APRIL PROGRESS REPORT, CONTRACT(Sanitized)

Document Type: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78B04747A001600020028-3
Release Decision: 
RIPPUB
Original Classification: 
K
Document Page Count: 
6
Document Creation Date: 
December 28, 2016
Document Release Date: 
April 19, 2000
Sequence Number: 
28
Case Number: 
Publication Date: 
April 30, 1964
Content Type: 
MEMO
File: 
AttachmentSize
PDF icon CIA-RDP78B04747A001600020028-3.pdf305.62 KB
Body: 
Approved For Release 2000/06/07 : CIA-RDP78B04A STATOTHR Memorandum STATOTHR Memo No: 1139 STATOTHR TO; Cortracting Officer FROM: roject Engineer, E80 SUBJECT: April Progress Report, STATOTHR DATE: 30 April 1964 A. General Progress this month has been better. The coordinatograph assembly has arrived and appears to move quite smoothly by hand. The motors and tachometers are being installed now, though, the motor control system is not yet complete. The control cabinets, painted green outside, white inside, have arrived. The pie-wired racks are being installed and further testing will continue, The paper feed system design is complete and manufacturing has begun. See the schedule EY00/ for further details. Schedule Percent Required r,"Aaaor Project Tasks Percent Complete By Project Schedule I System Engineering 100% 100? II Subsystem Design 909 1000/0 Ill Construction and/or Purchasing and Assembly 309; ~ 60?io IV Testing and Debugging 20% 3090 V Final Inspection O% 0 C. Summary of Progress 1 , f'ror;ramming We sent a table of the data format BJ0002 for information to the programmels. DECLASSIFICATION REVIEW BY NIMA / DOD Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020028-3 joved For Release 2000/06/07: CIA-RDP78BO4747AO01600020028-3 Koom Preparation STATOTHR We called the GSA to check on progress and found that the electrical engineer assijned to the jol.', has been trun.fo-rr M.I.r. mechanical engineer is still working on the coolant system, howevi r, even he has been busy on other special projects. will be taking the responsibility for the job now and expects that work will begin soon. He will keep in close touch with us. STATOTHR The general plan is to start with 850F air, pass it over a pre-cooling coil at 650 cfm, then pass only 100 cfm of that over a small chemical dehumidifier. Next it will pass over an after cooling coil which will have the required output of 420F, 45% rh air. Since we will have a closed system the small sized humidi- tier will amply take care of the problem. Planned Work Effort The general schedule is as follows: N1aY_ 1 . Transfer veloe;ty loop rack to main cabinet. Ins[,--ill all printed circuit boards and test electronics. 3. Assemble miscellaneous mechanical parts. June 1 , Test servos on coordinatograph 2. Test electronic control. by roved For Release 2000/06'/07 : CIA-RDP78BO4747AO01600020028-3 Approved For Release 2000/06107:--CIA-RDP78BO4747AO01600020028-3 art on 5 roe ct I UsKI i roj:cir ~c,sEc; _.t.?rat rirrewtin rs`clo _:jossi~ty _~ ,c eifiCatirsil5 1. trictur L riv': y t..rii .y, u3"rr311 rT< n.'erin 4. +'CS t?r '4 ubsysten 100 100 100 100 100 (ectrorrics e?onrr~ Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020028-3 Approved For Release 2,D,10 E16 rr 9t A'E 79,13 4747A001600020028-3 rcj(ct risks tructuru C7f.3 Cc '. i f'EClt"J~I~~f'i 41. rli i t?rt and i wi e3. _?nti'y ana Carrie;. c. Vacuum Flaten %rivc _ y t& to la cr Controi owcr _:,u i~) ly e tC3~t i p Graft ,ot Load Calculations urFan n ira c,ring tiur:i S`:ontrols Co in try, 100 100 100 100 75 100 100 75 100 ipLr i= ;:;d -,ulbsystem ri n; i i,~ ac r~4ctr is E. on -r3~ to i l e c4 L,::),.s Ac 75 p-ciul Circuit .. si,4n 75 ,,:ickc ui ti obl,, ' llotrix:nt 50 { . xi< In trurii-,nto6a i 100 is r t Loud `,.ulcul?tion 100 Approved For Release 2000/06/07 : CIA-RDP78BO4747AO01600020028-3 :l ;turfy?.,'- t[.. !t)rT t C, Approved For Release 2000106/07 : C1A-RDP78B04747A00.1600020028-3 Ij t t= . J+x y C1flJ Crria IOWt,V ontr 1 r. Test t: r'r