PROPOSED PASEWALK/OST TRANSFORMER STATION AND CONNECTING HIGH TENSION LINES
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP80T00246A039400120001-1
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
3
Document Creation Date:
December 22, 2016
Document Release Date:
July 27, 2010
Sequence Number:
1
Case Number:
Publication Date:
January 3, 1958
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 92.31 KB |
Body:
Sanitized Copy Approved for Release 2010/07/27: CIA-RDP80T00246AO39400120001-1
INFORMATION REPORT INFORMATION REPORT
CENTRAL INTELLIGENCE AGENCY
This material contains Information affecting the National Defense of the United States within the meaning of the Espionage Laws, Title
18, U.S.C. Secs. 793 and 794, the transmission or revelation of which In any manner to an unauthorized person Is prohibited by law.
COUNTRY Last Germa y
SUBJECT Proposed Tasewalk/4st Transformer
Station and Connecting Nigh Tension
7dnes
REPORT L_
DATE DISTR.
NO. PAGES
REQUIREMENT
NO.
DATE OF
INFO.
PLACE &
DATE AC
8 JAN 1951
ROCESSING COPY
1. The new transformer station,Pasewalk/Qst, will be erected just to the south of
the Pasewalk-Grrambow railway line, and the high tension pylons leading to and
from the new station will follow a line approximately 25 me from and parallel
to the railway.
2. The following high tension overhead lines will be corrected with the Pasewaik/
Gat transformer station:
3.
(a) 110 kv overhead line Pasewalk-Eggesin which will be connected to the Paso-
walk/Cot station and the existing transformer station Pasewalk/V9st, and
will be connected also to the new 110 kv overhead line to the Lggesin
transformer station. The present overhead line from the transformer station
Pasevalk/fiest ends in a temporary transformer station an the site of the
projected new Pasewalk/Qst station.
(b) A 1.10 kv overhead line will run from the new transformer station Pasevalk/
. 0st-Granzin.
(c) A 1]0 kv overhead line from. Plasewalk/Wt to Greifswald is also planned.
(d) A 110 kw overhead line to Eggesin is -under construction.
Nark on the new Pasewalk/Qst transformer station has progressed beyond the sur-
vey. The planned completion date is the and of 1960. An alignment of a rail
spur from the asewalk-Grambow line to the planned new transformer station has
been planned, but details are not yet availableo
Pylon number 27, which is the and pylon of the connection between Phsewalk/tlTest-
Pasevalk/Qst, has already been erected. This completed construction of the Pase-
wnik/Vest-Pasewalk/Qst overhead connection.
Pylon umber 1 of the main connection As.sewalk/Ost-Lggesin is already in position.
STATE = ARMY = AVY I X IAIR
Sanitized Copy Approved for Release 2010/07/27: CIA-RDP80T00246AO39400120001-1
Sanitized Copy Approved for Release 2010/07/27: CIA-RDP80T00246AO39400120001-1
S4&.0-1-&-T
~. As soon as the in overhead eeiaeetien Pluewa3k/Q9t-Zggeeim had been eaepleted,
which is planned for 20 Deember 1957, it will be put into eperatiem.
50X1-HUM
Sanitized Copy Approved for Release 2010/07/27: CIA-RD P80T00246AO39400120001-1
Sanitized Copy Approved for Release 2010/07/27: CIA-RDP80T00246AO39400120001-1
Sanitized Copy Approved for Release 2010/07/27: CIA-RDP80T00246AO39400120001-1