RAILROAD BRIDGE CONSTRUCTION AT RACIBORZ
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP80-00810A004100930002-2
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
2
Document Creation Date:
December 22, 2016
Document Release Date:
February 2, 2010
Sequence Number:
2
Case Number:
Publication Date:
June 18, 1954
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 77.63 KB |
Body:
Sanitized Copy Approved for Release 2010/02/02 : CIA-RDP80-0081 OA004100930002-2
CENTRAL INTELLIGENCE AGENCY
INFORMATION REPORT
This Document contains information affecting the Na-
tional Defense of the United States, within the mean-
ing of Title 18, Sections 793 and 794, of the U.S. Code, as
amended. Its transmission or revelation of its contents
to or receipt by an unauthorized person is prohibited
by law. The reproduction of this form is prohibited.
S 1! REST/CONTRQL U. S. OFFICIALS ONLY
COUNTRY Poland REPORT
SUBJECT Railroad Bridge Construction at DATE DISTR.
18 June 1951
Raei orz
NO. OF PAGES
2
PLACE ACQUIRED
REQUIREMENT NO.
REFERENCES
RD
THE SOURCE EVALUATIONS IN THIS REPORT ARE DEFINITIVE.
THE APPRAISAL OF CONTENT IS TENTATIVE.
(FOR KEY SEE REVERSE)
1. The cgnstructfoi of a railroad bridge over the Oder River at Raciborz (Ratibor) was
started in , the Spring of 1953, approximately ten meters to the right (viewed from
the.town,) of the old, destroyed, railroad' bridge.
2. The piles of the new bridge have been erected, and work i, in progress on the sur-
face. Foundations for two tracks were-observed to have been constructed. Hitherto
a temporary wooden bridgeeerected on the piles #4f the destroyed bridge, has been in
use for rail-traffic. When the new bridge i$ put into co>mnission,.the old tracks
will have to be transferred. Earth works are proceeding for this purpose at the
new bridge.
The following a"e the pertiment date on the new bridge.
Location: coordinates 50P 5.5 N; 180 141E. Nearest 'towntRacibor* ( tibvr)e
grosses the Oder River where the river is aptroximAel7 O
fide and approximately 2.5 to 3 meters deep.
Bridge Description:. Approximately 60 meters long snd 9 meters wide, it has
three ferroconcrete piles. The'distance above the water
is approximately 1..5 meters and the.openings between the
piles measure approximately 12 meters each (see sketch).
4. The bridge will be used by the railroad line going from Raciborz to Kedzierzyn
(Seyd.breck) and will have two tracks.
SECRET/CONTROL - U.S. OFFICIALS ONLY
STATE ARMY X NAVY
X AIR x
I
(Note; Washington Distribution Indicated by "X"; Field Distribution By "#".)
Sanitized Copy Approved for Release 2010/02/02 : CIA-RDP80-0081 OA004100930002-2
FBI AEC
Sanitized Copy Approved for Release 2010/02/02 : CIA-RDP80-0081 OA004100930002-2
SECRET/CONTROL - U.S. OFFICIALS ONLY
1(-9 m.-i 4
SECRET/CONTROL - U.S. OFFICIALS ONLY
Sanitized Copy Approved for Release 2010/02/02 : CIA-RDP80-0081 OA004100930002-2