ECONOMIC - RAILROADS

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP80-00809A000600140126-7
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
3
Document Creation Date: 
December 22, 2016
Document Release Date: 
June 13, 2011
Sequence Number: 
126
Case Number: 
Publication Date: 
January 27, 1951
Content Type: 
REPORT
File: 
AttachmentSize
PDF icon CIA-RDP80-00809A000600140126-7.pdf183.04 KB
Body: 
Sanitized Copy Approved for Release 2011/07/14: CIA-RDP80-00809A000600140126-7 COUNTRY DATE OF iNFORf.1ATtON 1950 DATE D1ST. 9Jen 1.951 50X1 -H NO. OF PA ES }NFL sO PIIR gO1FRO0Mi IN I*lAO! "Mn" T" "0"" own" p rag CMiMO i1CMi l19MIM tot MYMIMO OY MMf%OYI1N AO F* L , 9. ,. oA AMO xC. OMSICNN. RII YMYMOMlo0IOi WM INiON 0 IRO GCinpN PM N1. M"Mii IN *N MMOORiiIlIYtM plat" IN INN- NI 611. Me1MNMCOIOM 0/ YMI$ -Oii It P INPITCM? REPORT NO. Before discussing the present situation of the Soviet railroads, it is necessary to emphasize a complete unknown fact: during World War II the Soviets dismantledlmany railroad lines distant from the theaters of operations and transferred the installations of these lines to the areas of militltry operations. Soviet postwar data and maps are, therefore, often exaggerated because many railroads indicated in such publications may not exist at all. The following 13 railroad lines were planned by the Fourth Five-Year Plan and are either under construction or have already been completed: 1. South Siberian Railroad a, Akmolinsk-Pavlodar section. More than 200 kilometers had been laid on this 4147-kilometer line by the end of 1948. b. Barnaul-Stalinsk section. In April 1949, rails were laid up to the Smaznevo station, located 100 kilometers from Barnaul, and blasting was started in the Altai Mountains. c. Dzhambul-- Chulak-Tau branch. This branch had not been begun in 1948. * 2. Kagnitogorsk-Sterlitamak line. Construction. began in December- 1947 and was completed in March 1949. 3. Ishimbay-Termoleyevo line. Construction began in January 1948. By September 1948 it advanced 93 kilometers. Operations were started in February 19149. 4: Chardzhou-Kund line (A-W kilometers long). In November 1948, err th- work was completed up to Novo-Urgen (400 kilometers). Construction of the Chardzbou-Kilcm-eter 80 section was completed in March 1949. In March 1949, it was decided to continue the line to Aarganata (210 kilometers from Chardzhou). ? r GPn..~fww. ~en?vrn..R ww -_~r, Sanitized Copy Approved for Release 2011/07/14: CIA-RDP80-00809A000600140126-7 50X1-HUM 50X1-HUM 50X1-HUM Sanitized Copy Approved for Release 2011/07/14: CIA-RDP80-00809A000600140126-7 '~?n8~' ~w2R ,~a;w ,d rcv,4~'~~rn"",o my ~s ?'. ai Y a8^'' .r+~4''fdr a~ J ,~ -e, Y y s, A SECRET Mointy-Chu line (443 kilometers long). Construction was started in March 1948. By duly 1948, about 40 kilometers were finished. In completed in September 1950. 1946. 8, Semipalatinsk-I4alinovoye Ozero (152 kilometers long). To be continued 7. Kars-Tau--Taldy-Kurgan line. This line was finished by the end of 1947. further. Besides this list, the following lines were planned: 12. Uruscu-Narychevo line. 13. Shuya-Yuzba-Il'ino line. Nauchki-Ular. Bator line (350 kilometers long). Connects the Siberian line from Kyakhta with the Mongolian capital and has been in operation since August 1949. An 85-kilometer railroad line is planned up to Yardinskaya Lesnaya Dache (in Kara Kumy, Turkmen SSR), but construction has not yet begun. A part of the Transsiberian railroad line, from Novokuznetsk via Omsk and Chelyabinsk to the station of Dema, a distance of 2,350 kilometers, is being electrified. Two lines, toward Targagatay and toward Zasianek are to be finished in 1951. The most important repair and reconstruction projects in 1946-48 were as follows: 1. Double-tracking of the Moscow-Leningrad, Moscow-Kharkov, Rostov- Prokhladnaya, and Karaganda-Akmolinsk lines. 2. Reconstruction of the railroad centers in the Donets and Krivoy Rog basins. 3. Reconstruction and restoration of the bridges over the Dnepr, Don, Nenan, Svi.r', northern Donets, and Irtysh rivers. 4. Reconstruction and restoration or var ous station buildings. During 1946-47 these construction projects progressed very aloaly because of a lack of rails and bridge installations. Rail production increased slowly (production in 1947 was only 25 percent above tb9t of 1946) and the Ministry of Transportation was obliged to import rails: In 1946-47, only one million tons of raids were supplied to the railroads, while the roads could have used at least four timea that much. Sanitized Copy Approved for Release 2011/07/14: CIA-RDP80-00809A000600140126-7 Sanitized Copy Approved for Release 2011/07/14: CIA-RDP80-00809A000600140126-7 Sae following table of verified data abovs 1945.47 results, 1946 M4 Rails for construction, repair at least 850 km a~ 1,226 ka Rails for construction of second t;aoks 200 1,265 Rails for sidings 800 ?btal It b 2,050 km 3,291 km Electrification blocking) 2,259 km 1,640 km least 85 464 995-1000 1,744 144 -- Capital investments About 5 billion rubles About 6 billion rubles Including the Eos?ve-Alaapayevsk and Dzhm ul-4hulak Tau lines. Doubtful whether completed. Copy Approved for Release 2011/07/14: CIA-RDP80-00809A000600140126-7 50X1-HUM