5.2.5
645028
4.5.2.5
645029
4.5.2.2
645030
4.5.2.2
645031
4.5.2.2
WBS WBS
TITLE DESCRIPTION
CPCI Listings As-built This covers the CPCI BMMGMT during the FOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
Prepare Programmers Manual This covers the CPCI BMMGMT during the FOC
(Final) phase and includes the preparation of final
version of the Programmers Manual (CDRL
#138).
Prepare Inputs to Training This covers the CPCI BMMGMT during the FOC
Manuals phase and includes the preparation inputs
to the various training manuals.
Prepare As-Built Part II This covers the CPCI BMMGMT during the FOC
Specs. phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
Prepare Built-to Part II This covers the CPCI BCCNTR during the FOC
Specs. and Conduct Internal phase and includes the preparation of the
Design Review CPCI Part II Specification or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
Prepare (Prelim) This covers the CPCI BCCNTR during the FOC
Programmers Manual phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
Prepare CPCI Test Plan This covers the CPCI BCCNTR during the FOC
(Final) - Appendix for phase and includes the preparation of the
BMMGMT final CPCI Test Plan (CDRL #131).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
645032
4.5.2.3
645033
4.5.2.3
645034
4.5.2.4
645035
4.5.2.4
645036
4.5.2.4
645037
4.5.2.4
WBS WBS
TITLE DESCRIPTION
Code and Unit Test This covers the CPCI BCCNTR during the FOC
phase and includes the development of
source code at the module level, its unit
test and debug.
Integrate and Test to CDC This covers the CPCI BCCNTR during the FOC
Level phase and includes the SW development
activities to integrate and test modules
up to CPC level.
Test at the CPC and CPCI This covers CPCI BCCNTR during-the FOC
Levels phase and includes the formal testing by the
T&V group. This testing consist of PQT
testing of CPC/Strings and FQT testing of com-
plete CPCI's and its interfaces with other
CPCI's.
Develop SW Test Procedures This covers the CPCI BCCNTR during the FOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Support Test and Verification This covers the CPCI BCCNTR during the
FOC phase and includes the activities of
the SW Development group to support all
formal tests by the T&V group up to accept-
ance. Also includes all problem analysis
and error correction.
Prepare Test Reports This covers the CPCI BCCNTR during the FOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
RFP
WBS NO.
WBS NO.
645038
4.5.2.5
645039
4.5.2.5
645040
4.5.2.5
645042
4.5.2.5
645043
4.5.2.2
645044
4.5.2.2
WBS WBS
TITLE DESCRIPTION
Prepare Inputs to User, This covers the CPCI BCCNTR during the FOC
Operator and Data Base phase and includes the preparation of inputs
Administration Manuals to Users Manual (CDRL #135), Operators
Manual (CDRL #136), and Data Base Admin-
istrators Manual (CDRL #137).
CPCI Listings As-built This covers the CPCI BCCNTR during the FOC
phase and includes the listing of source
instruction statements and object code for
all CPC forming the CPCI (CDRL #150).
Prepare Programmers Manual This covers the CPCI BCCNTR during the FOC
(Final) phase and includes the preparation of final
version of the Programmers Manual (CDRL
#138).
Prepare As-Built Part II This covers the CPCI BCCNTR during the FOC
Specs. phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs. (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
Prepare Built-to Part II This covers the CPCI BTTDEV during the FOC
Specs. and Conduct Internal phase and includes the preparation of the
Design Review CPCI Part II specification1or the "built-to"
specification (CDRL #142) and participation
in internal design reviews.
Prepare (Prelim.) This covers the CPCI BTTDEV during the FOC
Programmers Manual phase and includes the preparation of the
preliminary Programmers Manual (CDRL #138).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
645045
4.5.2.2
645046
4.5.2.3
645047
4.5.2.3
645048
4.5.2.4
645049
4.5.2.4
645050
4.5.2.4
WBS WBS
TITLE DESCRIPTION
Prepare CPCI Test Plan This covers the CPCI BTTDEV during the FOC
(Final) - Appendix for phase and includes the preparation of the
BTTDEV final CPCI Test Plan (CDRL #131).
Code and Unit Test This covers the CPCI BTTDEV during the FOC
phase and includes the development of
source code at the module level, its unit
test and debug.
Integrate and Test to CPC This covers the CPCI BTTDEV during the FOC
Level phase and includes the SW development
activities to integrate and test modules
up to CPC level.,
Test at the CPC and CPCI This covers CPCI BTTDEV during the FOC phase
Levels and includes the formal testing by the T&V
group. This testing consist of PQT testing
of CPC/String and FQT testing of complete
CPCI's and its interface with other CPCI's.
Develop SW Test Procedures This covers the CPCI BTTDEV during the FOC
phase and includes procedures describing
test cases and acceptance criteria. Also
includes detailed testing steps and
environment data to be collected.
Support Test and Verification This covers the CPCI BTTDEV during the
FOC phase and includes the activities
of the SW Development group to support all
formal tests by the T&V group up to accept-
ance. Also includes all problem analysis
and error correction.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
RFP
WBS NO.
