PAI YANG HO PETROLEUM REFINERY, YU-MEN YU-MEN, CHINA
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP79T00909A000500010016-4
Release Decision:
RIPPUB
Original Classification:
T
Document Page Count:
13
Document Creation Date:
December 28, 2016
Document Release Date:
June 18, 2008
Sequence Number:
16
Case Number:
Publication Date:
June 1, 1969
Content Type:
REPORT
File:
Attachment | Size |
---|---|
CIA-RDP79T00909A000500010016-4.pdf | 510.59 KB |
Body:
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
i op secret
DIRECTORATE OF
INTELLIGENCE
Industrial Facilities
(Non-Military)
Basic Imagery Interpretation Report
Pai Yang Ho Petroleum Refinery, Yu-men
Yu-men, China
Top Secret
DATE
JUNE 1969
copy
105
PAGES
I I
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
TOP SECRET RUFF
CENTRAL INTELLIGENCE AGENCY
Directorate of Intelligence
Imagery Analysis Service
Pai Yang Ho Petroleum Refinery, Yu-men
UTM COORDINATES
47SLQ769095
GEOGRAPHIC COORDINATES
39-50-ION 97-41-50E
RCS - 13/0185/69
MAP REFERENCE
15th RTS. USATC 200. Sheet M0332-2HL, 3rd edition, August 1968, Scale 1:2'00,000
(SECRET
Not Required
This report provides a detailed imagery-derived analysis of the Pai Yang Ho
Petroleum Refinery, Yu-men, China from September 1959 to August 1968.
The major production facilities at this refinery were complete and in
operation when first seen on photography of September 1959. Between 1964 and
1966 a possible lubricating oil plant was added. The refinery products are
gasoline, kerosene, diesel and fuel oil, residuum and possibly a full range
of lubricating oils, waxes and asphaltic materials.
This report includes a detailed line drawing, a photograph of the refinery,
a discussion of the physical features, operational functions, facilities and
equipment, and reference data.
TOP SECRET RUFF
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
TOP SECRET RUFF
TOP SECRET RUFF
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
TOP SECRET RUFF
25X1
25X1
The Pai Yang Ho Petroleum Refinery, Yu-men, is located in Kansu Province
on the west side of the town of Yu-men. Crude oil for charging the refinery is
probably brought in by pi eline from the nearby oil fields. The Yu-men Heat
and Thermal Power Plant which furnishes electric power to the 25X1
refinery, is located I nautical mile to the north. The refinery is served by
a good all-weather road system and by a spur from the main line between Ha-mi
and Lan-chou.
Physical Features
The refinery occupies an irregular-shaped area. which measures approximately
5,600 by 3,800 feet and contains approximately 490 acres. The refinery is
partially secured by a fence or a wall.
Operational Functions
The major products of this refinery are gasoline, kerosene, diesel and fuel
oil, and residuum. A full range of lubricating oils, waxes and asphaltic materials
are also possibly produced.
The major functional units include a shell still, an atmospheric distillation
unit, a multistage distillation unit, a possible thermal cracking unit, and a
possible light ends unit. The identification of a possible lubricating oil plant
is based on the existence of groups of closely spaced, small and medium size
tanks, located adjacent to processing equipment typical of that found in lub-
ricating oil production facilities.
Status and Activity
Poor resolution and small scale of the early photography made a detailed
analysis of the development of the refinery nearly impossible.
The crude oil distillation, thermal cracking and light ends recovery units
appeared complete and operating when first seen on photography of September 1959.
The possible lubricating oil plant (Area C) and the unidentified secondary
processing units (Area E) were constructed between September 1964 and February
1966.
The only construction activity on August 1968 coverage was in the
unidentified processing area (Area B). The plant appeared to be operating
on this imagery, the latest used in this report.
-3-
TOP SECRET RUFF
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
TUP SECRET RUFF
25X1
25X1
Facilities and Equipment
The following table lists the functional area and equipment within the
refinery. All items are keyed to Figure 3.
Area Description
Equipment*
A Possible Treating and I Pipe furnace
Storage 4 Processing buildings
23 Cylindrical treating/storage tanks
1-45 ft. diam.
2-40 ft. diam.
