BI MONTHLY PROGRESS REPORT, CONTRACT(Sanitized)

Document Type: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78B04747A001600020096-8
Release Decision: 
RIPPUB
Original Classification: 
K
Document Page Count: 
7
Document Creation Date: 
December 28, 2016
Document Release Date: 
April 19, 2000
Sequence Number: 
96
Case Number: 
Publication Date: 
December 30, 1963
Content Type: 
MEMO
File: 
AttachmentSize
PDF icon CIA-RDP78B04747A001600020096-8.pdf184.51 KB
Body: 
DECLASSIFICATION REVIEW BY NIMA / DoD TO: SQ itM9cting Officer FROM: Project Engineer, E80 SUBJECT: Bi Monthly Progress Report, Contract DATE: 30 December 1963 A. General The progress report is seperated into several sections, the first of which is a percentage summary of the schedule. This is followed by a statement on the progress and remarks on work completed, work in process and planned work effort. Finally a table showing each task and the percentage complete is supplied. B. Schedule Major Project Tasks Percent Complete Percent Required By Project Schedule I System Engineering 75% 100% Il Subsystem Design 50% 50% III Construction and/or Purchasing and Assembly 100/0 10% IV Testing and Debugging (0/o 0% V Final Inspection 0% 0% As indicated in the project completion percentages, the project is progressing according to schedule with the exception of two tasks identified in the listing in Table I. It is expected that these will be completed in January. C. Summary of Progress 1. General The major effort has been directed toward specifying the components having long delivery times; such as motors, large machined parts, special heat sinks, instrumentation, etc. Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020096-8 Memo No. 1040 - Aq%w&ed For Rely a 2000/06/07: CIA-RDP78BO4747A401a 00020096-8 2. Coordiratograpls Ile coordinatograph structure has been designed, detailed and released for manufacture. ` Hce the delivery time for this assembly is approximately 16 weeks, it is planned to prepare a test riq to check the power controls. The drive motors and some of the ri st apparatus will be used in the final assembly as well. T;.e motors have been ordered and the delivery of one is expected by January 2i. In the operation of this test apparatus, cold air from outside the i;uildinq will be used for t_axtractinq heat from the motors and control console. Measurer;,ents will be made on air temperature and volume required to confirm prediction,-. 3. Power Control the motor pow-r control circuitry except for the power supply portion, has been designed and some of the parts have already been received. All the copper heat sinks and the frames that hold them have arrived. 4. tyl ectronic Control The data handl ing logic has been nearly completed; the compattTiottirerface amplifiers are being designed. More communication with th engineers will be necessar-, o determine the best way to terminate the 75 foot long computer lines supplied to the plotter room. 5. Meeting A meetinr3 was held at the installation, December 10, 1963, to discuss the air cooling and vacuum system requirements. It was decided that the existing coot air supply in the Luilding was insufficient and that an auxilliary conditioner would be installed to produce about 600 cfr;t of 420F air. A seperate vacuum system to supply about 80cfrm at I psi vacuum would also be installed. Planned Work i f fort As the components arrive, the plan it. to incorpor