WBS NO.
645051
4.5.2.4
645052
4.5.2.5
645053
4.5.2.5
645056
4.5.2.5
WBS WBS
TITLE DESCRIPTION
Prepare Test Reports This covers the CPCI BTTDEV during the FOC
phase and includes activities by the T&V
group to prepare formal test reports on
results of PQT/FQT testing.
Prepare Inputs to User, This covers the CPCI BTTDEV during the FOC
Operator and Data Base phase and includes the preparation of inputs
Administration Manuals to Users Manual (CDRL #135), Operators
Manual (CDRL #136), and Data Base Admin-
istrators Manual (CDRL #137).
CPCI Listings As-built This covers the CPCI BTTDEV during the FOC
phase and includes the listing of source
instruction statements and object code for.
all CPC forming the CPCI (CDRL #150).
Prepare As-Built Part II This covers the CPCI BTTDEV during the FOC
Specs phase and includes the preparation of the
"as-built" version of the CPCI Part II
specs (CDRL #142). The "as-built" version
defines the exact configuration of accepted
computer programs.
Hardware Development
This category covers the hardware develop-
ment effort and includes: management,
preliminary design, critical design, devel-
opment test and documentation functions.
646100 4.6.1 Manage All Hardware This covers the efforts of second and third
Development level management required in order to
manage the hardware development tasks in
the BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
RFP
WBS WBS
WBS NO.
WBS NO.
TITLE DESCRIPTION
646200
4.6.2.1
Accomplish (Prelim.) CI This covers the Cl BASIC IWS during the
Design and Reports BOC phase and includes the design effort
Analysis and Allocation which provides for analysis of the Segment
646203
4.6.2.2
Accomplish Detailed
Design of CI
646206
4.6.2.3
Accomplish Fabrication of
All Manufactured HW
Design Spec. functions and performance and
their allocation to individual CI's. This
effort occurs after completion of the Design
Concept Review and leads to generating of
the CI spec.
This covers the Cl BASIC IWS during the
BOC phase and includes the effort, fol-
lowing PDR approval which provides for
detailed design including identification of
all components and assemblies.
up a manufacturing line including tooling
and test equipment, procure components,
and accomplish the manufacture and unit
test and checkout of the integrated
work stations.
This covers the CI BASIC IWS during
the BOC phase and includes the
effort, following CDR approval, to set
646212 4.6.2.4 Prepare Hardware Test and This covers the CI BASIC IWS during
TEMPEST Test Procedures the BOC phase and includes the
effort, based on approved Segment Test
Plan, to prepare detailed test procedures
describing test cases and acceptance
criteria. Also included is the effort to
test to TEMPEST qualify all solution.
646253 4.6.2.5 Prepare Equipment Operation This covers the CI BASIC IWS during
and Maintenance Manuals the BOC phase and includes the
preparation of the Equipment Operation
and Maintenance Manuals (CDRL #148).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
646232 4.6.2.5
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
RFP
WBS NO.
WBS
TITLE
Accomplish (Prelim.) CI
Design and Reports
Analysis and Allocation
WBS
DESCRIPTION
This covers the CI Enhanced IWS during
the BOC phase and including the design
effort which provides for analysis of the
Segment Design Spec functions and performance
and their allocation to individual CI's.
This effort occurs after completion of the
Design Concept Review and leads to generating
of the CI spec.
Prepare CI Specification
and Conduct Internal Design
Reviews
Prepare Built-to Component
Specs and Conduct Internal
Design Review
Support Test and Verification
Prepare Equipment Operation
and Maintenance Manuals
This covers the CI Enhanced IWS during the
BOC phase and includes the preparation of
the CI Specification (CDRL #143) and the
performance of internal design reviews.
This covers the Cl Enhanced IWS during
the BOC phase and includes the
effort, following PDR approval, which
provides for the generation of build-
to component specs and the performance
of internal design reviews.
This covers the CI Enhanced IWS during
the BOC phase and includes the activities
of the HW Development group to support all
formal tests by the, T&V group up to
acceptance. Also includes all problem
analysis and error correction.
This covers the CI Enhanced IWS during
the BOC phase and includes the preparation
of the Equipment Operation and Maintenance
Manuals (CDRL #148).
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
IBM
WBS NO.
RFP
WBS NO.
646233
4.6.2.5
646234
4.6.2.5
647100
4.7.1
647222
4.7.2.3
647226
4.7.2.4
647230
4.7.2.2
Approved For Release 2007/07/05: CIA-RDP84TOO037ROO0300060001-2
w
WBS
TITLE
WBS
DESCRIPTION
?
Prepare Inputs to Segment/ This covers the CI Enhanced IWS during
System Operation and User the BOC phase and includes the preparation
Manuals of inputs to the Segment/System Operation
and User Manuals (CDRL #136 and CDRL #135
respectively).
