RECOGNITION AND PRE-DISPOSAL OF PROBLEMS ASSOCIATED WITH (Sanitized)1540 LIGHT TABLE PRE-PRODUCTION MODEL AND SUBSEQUENT PRODUCTION

Document Type: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78B05171A000400030094-7
Release Decision: 
RIPPUB
Original Classification: 
C
Document Page Count: 
4
Document Creation Date: 
December 28, 2016
Document Release Date: 
June 7, 2005
Sequence Number: 
94
Case Number: 
Publication Date: 
September 8, 1970
Content Type: 
MFR
File: 
AttachmentSize
PDF icon CIA-RDP78B05171A000400030094-7.pdf164.93 KB
Body: 
Approved Release 2005/06/23: CIA-RDP78B01A00040003 Declass Review by NGA/DoD TSG/ESD/TEB-02870 8 September 1970 MEMORANDUM FOR THE RECORD SUBJECT: Recognition and Pre-disposal of Problems Associated with 1540 Light Table Pre-production Model and Subsequent Production -REFERENCE: Test Plan - F_MLT 1540 Light Table Pre-Production Model 1. A meeting was held at 1300 on 3 September 1970 in the ESD Division Office. Attending were 25 3. 0 stated that the table will not be used for vibra- tion work. It is expected that the second or third 0 table off the production line will be sent GFE to Since that table belongs to IEG, their concurrence is required, and will be solicited by RED in the ---near future. 4. The reference test plan was discussed. Oquestioned the 2 __--length of time scheduled by_TEB/ESD to run performance tests on the pre-production model. stated that no finisheditable had been 2 seen, and the information gained from a test period would outweigh the time loss for production. 0 assured 0 that if the time spent 2 on these tests could be reduced, it would certainly be done. Assurances were given that any problems which were found would be relayed to 2 immediately. 5. I lexpressed concern that, during the operational inspec- tion, PI s may find things that they would like changed which were not mentioned in the operational evaluation. This would wreck the production schedule if they were adament in their demands. It is ESD's position that operational components must be given an opportunity to see the finished swap excluded team "roma;i, I _A 2. The meeting was opened by who listed the main 25 -areas of ESD concern. These are: 1) That the pre-production model should be shipped to NPIC as soon as possible to insure that defects which may exist will be found before other units come off of the production line, 2) That the specification states the light source must be operated for 100 hours prior to testing, 3) That previously announced plans to ship the Mod II table to would not yield a solution to vibra- tion isolation problems due to differences in construction between 2r tables. rk1NIVV U rur rFGIGabG LVV i Mr/oovaif 1MVVV4VVVjVVV4 Approved Release 2005/06/23: CIA-RDP78B 1A000400030094-7 SUBJECT: Recognition and Pre-disposal of Problems Associated with 0 15+0 Light Table Pre-production Model and Subsequent Production product. It is better to correct a fault at that juncture than live with -it for years and perhaps introduce inefficiencies into the exploitation 6. In order to iiia off defects in shipped units, particularly the pre-production model, the following schedule of events was agreed on. a. 0 plans to visit during the week of 15 September 25 and inspect progress to date. If TEB assistance is requested by 25 it will be furnished. b. = will submit, as per contract, their Acceptance Test Plan on or about 21 September. This will be reviewed by ESD and RED to insure that the production units are in the best possible condition when shipped. RED, with ESD participation, will conduct a pre-acceptance test at 0 as soon as the pre-production model is completed, which is scheduled for the week of 5 October. Operational components may be asked to send a representative to insure that no PI problems slip by before - shipment. ESD strongly requested that this first unit be shipped by air immediately following this pre-acceptance test. agreed to do this 25 if at all possible. The remainder of-theischedule assumes this will be done. A. --Test & evaluation of the pre-production model at NPIC should start 12 October, and an acceptnace decision should be made by 23 October. e. If production continues from 5 October through 23 October, it _is_ I risk.- expressed concern over the possibility that production would stop during this period, thereby slowing the production schedule. 7. Q stated that =plans to energize the light tubes for the 100 hours mentioned in the spec, prior to assembly and/or shipment. .O Erequested that this intention, and its fulfillment, be documented by to relieve problems if non-spec conditions are found in the illumi- nation source during acceptance testing, either of pre-production on production units. 8. II requested that =space shipments of the tables so that no storage problem of tested tables occurs. stated that EPB is 25 planning to test a minimum of 4 per day, -nd shipments should be planned accordingly. concern in this matter was that a backlog of finished tabl o occur while =waits for an acceptance decision, 25 5 through 23 October - assuming that no rework is required as a result of that testing. Every attempt will be made by 0 to see that the 25 shipments are spaced. 9. 0 also requested that a list of parts which must be stocked by EPB be provided as soon as possible. Il asked that preventive maintenance procedures be supplied as s o bb11 responded Approved For Release 200? J23 : CIA-R6P796 i t OOe640 Approved Release 2005/06/23: Cl R P 8B0 lA000400030094-7 L, .. SUBJECT: Recognition and Pre-disposal of Problems Associated with 0 25 1540 Light Table Pre-production Model and Subsequent Production that these procedures would be included in the manuals. The manuals will be delivered with the first machine. Distribution: . 1 - Attendees 2 - Approved For Release 200 MV ib -. 1IAl8 71 A000400030094-7 25X1 Approved For Release 2005/06/23 : CIA-RDP78BO5171A000400030094-7 Approved For Release 2005/06/23 : CIA-RDP78BO5171A000400030094-7