(Sanitized)RECD TDY REPORT (Sanitized) SEPT 66 - 15 JAN 67(Sanitized)

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP78-05601A000100250004-9
Release Decision: 
RIPPUB
Original Classification: 
S
Document Page Count: 
18
Document Creation Date: 
December 9, 2016
Document Release Date: 
August 9, 2000
Sequence Number: 
4
Case Number: 
Publication Date: 
November 15, 1967
Content Type: 
PERRPT
File: 
AttachmentSize
PDF icon CIA-RDP78-05601A000100250004-9.pdf1.2 MB
Body: 
Approved For Release gat:11/03/03 : CIA-RDP78-05601A000100250004-9 *411b. BROD TIM =POW f3eirt 66 - Jim 67 25X1A2g 25X1A2g 25X1A9a Approved For Release 2001/Mafel1a6OP78-05601A000100250004-9 Approved For Release 20,01/03/03 : CIA-RDP78-05601A004100250004-9 25X1C4e 41,41104,44T warns =MARY 1. Engineering Problems 1.1 Drawings 1.2 Specifications 1.3 GPM 2. Change Orders 2.1 Gpper Comp 2.2 Lower Camp 3. Pield Support 3.1 Station 3.2 Base 3.3 4. Contractor Evaluation 4.1 Personnel 4.2 Workmanship 4.3 Financial Resources 4.4 Crganization 5. Field Criticism of the Construction Project 5.1 Project Management 5.2 Construction Commitments Recommendations 6.1 Technical 6.2 Managerial Appendix A. LettetAILL1 Sept 1966 to 25X1A2g froillIllIl Site Engineer, subject: Preliminary Drawings. B. Summary of Lower Capp Change Orde Lower Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 25X1C4e 25X1A2g Approved For Release2001/03/03 : CIA-RDP78-05601AGI00100250004-9 SECRET SUMMARY Delayed and damaged QPM, and a breakdown in communicationS between Headquarters and the COB were the most eignificant problems encountered during the course of thip TDY. The 'delved OM set the rate of the job and prevented earlier coepletion. The breakdown in communications between Headquarters and the COB resulted in a negative climate which definitely influenced the COB'; conduct towards those who represented the Headquarters element. AlthoUgh this report blem areas, it is not intended to dieinish the fact that the construe- 25X1A2g tion is rapidly nearing completion under what have been extremely difficult field conditions. Reeommendations at the end of this report suggest means of eliminating the aforementioned and other problems by establishing procedures which insure greater Supply Division project participation, designate permanent "project engineers", and call for the establish- 25X1A2g ma of direct Contractor relationships. It should be noted that these Recommendations are based on field observations which to some degree may be altered by Headquarters considerations unknown to this writer. Approved For Release 2001/03/Q3 ? q14-NP78-05601A000100250004-9 Approved For Release 2401/03/03 : CIA-RDP78-05601A000100250004-9 125X1C4e SECRET Problems 1.1 Drawing* The construction drawings were, for the most part, a e actory. However, in several critical areas, they were somewhat lacking in detail, incorrect, and incomplete. The Upper Camp Operations Building air conditioning drawl r. ILmaigimilidomewhat lafilleg.in detail. The Contractor and the ...Mate Engineer were unable to determine 1.1.,?gtioning Piping layout from this drawing. It should be pointed out that a person with U.S. equivalent air conditioning experience would probably have been able to devise and install a suit- able air conditioning piping viten% without detailed drawings. However, the Upper Camp Specifications only stipulated that "...the install.ation shall be accomplished by workmen skilled in thia type of k..."1 The COntractor's position generally supported by was that he would provide people skilled, by local standards in the all:sal installation of tha,air conditioning piping, but t this did not mean that these persons must be able to devise a suitable piping system. The impasse was resolved when a Electrical Engineer then at the site agreed to supervise the complete powerhouee inatalla- Um while the Contractor would commission a European air conditioning master to devise and install a suitable air conditioning piping system. In several areas the manufacturers as well as the contract drawings were incorrect. The pelletiser perma-valk drawings, for example, were impossible to follow because the drawings were obviously drawn for a type of pelletizer other than that provided. In the end, these drawings were discarded and the perma-valk WAS completely reconstructed. In other instances, the drawings were incorrect in that they specified items to be a47.44 which were Contractor-furnished, and other items to be Contractor-furnished, which were OFM.3 3-Section 1S-07, AIR CONDITIONING EQUIPMENT) Specifications for Upper Camp Paciljtjes, May 1966. 20enerator Anchor Bolts, Upper Camp **tor Pool Fuel Pump, laver Camp 3Uhit Heater Ilia Pump, Lower Camp SECRET Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 25X1C4e 25X1C4e 25X1A2g 25X1A2g 25X1A2g 25X1A2g Approved For Relew 2001/03/03 : CIA-RDP78-05604000100250004-9 SECRET The most serious 9robi.rte with the drawings, however, resulted from the fact ttat they were incomplete. Although V$ advised, in writing,more than a month prior to the signing of the Lower Cam contract thai seven drawings had beeenmitted, they failed to inplude these drawings in the final contract drawings. In fact, the omitted drawings had still not been provided three menthe later tree-tor was forced to use unofficial drawings rovided by the Site Engineer. 