Prepare Inputs to Training This covers the CI Enhanced IWS during
Manuals the BOC phase and includes the preparation
of inputs to the various training manuals
(CDRL #146).
Manage All Hardware This covers the efforts of second and
Development third level management required in order
to manage the hardware development tasks
in the IOC phase.
Prepare Manufacturing This covers the CI Enhanced IWS during
Drawing Packages the IOC phase and includes the preparation
of manufacturing drawing packages.
Support Test and Verification This covers the CI Enhanced IWS duirng
the IOC phase and includes the activities
of the HW Development group to support all
formal tests by the T&V group up to
acceptance. Also includes all problem
analysis and error correction.
Accomplish Detailed This covers the CI Full Capability IWS
Design of CI during the IOC phase and includes the effort,
following PDR approval which provides for
detailed design, including identification of
all components and assemblies.
Approved For Release 2007/07/05: CIA-RDP84TOO037ROO0300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
647231
4.7.2.2
647232
4.7.2.2
647242
4.7.2.5
648100
4.8.1
648232
4.8.2.2
249000
4.9
WBS WBS
TITLE DESCRIPTION
Prepare Built-to Component This covers the CI Full Capability IWS
Specs. and Conduct Internal during the IOC phase and includes the
Design Review effort, following PDR approval, which
provides for the generation of build-
to component specs and the performance
of internal design reviews.
Accomplish Critical Design This covers the CI Full Capability IWS
of Commercial Product during the IOC phase and includes the
Modification engineering effort to analyze and design
any D/C segment peculiar modifications to
commercial products used in the work
station configuration.
Prepare Equipment Operation This covers the CI Full Capability IWS
and Maintenance Manuals during the IOC phase and includes the
preparation of the Equipment Operation
and Maintenance Manuals (CDRL #148).
Manage All Hardware This covers the efforts of second and
Development third level management required to
manage the hardware development tasks
in the FOC phase.
Accomplish Critical Design This covers the CI Full Capability IWS
of Commercial Product during the FOC phase and includes the
Modifications engineering effort to analyze and design
any D/C segment peculiar modifications to
commercial products used in the work
station configuration.
Automated Data Processing This category covers the acquisition of all
Equipment (ADPE) Hardware ADPE, the acceptance testing of ADPE, and
and Software the modification, installation, testing and
maintenance of GFE.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
v 649103
RFP
WBS NO.
WBS
TITLE
Manage All ADPE Procurement
Activities
Manage All ADPE Procurement
Activities
Manage All ADPE Procurement
Activities
Provide and Enforce All
Procurement Practices,
Standards and Conventions
Provide and Enforce All
Procurement Practices,
Standards and Conventions
WBS
DESCRIPTION
This covers the second and third level
management of all the activities asso-
ciated with the ADPE category during the
BOC phase.
This covers the second and third level
management of all the activities associated
with the ADPE category during the IOC phase.
This covers the second and third level
management of all the activities associated
with the ADPE category during the FOC phase.
This covers the management activities asso-
ciated with providing and enforcing all
procurement practices, standards, and con-
ventions during the BOC phase.
This covers the management activities asso-
ciated with providing and enforcing all
procurement practices, standards, and con-
ventions during the IOC phase.
Provide and Enforce All
Procurement Practices,
Standards and Conventions
Project Labor to Support
Procurement
This covers the management activities asso-
ciated with providing and enforcing all
procurement practices, standards, and con-
ventions during the FOC phase.
This covers the effort by the SW Development
group to provide support in the procurement
of commercial CPCI's. This element covers
the BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
649107
4.9.1
649108
4.9.1
649109
4.9.1
649110
4.9.1
649111
4.9.1
649112
4.9.1
649113
4.9.1
WBS WBS
TITLE DESCRIPTION
Project Labor to Support This covers the effort by the SW Development
Procurement group to provide support in the procurement
of commercial CPCI's. This element covers
the IOC phase.
Project Labor to Support This covers the effort by the SW Development
Procurement group to provide support in the procurement
of commercial CPCI's. This element covers
the FOC phase.
Procurement This covers the monthly licensing and
service costs of commercial CPCI's during
the BOC phase, prior to commencement of the
BOC O&M period.
Procurement This covers the monthly licensing and
service costs of commercial CPCI's during
the IOC phase, prior to commencement of the
IOC O&M period.
Procurement This covers the monthly licensing and
service costs of commercial CPCI's during
the FOC phase, prior to commencement of the
FOC O&M period.
Project Labor to Support This covers the effort by the System
Procurement Engineering group to provide support in
the procurement of commercial Cl's during
the BOC phase.
Project Labor to Support This covers the effort by the System
Procurement Engineering group to provide support in
the procurement of commercial CI's during
the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05 CIA-RDP84T00037R000300060001-2
w
IBM
WBS NO.
RFP
WBS NO.
649115
4.9.1
649116
4.9.1
649300
4.9.3
649301
4.9.3
649303
4.9.3
241000
4.10
WBS WBS
TITLE DESCRIPTION
Procure This covers the purchase cost of commercial
Cl's during the BOC phase, prior to com-
mencement of the BOC O&M period.
