MONTHLY CONTRACT STATUS REPORT NO.
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP78B05171A000400020036-2
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
3
Document Creation Date:
December 28, 2016
Document Release Date:
February 1, 2005
Sequence Number:
36
Case Number:
Publication Date:
November 3, 1971
Content Type:
REPORT
File:
Attachment | Size |
---|---|
CIA-RDP78B05171A000400020036-2.pdf | 87.13 KB |
Body:
Arr~1A
Approved For Release 2005/02/17 : CIA-RDP78B05171A000400020036-2
.lame of Contractor 25X1
>`:O:+T ELY CC::L'ACT STATUS RE FORT NO.
For Period 1 October 1971
25X1 Contract :o Task No.
Period of Contract 26 April 1971
25X1
Amount of Obligations
and/or Expenditures This Period:
Amount of Obligations
and/or Expenditures to Date
Estimate of Funds to Complete .
Percentage of Funds Expended to date
Percentage of Work Completed to date
31 October 1971 Date: 3 November 1971
Project No.
30 May 1972
(Note: All amounts shown must include overhead, G&A, handling charges, fees, etc.)
1. Is work on schedule? Yes (Attach sheets if necessary)
3. Can the Contract be completed with the authorized funds? Yes
Comments: (Attach sheets if necessary)
Can the Contract be completed in the authorized time? Yes
SEE ATTACHMENT #1
Technical Progress in Period: (Attach sheets if necessary)
SEE ATTACHMENT #1
Objective for the Next Period: (Attach sheets if necessary)
Submitted by
SEE ATTACHMENT #1
Declass; WbR iP-pRc4iC"G;4QQ2/17 : CIA-RDP78BO5171A000400020036-2.
25X1
Approved or Release
25X1
MONTHLY TECHNICAL PROGRESS REPORT #5 - ATTACHMENT #1
The Preliminary Design Review was held on 22 and 23 September 1971 at
the contractor's facility. The Preliminary Design Review Briefing Package presented at
that time is included in this report as attachment #2.
A mock-up of the HILS utilizing the tungsten-halide lamp was demonstrated
in the GFE MLT-1540. It was an optically complete HILS, with motor-driven iris dim-
ming control, placed in proper relationship to the background lamps beneath one of the
viewing surfaces, allowing direct comparison between the HILS and the standard viewing
surface on the other side of the MLT. This mock-up did not include the motion or tracking
systems.
The design approach utilizing the ELH lamp, as presented and recommended
in the Briefing Package, was accepted by the customer with two points being raised:
the possibility of reducing the shadowing of the background illumination by the HILS
assembly with a slightly smaller configuration utilized in the final design; the proposed
maximum HILS motion speed of 1 "/sec. to be raised to 5"/sec. as a design goal.
A demonstration for obtaining higher light levels was presented; techniques
included removing the color correcting filter, changing the spot size, and changing the
diffuser (see attachment #2 for details). Light levels in excess of 200,000 foot lamberts
were shown.
Technical Progress for the Period Included:
Completion of Study Phase of program
Completion of the HILS mock-up assembly
Completion of temperature and cooling tests
Basic design for the final HILS assembly completed and
optical components defined
Approved For Release 2005/02/.17 : CIA-RDP78BO5171A000400020036-2
25X1
7 5/02/17: CIA-RDP78B05171A000400020036-2
Completion by contractor and acceptance by customer of PDR
(as summarized in attachment 112)
Objectives for the Next Period
Initiate detailed design of light tray
Initiate detailed design of motion system
Establish specification for all optical components
Procure background lamps