7 Associated buildings
I Spray pond
B Unidentified Processing I Processing building U/C
U/C 12 Support buildings
I Spray pond
2 Cylindrical tanks U/C
25 ft. diam.
2 Tank bases U/C
C Possible Lubricating I U/I processing unit with
Oil Plant I Pipe furnace
2 Large possible packaging buildings
12 Cylindrical processing tanks/
storage tanks
I U/I processing unit with
2 Banks U/I equipment
3 U/I processing buildings
40 Cylindrical processing/storage
tanks
as o er
TOP SECRET RUFF
25X1
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
TOP SECRET RUFF
Area Description
I Possible packaging plant with
I large L-shaped possible packaging
building
20 Cylindrical tanks
25X1
LOA I
I U/I processing unit with
I large irregularly shaped building
2 Associated buildings
25 Cylindrical processing/storage tanks
25X1
I U/I processing unit with
2 Processing buildings
II Miscellaneous buildings
14 Cylindrical tanks
1-20 ft. diam.
6-15 ft. diam.
6-10 ft. diam.
5 Miscellaneous buildings
D Products Storage
Equipment*
I Possible packaging building
12 Associated buildings
-5-
TOP SECRET RUFF
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
TOP SECRET RUFF
Area Description Equipment*
E Secondary Processing 5 U/I secondary processing units
I Unit with
I Pipe furnace
I Bank U/I processing equipment
I Processing building
3 Associated buildings
II Cylindrical processing tanks
Crude Oil Distillation I Shell still (10 stills)
4 Pipe furnaces
2 Fractionating columns
I Possible compressor building
I Transfer building
5 Associated buildings
-6-
TOP SECRET RUFF
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
7-10 ft. diam.
I Unit with
4 Processing buildings
2 with processing equipment on roof
4 Columns/reactors
I Bank processing equipment
I Unit with
I Pipe furnace
I Processing building
8 Cylindrical processing tanks
I Unit with
2 Processing buildings
14 Cylindrical processing tanks
1-20 ft. diam.
7-15 ft. diam.
I Unit with
I L-shaped building
I Bank processing equipment
2 Miscellaneous buildings
10 Miscellaneous buildings
I Pipe furnace (in state of disrepair)
17 Cylindrical storage tanks
25X1
25X1
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
TOP SECRET RUFF
Area Description Equipment*
7 Cylindrical tanks
2-20 ft. diam.
2-15 ft. diam.
G Intermediates Storage 2 Possible control/pumping buildings
24 Cylindrical tank
25X1
H Crude Oil Distillation and I Topping unit with
Secondary Processing I Fractionating column
I Pipe furnace
I Compressor/control building
I Atmospheric distillation unit with
I Fractionating column
I Redistillation column
I Pipe furnace
I Compressor/control building
I Multistage distillation unit with
I Atmospheric distillation column
I Vacuum distillation column
I Redistillation column
2 Pipe furnaces
I Compressor building
I Control building
I Bank of heat exchangers/cooling coils
I Possible cracking unit with
4 Fractionating columns/reactors/
flash chambers
I U/I column
2 A-frame furnaces
I Control building
I Associated building
I Possible light ends unit with
3 Columns/absorbers
4 Associated buildings
I Cooling pond
2 Water spray ponds
I Water treatment pond
5 Miscellaneous buildings
I Flare stack
-7-
TOP SECRET RUFF
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Next 1 Page(s) In Document Denied
Iq
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Area Description
TOP SECRET RUFF
Equipment*
24 Cylindrical tanks
I Crude Oil Storage I Large U/I building
4 Pumping buildings
I
9
Water pond
Cylindrical
tanks
1-95
ft.
diam.
1-50
ft.
diam.
6-40
ft.
diam.
*All storage tank dimensions are approximate.
-10-
TOP SECRET RUFF
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
TOP SECRET RUFF
Map
15th RTS. US Air Target Chart, Series 200, Sheet M0332-2HL, 3rd edition,
Requirement
EXSUBCOM - BR-N/002-69
- II -
TOP SECRET RUFF
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4
Top Secret
Top Secret
Approved For Release 2008/06/18: CIA-RDP79T00909A000500010016-4