Procure This covers the purchase cost of commercial
CI's during the IOC phase, prior to com-
mencement of the IOC O&M period.
Install and Checkout GFE This covers the effort to install and
checkout GFE during the BOC phase.
Principle item is the Local Area Network
equipment installed at the development
facility.
Provide GFE Maintenance
Provide GFE Maintenance
Test and Verification
This covers the effort to provide main-
tenance of GFE during the BOC phase.
This covers the effort to provide mainte-
nance of GFE during the FOC phase.
management, test support, integration test,
and factory pre-ship test. All test and
verification activities will be conducted
at the development site.
This covers the formal and informal testing
of software, hardware, and system components
that make up the D/C Segment. Included
in this element are the following: test
641010 4.10.1 Provide Management of Segment This covers the technical management of
Test Activities the segment test activities during the BOC
phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
641011
641012
4.10.1
4.10.1
Prepare Test Plans
Prepare Test Procedures
641013
4.10.1
Prepare Test Plan for GFE
o
Equipment
641020
4.10.2
Provide Necessary Software
to Support Integrated Testing
641021
4.10.2
Provide Necessary Hardware
to Support Integrated Testing
641022
4.10.2
Provide Necessary Data to
Support Integrated Testing
641030
4.10.3
Accomplish Inter-CPCI Testing
WBS
DESCRIPTION
This is the activity to write detailed Test
Plan (CDRL #131) covering all formal T&V
steps at the development site during the
BOC phase.
This is the effort required to develop
test procedures and covers test cases for
hardware subsystem test and site installa-
tion and checkout. Also included are
hardware/software integration, and site
tests including acceptance tests. This
element covers the BOC phase.
This covers the effort required to write
detailed test plans for the UNIVAC 1100/81,
GFE test, and Local Area Network communica-
tion interface during the BOC phase.
This covers TPNS script generation for
hardware/software integration and stress
testing during the BOC phase.
This covers the effort to plan and provide
test configuration and the integration of
the test computer and LAN for execution of
TPNS during the BOC phase.
This covers the effort to provide data to
be used in support of the testing efforts
detailed in 641020 and 641021. This
element covers the BOC phase.
This covers the checkout and verification
of integrated CPCI's using external
interface simulators during the BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
V
IBM
WBS NO.
RFP
WBS NO.
641031
4.10.3
641032
4.10.3
641033
4.10.3
641040
4.10.4
641041
4.10.4
641110
4.11.1
641111
4.11.1
WBS WBS
TITLE DESCRIPTION
Accomplish Inter-CI Testing This is the checkout and debug of the CI
interfaces (processor, LAN, IWS) with
diagnostic software during the BOC phase.
Accomplish Integrated CPCI/ This covers stress testing the integrated
CI Testing hardware/software system with the test
computer and TPNS scripts during the BOC
phase.
Provide Integration Test This is the effort to prepare reports of
Reports the results of tests performed on the
integrated CPCI's during the BOC phase.
Perform Formal Preship Test This covers the final preship test including
factory acceptance witnessed by the Govern-
ment and support to CM audit during the BOC
phase.
Provide Preship Test Report This covers the factory acceptance test
report during the BOC phase.
Provide Management of This covers the technical management of
Segment Test Activities the Segment Test activities during the
IOC phase.
Prepare Test Plans This is the activity to write detailed
Test Plan (CDRL #131) covering all formal
T&V steps at the development site during
the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
641112
4.11.1
641113
4.11.1
641120
4.11.2
641121
4.11.2
641122
4.11.2
641130
4.11.3
641131
4.11.3
WBS WBS
TITLE DESCRIPTION
Prepare Test Procedures This is the effort required to develop test
procedures and covers test cases for hardware
subsystem test and site installation and
checkout. Also included are hardware/
software integration, and site tests includ-
ing acceptance tests. This element covers
the IOC phase.
Prepare Test Plan for GFE This covers the effort required to write
Equipment detailed test plans for the UNIVAC 1100/81,
GFE test, and Local Area Network communi-
cation interface during the IOC phase.
Provide Necessary Software This covers TPNS script generation for
to Support Integrated Testing hardware/software integration and stress
testing during the IOC phase.
Provide Necessary Hardware This covers the effort to plan and provide
to Support Integrated Testing test configuration and the integration of
the test computer and LAN for execution of
TPNS during the IOC phase.
Provide Necessary Data to This covers the effort to provide data to
Support Integrated Testing be used in support of the testing efforts
detailed in 641120 and 641121. This
element covers the IOC phase.
Accomplish Inter-CPCI Testing This covers the checkout and verification
of integrated CPCI's using external
interface simulators during the IOC phase.
Accomplish Inter-CI Testing This is the checkout and debug of the CI
interfaces (processor, LAN, IWS) with
diagnostic software during the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05 CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
641132
4.11.3
641133
4.11.3
641140
4.11.4
641141
4.11.4
641210
4.12.1
641211
4.12.1
641212
4.12.1
WBS WBS
TITLE DESCRIPTION
Accomplish Integrated CPCI/ This covers stress testing the integrated
CI Testing hardware/software system with the test
computer and TPNS scripts during the IOC
phase.
