TRIP REPORT TO (Sanitized)
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP81B00961R000100120033-7
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
2
Document Creation Date:
December 9, 2016
Document Release Date:
September 13, 2000
Sequence Number:
33
Case Number:
Publication Date:
August 6, 1962
Content Type:
MFR
File:
Attachment | Size |
---|---|
CIA-RDP81B00961R000100120033-7.pdf | 122.45 KB |
Body:
Approved ForRelease2001/03/04 : CIA-RDP81600961R000100120033-7
MET
MORANDVM FOR THE RECORD
JFCT: Trip Report to
25X1A
WA-0681-62
6 August 1962
25X1A
1, On 1 August 1962 Messrs
visited the office in e purpose of e 25X1A
visit was to inspect construction in progress on the addition 25X1A
to existing building and to review the Construction Contract.
a. Contract: A contract to erect the additional 25X1A
ing was signed between M, the owner and the Con-
tion Company on e June 1962 in the amount of immimmomm 25X1A
Order No. I was prepared and signed on 20 June 1962 25X1A
g some work from the contract thereby reducing the total ?
f the contract by 1111.111.111. The adjusted contract price 4Alt.?
102411111111111/ 25X1A
b. Construction: Construction Co. was given 25X1A
deri-EFIFF5agia-with construction on 6 June 1962. Work
ed 9 June 1962. The following work is in progress:
(1)
Relocating utility
lines
98% complete
(2)
Excavation for foundation
SO%
(3)
Excavation for basement
floors
60%
(4)
Concrete foundations
SO%
(5)
Reinforcement steel in
place for basement walls
60%
(6)
Concrete forms for base
ment walls in place 40%
2. The contractor ts schedule is for placing concrete in
the basement walls 3 /iugust 1962. The contractor was delayed
several weeks by a stiike of steel works. Since settlement
of strike, be has increased his steel working crews and is
about on schedule.
klrfincr
Approved For Release 2001/031,04iGIA-RDP8113
? r
61R000100120033-7
.L.064540,
Approved For Release 2001/03/04
JAADP81600961R000100120033-7
OSA-06 2
Page Two
3. iuring excavation, four boulders exceeding cubic
yard each uncovered. Since the specificat on* *tate
any boulder over cubic yard in size shall be paid for sep-
arately at the price stated in the bid proposal, it will be
necessary to prepare Change Order No. 2 which will be a sligh
increase of a few hundred dollars to the contract price.
4. The contractor appears to be running a very orderly
and clean Job. The work in progress in well supervised and
planned.
25X1A
MD/USA. %A:1111111:mrs
Dist 1 - C/MD/CSA
1 - AJ/OSA
I DO/OSA
1 Admin/OSA
I1 - RIB/OSA
25X1A
Approved ForRelease2001/W/Q4 :CIA-RDP81600961R000100120033-7