LIMITATION OF DAMAGES(Sanitized)

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP84-00709R000400070095-8
Release Decision: 
RIPPUB
Original Classification: 
K
Document Page Count: 
2
Document Creation Date: 
December 9, 2016
Document Release Date: 
June 6, 2001
Sequence Number: 
95
Case Number: 
Publication Date: 
October 18, 1948
Content Type: 
MEMO
File: 
AttachmentSize
PDF icon CIA-RDP84-00709R000400070095-8.pdf152.57 KB
Body: 
Approved For Rese 2001/09/03: CIA-RDP84-00709R0004 A6. a. cc Memorandum ? UNITED STATES GOVERNMENT OGC Has Reviewed ? Piles DATE: 18 October 1948 Limitation of Damages 1. This contract provides for the installation, and main- tenance and oneravion of a burglar-alarm system. This contract contains a clause limiting the liability of the contractor to the Government for each breach. The liquidated damages are nominal. (850.00) aW.3 are proposed on the basis that it would be "impractical and extremely difficult to fix the actual daragos". In this regard, it is assumed that the contents of the vault protected will consist of almost, if not, entirely classified papers which are net readily susceatible to monetary valuation. 2. The 1t.w appears to be well settled that the parties to a contract may agree on liquidated damages for any breach of the, contract when the material or services to be provided under the con- tract cannot be readily obtained on the open market, and damages would be difficult to determine. The Supreme Court has stated (S:zn ?rintinr and Publishing Ase.ciatioA v, Moore, 183 U.S. 642) tent: be proven; it is sufficient to plead the breach of contract. 3. On the other hand, if the stipulation for liquidate dame e is, on the face of the contract, disproportionate to possible tual. &xma;es, then the sum will most probably ba construed as a pe ty and enforced only to ttie extent of actual damages sustained. n passing, it is noted that proper liquidated daxuagee do not to to enforce the contract." "The decisions of this court on the doctrine of liquidated damages and penalty lend no support to the contention that parties may not bona fide, in a case where the damages are of an uncertain nature, estimate and agree upon the measurebf damages which may be sustained. from the breach of an agrement, On the c^.ntrary, this court has consistently maintained the. principle that the intention of the parties is to be arrived at by the proper construction of the agreement made betwein them, and that whether a particular stipulation to pay a sum of money is to be treated as a penalty, or as an agreed cer- tainment of damages; is to be determined. b,.r the contract,` fairly construed, it being the duty of the court always, where the damages are uncertain and have bEen liquidated by an agr went, Approved For Release 2001/09/03 : CIA-RDP84-00709R000400070095-8 Approved FoTRelease 2001/09/03: CIA-RDP84-00709RO 400070095-8 4. In reviewing the statutes and opinions, there does not av en.r to he any restriction of the Government's right tc agree to liquidate da^:n.f-es. When 'Time of Delivery' is of the essence or services or :arterial cannot be readily obtained in the open market, an aanronriate liluidated damages clause can be properly included in the contract. Generally, liquidated damages should not be permitted to encceei the contract price, although this usually applies to situations where supplies or commodities can be readily obtained, and, in which liquidated damages should not have been stinalnted at all. The converse is illustrated in the situation on which the Co:-ptroller commented in 16 Comp. Gen. 344. In that case, diuna es were stipulated for delays in delivery of two items - of nnterial not readily obtalnable in the open market. Damages amounted to $800.00 for $105.00 worth of supplies, and the Comptroller stated thr,t althou/-.h the clause was appropriate, there was no annarent relationship between the agreed sum and the potential injury. rn Per the absence of a shooing of actual damage resulting from the delay in delivery, the provision was treated in the nature of a penalty and not recognized. It. should be noted that a contributing factor to this conclusion was the fact that the stipulated damages aurlied equally to two items and failed to distinguish a suitable measure of dansees.rr+~,--irr.e,7i -c TQ. fl y*'l The opiniDna of the Comptroller have been directed at ccntracte in which payment of stipulated damages have worked a hard- ship on the Contractor rather than the Government. The clause in the contract under concid.eration is governed by the general rules out- lined above, but it also raises the question of whether there is any li nitation on the contracting officer's authority to limit tL tGovern- me.-it 1 e -potential right to claim damages. Since the services to be pro- vided cannot be readily (indeed, cannot be satisfactorily) obtained from any other contractor, a liquidated damages clause is appropri- ate. Since it is assured that the contents of the protected vault do not have an intrinsic value in money, the amount indicated in the clause mt;.y be accepted as appropriate. If at any time there is a loss of oronerty which is susceptible to accurate evaluation, then the stipulated amount mi.-ht be considered so disproportionate as to permit an atRessment of actual damage. ? Approved For Release 2001/09/03 : CIA-RDP84-00709R000400070095-8