Provide Integration Test This is the effort to prepare reports of
Reports the results of tests performed on the
integrated CPCI's during the IOC phase.
Perform Formal Preship Test This covers the final preship test including
factory acceptance witnessed by the Govern-
ment and support to CM audit during the IOC
phase.
Provide Preship Test Report This covers the factory acceptance test
report during the IOC phase.
Provide Management of This covers the technical management of
Segment Test Activities the Segment Test activities during the
FOC phase.
Prepare Test Plans This is the activity to write detailed
Test Plan (CDRL #131) covering all formal
T&V steps at the development site during
the FOC phase.
Prepare Test Procedures This is the effort required to develop test
procedures and covers test cases for hardware
subsystem test and site installation and
checkout. Also included are hardware/
software integration, and site tests includ-
ing acceptance tests. This element covers
the FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
V
IBM
WBS NO.
RFP
WBS NO.
641220
4.12.2
641221
4.12.2
641222
4.12.2
641230
4.12.3
641231
4.12.3
641232
4.12.3
641233
4.12.3
641240
4.12.4
WBS WBS
TITLE DESCRIPTION
Provide Necessary Software This covers TPNS script generation for
to Support Integrated Testing hardware/software integration and stress
testing during the FOC phase.
Provide Necessary Hardware This covers the effort to plan and provide
to Support Integrated Testing test configuration and the integration of
the test computer and LAN for execution of
TPNS during the FOC phase.
Provide Necessary Data to This covers the effort to provide data to
Support Integrated Testing be used in support of the testing efforts
detailed in 641220 and 641221. This
element covers the FOC phase.
Accomplish Inter-CPCI Testing This covers the checkout and verification
of integrated CPCI's using external
interface simulators during the FOC phase.
Accomplish Inter-CI Testing This is the checkout and debug of the CI
interfaces (processor, LAN, IWS) with
diagnostic software during the FOC phase.
Accomplish Integrated CPCI/ This covers stress testing the integrated
CI Testing hardware/software system with the test
computer and TPNS scripts during the FOC
phase.
Provide Integration Test This is the effort to prepare reports of
Reports the results of tests performed on the
integrated CPCI's during the FOC phase.
Perform Formal Preship Test This covers the final preship test including
factory acceptance witnessed by the Govern-
ment and support to CM audit during the FOC
phase..
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
IBM
WBS NO.
RFP
WBS NO.
241300
4.13
641310
4.13.1
641320
4.13.2
641321
4.13.2
641330
4.13.3
641331
4.13.3
641332
4.13.3
WBS WBS
TITLE DESCRIPTION
Installation, Checkout and This covers all efforts at the operational
Test site to provide management, planning of and
installation, checkout and test. Includes
segment acceptance test and support to the
SI to perform Inter-Segment Demos and
Program Demos.
Provide Management of This is the technical management at the
Installation and Checkout operational site of all installation and
Activities checkout activities during the BOC phase.
Provide Facility Interface This covers the preparation of the Facility
Drawings/Requirements IDRS (CDRL #139) including the floor plan
for equipment installation during the BOC
phase.
Provide Facility Planning This is the analysis and coordination
required for the equipment installation
during the BOC phase.
Prepare Segment Shipping This covers the preparation of the Shipping
Plan Plan (CDRL #147) and includes instruction
covering the packaging, and shipping of
the equipment during the BOC phase.
Prepare Segment Installation This covers the preparation of the Segment
Plan Installation Plan (CDRL #134) and covers the
instruction on the physical installation of
the equipment on a non-interference basis.
This element covers the BOC phase.
Provide for Shipment, This covers the physical shipment of the
Installation and Checkout equipment and checkout of all the segment
of All Segment Items items during the BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Accomplish Segment Integra-
tion and Transition to
Operational Status
Perform Formal Site Segment
Test
Provide Site Segment Test
Report
Contribute to System Test
Plan and Test Report to Be
Prepared by the SI
Participate In On-Site
System Testing
WBS
DESCRIPTION
This covers the effort required to perform
diagnostic test on the equipment to ensure
operational readiness during the BOC phase.
This is the rebaselining of the hardware/
software system and includes the performance
of installation and checkout tests and pro-
cedures and concludes with formal acceptance.
This element covers the BOC phase.
This covers the preparation of the Segment
Test Reports (CDRL #154) which covers the
activities defined in 641340. This element
covers the BOC phase.
This covers the preparation of inputs to
SI's Test Plan and subsequent Test Reports
during the BOC phase. These inputs constitute
CDRL ##153 - System Test/Demo Inputs.
This covers the effort to support the SI
conducted on-site system testing during the
BOC phase.
