CONTRACT(Sanitized): TRAVEL COSTS CLAIMED BY CONTRACTOR

Document Type: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78B04747A001600020012-0
Release Decision: 
RIPPUB
Original Classification: 
U
Document Page Count: 
2
Document Creation Date: 
December 28, 2016
Document Release Date: 
April 20, 2000
Sequence Number: 
12
Case Number: 
Publication Date: 
December 15, 1964
Content Type: 
MF
File: 
AttachmentSize
PDF icon CIA-RDP78B04747A001600020012-0.pdf151.38 KB
Body: 
Approved For Release 2000106/07 '1A D P78B04747A001600020012-0 Declass Review, NIMA/DoD 15 December 1964 M dORANDW, FOR: Chief, Procurement Division, OL ATTENTION: Contracting Officer STATOTHR SUBJECT: Contrac Travel Costs Clam ' NCi STATOTHR STA- THR?' (a) Letter Doted 23 October 1964 from (b) Notice of Costs Spent a d./or Disapproved, No. 2078-1, Dated 15 October 1964, Voucher No. 2556 1. It is requested that the propriety of the costs cited in Refer- ences (a) and. (b) be determined at the time of contract settlement. NPIC will concur with the findings of the Procurement Division at that time. 2. Inasmuch the trips cited in Reference (a) were made at the request of the Government, NPIC does not question the propriety of reimbursing the contractor for travel and subsistence expenses incurred'. thereby. Hiever, considering that delivery and installation instruc- tions in the Schedule of the contract itself stated that "the contractor shall likewise provide the Technical Representative with installation instructions, per requirements and venting if required, to provide the proper space and service facilities at the installation site", the additional charges for the time of a Senior Engineer at $iL4.0O per day do not seem to be justified. 3.. It is our contention that the contractor is required to provide precisely the type of information elicited at these meetings in satisfac- tion of the contract, i.e. data concerning the technical features and characteristics of the instrument which had to be known in order to equip a room in which the instrument could be used. In other words, the con-= tractor's engineer was assisting in site preparation only indirectly in Approved For Release 2000106/07: CIA-RDP78804747A001600020012-0 Approved For Release 200fOI06/07 :,CIA- QF8 B04747A001600020012-0 STATOTHR SU T `T? Contr%ct- Travel Costs Claimed by Contractor that certain technic=al characteristics oaf' the equipment had to b e mscc known before the site could be prepared. Under the terms of the contr ct, the engineer would have had to furnish this information either here or at his plant, end it does not seem appropriate that the time spent in doing that should be treated as an additional cost. Furthermore, GSA an,,'. Agency personnel who attended, these meetings stated. that the contractor's engineer had not properly determined environmental and installationa` requirements for the equipment a:,nd'., ineed, derived many of these da..t? only at the request of Government personnel. At the 10 September meetin sosz seven months after the initial meeting, the contractor's engineer stated that the results of testing at his ,plant during the. preceding !s had nullifier the date., given previously to the Government and on basis of which the Government had already spent approximately $7,C930 for ME 'A70THR 4. he NPIC Technical Monitor for this contract, stated that vs he remembers it he had, concurred with the contractor's suggestion that an invoice for these costs be submitted, but that he had not made a coimnitme:nt as to whether or not they would be al.l..-Ned STATOTHR Assistant for Administration, NFIC Distribution Orig. & 1 - Addressee 1 - P&DS 2 - LB/8S/NPIC LB/SS/NPIC :2623(15 Dec 1964+) STATOTHR o Approved For Release.2Q00/06/g7 -C t9P78B04747A001600020012-0