Provide Input to Inter-
Program Demonstration Plan
to be Prepared by the SI
Support Program Demos
This covers the effort to provide input to
SI prepared Test Plan, and Test Procedures
employed in the conducting of Inter-Program
Demos during the BOC phase.
This covers the effort to support the SI
conducted Program Demos during the BOC
phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
Provide Management of
Installation and Checkout
Activities
Provide Facility Interface
Drawings/Requirements
Prepare Segment Shipping
Plan
Prepare Segment Installation
Plan
Provide for Shipment,
Installation and Checkout
of All Segment Items
Accomplish Segment Integra-
tion and Transition to
Operational Status
?
WBS
DESCRIPTION
This is the technical management at the
operational site of all installation and
checkout activities during the IOC phase.
This covers the preparation of Test Plan
during the IOC Phase.
This covers the preparation of the Facility
IDRS (CDRL #139) including the floor plan for
equipment installation during the IOC phase.
This covers the preparation of the Shipping
Plan (CDRL #147) and includes instruction
covering the packaging, and shipping of the
equipment during the IOC phase.
This covers the preparation of the Segment
Installation Plan (CDRL #134) and covers the
instruction on the physical installation of
the equipment on a non-interference basis.
This element covers the IOC phase.
This covers the physical shipment of the
equipment and checkout of all the segment
items during the IOC phase.
This covers the effort required to perform
diagnostic test on the equipment to ensure
operational readiness during the IOC phase.
This is the rebaselining of the hardware/
software system and includes the performance
of installation and checkout tests and pro-
cedures and concludes with formal acceptance.
This element covers the IOC phase.
641440 4.14.4 Perform Formal Site Segment
Test
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Provide Site Segment Test
Report
Contribute to System Test
Plan and Test Report to be
Prepared by the SI
Provide Input to Inter-
Program Demonstration Plan
to be Prepared by the SI
Support Program Demos
Installation checkout and
Test
WBS
DESCRIPTION
This covers the preparation of the Segment
Test Reports (CDRL #154) which covers the
activities defined in 641440. This element
covers the IOC phase.
This covers the preparation of inputs to
SI's Test Plan and subsequent Test Reports
during the IOC phase. These inputs constitute
CDRL #153 - System Test/Demo Inputs.
This covers
the
effort to provide input to
SI prepared
Test
Plan, and Test Procedures
employed in
the
conducting of Inter-Program
Demos during
the
IOC phase.
This covers the effort to support the SI
conducted Program Demos during the IOC
phase.
This covers all efforts at the operation
site to provide management, planning of and
installation checkout and test. Includes
Segment acceptance test and support to
the SI to perform Inter-Segment Demos and
Program Demos
Provide Management of
Installation and Checkout
Activities
This is the technical management at the
operational site of all installation and
checkout activities during the FOC phase.
This covers the preparation of the Facility
IDRS (CDRL #139) including the floor plan for
equipment installation during the FOC phase.
641520 4.15.2 Provide Facility Interface
Drawings/Requirements
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Provide Facility Planning
Prepare Segment Shipping
Plan
Prepare Segment Installation
Plan
Provide for Shipment,
Installation and Checkout
of All Segment Items
Accomplish Segment Integra-
tion and Transition to
Operational Status
WBS
DESCRIPTION
This is the analysis and coordination
required for the equipment installation
during the FOC phase.
This covers the preparation of the Shipping
Plan (CDRL #147) and includes instruction
covering the packaging, and shipping of the
equipment during the FOC phase.
This covers the preparation of the Segment
Installation Plan (CDRL #184) and covers the
instruction on the physical installation of
the equipment on a non-interference basis.
This element covers the FOC phase.
This covers the physical shipment of the
equipment and checkout of all the segment
items during the FOC phase.
This covers the effort required to perform
diagnostic test on the equipment to ensure
operational readiness during the FOC phase.
This is the rebaselining of the hardware/
software system and includes the performance
of installation and checkout tests and pro-
cedures and concludes with formal acceptance.
This element covers the FOC phase.
Perform Formal Site Segment
Test
Provide Site Segment Test
Report
This covers the preparation of the Segment
Test Reports (CDRL #154) which covers the
activities defined in 641540. This element
covers the FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Contribute to System Test
Plan and Test Report to be
Prepared by the SI
Participate In On-Site
System Testing
Provide Input to Inter-
Program Demonstration Plan
to be Prepared by the SI
Support Program Demos
Development and Test Facility
WBS
DESCRIPTION
This covers the preparation of inputs to
SI's Test Plan and subsequent Test Reports
during the IOC phase. These inputs constitute
CDRL #153 - System Test/Demo Inputs.
This covers the effort to support the SI
conducted on-site system testing during the
FOC phase.
This covers the effort to provide input to
SI prepared Test Plan, and Test Procedures
employed in the conducting of Inter-Program
Demos during the FOC phase.
This covers the effort to support the SI
conducted Program Demos during the FOC
phase.
This category covers the effort to define
and specify the elements of the Development
and Test Facility; to procure and checkout
the facility; and to provide the services
for operation and maintenance of the facility.
Provide Management, Planning
and Control of Development and
Test Facility
This covers the management, planning and
control of facilities to support the analysis,
human engineering, development, test and
verification of segment software and hard-
ware during the BOC phase.
Provide Management, Planning
and Control of Development
and Test Facility
Identical with 641610 except for the IOC
phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Provide Management, Planning
and Control of Development
and Test Facility
Develop Necessary Test Tools,
etc. for Development and Test
Facility
Develop Necessary Test Tools,
etc. for Development and Test
Facility
Provide ADPE Capable of
Supporting the Development
and Test Facility
Provide ADPE Capable of
Supporting the Development
And Test Facility
Operate the Development
and Test Facility
WBS
DESCRIPTION
Identical with 641610 except for the FOC
phase.
This provides for the development and/or
procurement of program products consisting
of test drivers, data reduction/analysis
programs for test and verification purposes
during BOC phase.
Identical with 641622 except for IOC phase.
This covers the lease cost of ADPE needed
to support the Development and Test Facility
during BOC phase.
Identical with 641630 except for IOC phase.
This provides the necessary skills (System
Engineers, System Programmers, Computer
Operators and Librarians) to operate the
Facility during BOC phase.
Operate the Development
and Test Facility
Maintain the Development and
Test Facility
Identical with 641640 except for IOC phase.
This covers purchase of commercial hardware
maintenance and purchase of commercial
software product licensing and service for
Facility ADPE during BOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
641654
4.16.5
641655
4.16.5
641656
4.16.5
641658
4.16.5
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
Maintain the Development and
Test Facility
Provide Management, Planning
and Control of Subcontractor
Development and Test Facilities
Provide Management, Planning
and Control of Subcontractor
Development and Test Facilities
Provide Management, Planning
and Control of Subcontractor
Development and Test Facilities
Services
Services
Equipment
Equipment
Equipment
WBS
DESCRIPTION
Identical with 641643 except for IOC
phase.
?
This provides management, planning and
control of subcontractor facilities to
support the analysis, human engineering,
development, test and verification of
segment software and hardware during the
BOC phase.
Identical with 641650 except for IOC phase.
Identical with 641650 except for FOC phase.
This covers the development and/or pro-
curement of software development tools,
library support capabilities and test
tools during the BOC phase.
Identical with 641653 except for IOC phase.
Identical with 641653 except for FOC phase.
This covers the lease cost of ADPE needed
to support the Development and Test Facility
during BOC phase.
Identical with 641656 except for IOC phase.
Identical with 641656 except for FOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
VW
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Operate Subcontractor
Development and Test
Facility
Operate Subcontractor
Development and Test
Facility
Operate Subcontractor
Development and Test
Facility
Operate Subcontractor
Development and Test
Facility
Operate Subcontractor
Development and Test
Facility
Operate Subcontractor
Development and Test
Facility
Training
WBS
DESCRIPTION
This provides the necessary skills (System
Engineers, System Programmers, Computer
Operators and Librarians) to operate the
subcontractor Facility during BOC phase.
Identical with 641659 except for IOC phase.
Identical with 641659 except for FOC phase.
This covers purchase of commercial hardware
maintenance and purchase of commercial soft-
ware product licensing and service for
Facility ADPE during the BOC phase.
Identical with 64165C except for IOC phase.
Identical with 64165C except for FOC phase.
This element includes: training management,
user training, operator training, and mainte-
nance training.
Manage All Training
Activities
This covers the management of all training
activities during the BOC phase.
641711 4.17.1 Manage All Training
Activities
This covers the management of all training
activities during the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
? Approved For Release 2007/07/05 CIA-RDP84T00037R000300060001-2 ?
w
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
Manage All Training
Activities
Provide Segment Training
Plan
Provide Segment Training
Plan
Accept Other Segment Inputs
and Prepare User Training
Materials
Accept Other Segment
Inputs and Prepare User
Training Materials
Accept Other Segment
Inputs and Prepare User
Training Materials
Train System Users and
Government Instructors
WBS
DESCRIPTION
This covers the management of all training
activities during the FOC phase.
This covers the preparation of the Segment
Training Plan (CDRL #140) during the BOC
phase.
This covers the preparation of the Segment
Training Plan (CDRL #140) during the IOC
phase.
This covers the effort required to integrate
inputs from other segments into user/operator
training materials and to prepare training
materials (CDRL #146) during the BOC phase.
This covers the effort required to integrate
inputs from other segments into user/operator
training materials and to prepare training
materials (CDRL #146) during the IOC phase.
This covers the effort required to integrate
inputs from other segments into user/operator
training materials and to prepare training
materials (CDRL #146) during the FOC phase.
This covers the effort required to train
users of the system and Government instructors
during the BOC phase.
641724 4.17.2 Train System Users and This covers the effort required to train
Government Instructors users of the system and Government instructors
during the IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
Train System Users and
Government Instructors
Prepare and Deliver Operator
Training Materials
Prepare and Deliver Operator
Training Materials
Prepare and Deliver Operator
Training Materials
Train Segment and System
Operators and Management
Personnel
Train Segment and System
Operators and Management
Personnel
Train Segment and System
Operators and Management
Personnel
Prepare and Deliver Mainte-
nance Training Materials
?
WBS
DESCRIPTION
This covers the effort required to train
users of the system and Government instructors
during the FOC phase.
This covers the preparation and delivery of
operator training materials (CDRL #146)
during the BOC phase.
This covers the preparation and delivery of
operator training materials (CDRL #146)
during the IOC phase.
This covers the preparation and delivery of
operator training materials (CDRL #146)
during the FOC phase.
This covers the effort required to train
segment and system operators and manage-
ment personnel during the BOC phase.
This covers the effort required to train
segment and system operators and manage-
ment personnel during the IOC phase.
This covers the effort required to train
segment and system operators and manage-
ment personnel during the FOC phase.
This covers the preparation and delivery
of maintenance training materials (CDRL
#146) during the BOC phase.
This covers the preparation and delivery
of maintenance training materials (CDRL
#146) during the IOC phase.
641741 4.17.4 Prepare and Deliver Mainte-
nance Training Materials
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
IBM
WBS NO.
RFP
WBS NO.
641811
4.18.1
641812
4.18.1
641813
4.18.1
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
s
WBS
TITLE
Prepare and Deliver Mainte-
nance Training Materials
Train All Segment Maintenance
Personnel
Train All Segment Maintenance
Personnel
Train All Segment Maintenance
Personnel
Operations and Maintenance
(O&M)
Provide O&M Management
Provide O&M Management
Provide O&M Management
Provide O&M Project Control
WBS
DESCRIPTION
This covers the preparation and delivery
of maintenance training materials (CDRL
#146) during the FOC phase.
This covers the effort required to train
all segment maintenance personnel during
the BOC phase.
This covers the effort required to train
all segment maintenance personnel during
the IOC phase.
This covers the effort required to train
all segment maintenance personnel during
the FOC phase.
This covers the management and planning
and control of O&M activities; the pro-
curement of equipment/services to perform
O&M; and the actual execution of O&M
services over the specified life of the
contract.
This covers the project management needed
to manage, plan and control O&M during the
BOC phase.
Identical with 641810 except for IOC phase.
Identical with 641810 except for FOC phase.
This provides the project schedule and
financial monitoring effort to maintain
project control including review and periodic
reporting to the Government.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
?
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
40
IBM
WBS NO.
RFP
WBS NO.
WBS
TITLE
WBS
DESCRIPTION
641814
4.18.1
Provide O&M Project Control
Identical with 641812 except for IOC phase.
641815
4.18.1
Provide O&M Project Control
Identical with 641812 except for FOC phase.
641836
4.18.3
Problem Analysis, Error
Correction and Update
Documentation
Problem Analysis, Error
Correction and Update
Documentation
Problem Analysis, Error
Correction and Update
Documentation
Test Software Changes
Test Software Changes
Test Software Changes
Maintain Commercial Software
Products
This provides system maintenance programmers
to perform problem analysis and error cor-
rection when software problems arise during
BOC phase. Also included is effort to update
documentation.
Identical with 641836 except for IOC phase.
Identical with 641836 except for FOC phase.
This provides test personnel to test
and verify conformance with specification,
any software changes made to the Segment
during BOC phase.
Identical with 641839 except for IOC phase
O&M.
Identical with 641839 except for FOC phase
O&M.
This covers purchase of commercial software
product licensing and service during BOC
phase 0&M.
64183D
4.18.3
Maintain Commercial Software
Products
Identical with 64183C except for IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
IBM
WBS NO.
RFP
WBS NO.
641844
4.18.4
641845
4.18.4
641870
4.18.7
641871
4.18.7
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2
w
WBS
TITLE
Maintain Commercial Software
Products
Hardware Problem Analysis,
Error Correction and Update
Documentation
Hardware Problem Analysis,
Error Correction and Update
Documentation
Hardware Problem Analysis,
Error Correction and Update
Documentation
Maintain Commercial Hardware
Maintain Commercial Hardware
Provide Travel and Living
Expenses of O&M Personnel
Provide Travel and Living
Expenses for O&M Personnel
WBS
DESCRIPTION
J
Identical with 64183C except for FOC phase.
This provides hardware engineers to perform
problem analysis and error correction when
hardware problems arise during BOC phase
O&M. Also included is effort to update
documentation.
Identical with 641840 except for IOC phase.
Identical with 641840 except for FOC phase.
This covers purchase of commercial hardware
maintenance based on 24 hour per day, 7 day
per week on-call maintenance during BOC
phase O&M.
Identical with 641843 except for IOC phase.
Identical with 641843 except for FOC phase.
This covers both local and long distance
travel and living expense of contractor
personnel engaged in performance of BOC
phase O&M.
Identical with 641870 except for IOC phase.
Approved For Release 2007/07/05: CIA-RDP84T00037R000300060001-2