1.2 Specifications The specification; were semetimes unclear as to responsi- occasionally wrong, and often unrealistic. As e. result, generally ignored by and the Engineer. An effort vas made by all concerned to provide ontidered by the boyernment Representatives to le good practice under the existing field conditions. The lack of clarity of the specifications is best illustrated by the following examples. In eonnection With the Upper Camp air conditioning the Contractor was requested by the Site Engineer to balance the System and conduct a perforMance Cheek. The Contractor at first refUsed to perform these operations based on the argument that the specifications did not require it. ln fact, neither Specifi- cation M2-13, AIR BALANCING, or M2-16, PERPORMANCE, of the Upper Camp Specifications stipulate that the Contractor shall perform these operations. in the end, the ContraCtor did decide to balance the system and conduct a performance test. in another instance au attempt was made to get the COntractor to operationally test the Upper Camp generators. The Contractor reflood to take ally respons.bi1ity for the operation of theie units again barged on the argonaut that the specifications did nat require him to do so and because heron he could not assume any reeponsibility formistakes whiCh may have occurred at the factor/. Pneoirication 13, GENERATING =TS, DUsX,PZECISItCs Upper Camp Specifications, refers only to the "installation" and not the "operlii2a1 testing" of the generating units. ftrtunately, there was aElectrical Engineer A. SECRET Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 25X1C4e 25X1C4e 25X1A2g 25X1A2g 25X1C4e 25X1A Approved For Re!eau 2001/03/03 : CIA-RDP78-05601.A000100250004-9 SECRET at the site at the time vho we able to correct factory errors vhieh actually did exist in the 4rin of the generators. X n some cases the specifications were simpiy wrong as with Specification C-4, FENCE, CHAIN LINE, Lower Camp Specifications for the "...erection of Government-furnished chain-link fence, complete..." Although this fence was neither intended to be OFM nor was it included in the list of OFM, the Contractor simply stated that since the specification referred to it as GPM, and the drawings did not contradict this he assumed it ws Oaf. In the end the fence was purchased by th; Government. In many cases the specific tions yore simply unrealistic. FOr example; Lover Camp Specification 3P-0081 SHOP DRAWINGS, requires that theContractor sUbmit phop draVings on GPM; Lover CanT PPenifica- tion S145, (=CRETE) SAMPLES AND TEST res that the Contractor provide test Wlinders vtion no teat lab exigted in the country for testing them; Lower Camp Specification Sl, CONCRETE, and 0-3, STASELTZED-AOGROGATE BASE COURSE, re quire aggregate grada- tions 'Mita the Contractor could not possibly have met using the local river gravel he had been given . =Iasi= to use; and Lover Camp Specification E3, GENERATING ta So DIESEL ELECTRIC CLEANING AND PUNTING 02' UNTERGROGND TANKS, requires that the unlerground tanks, be coated with coal-tar enamel even thOugh the Contractor *bates that he ttlIlat the time the 'pacification was written that coal-tar s not be obtained in the country and that be had DO inten- tion for coal-tar enamel and rUbstituted cut-back asphalt. 25X1C4e 1.3 Gover13ment-F4rnished Materials Most materials, with the exception Of the pa etiex units, .zrivad at the site in good condition. However, the rate et progress of the job was constantly set by the rate of arrival of the OFM. Most mechanical and electricel items arrived in good condition. However, one trWafOrMer WAS 44MAtled 433d the air conditioning arrived with all of the mechanical linkages loose. 7b.s.1 in particular, arrived in excellent condition. This resulted primarily from the fact that all member* were packed with heavy timbers and angle tron covers on all corners. Minor erection difficulties were encountered in that all Darts were met good :matches and it was necessary to use a cutting torch on maDY holes and some lengths. SECRET Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 Approved For Releate 2001/03/03 : CIA-RDP78-05601 000100250004-9 SECRET audition of the palletiser units on the other hand WA fair and in the case of the erected units, deplorable. for example, had to be completely reconstructed. The h car vas so completely damaeed that it required 200 onsiderable cost to repair it. The interior Stalls of ere completely broken out, pipes were broken, the tntertQr wall covering vas ripped, and the water cloeets were broken. The unit vas eo constructed that repairs were very difficult to)make, i.e., mastic sealed plastic sewer pipe and inaccessible aoldered water pipe connections. Most of this dame reoulted from the fact that there was ga Peeking of the erected units. the Lower Capp units, with the exoegion of the erected units, were not severely damaged. Bowever, at least one-third of the units suffered Same water damage reaulting in loose and broken linoleum. These units also suffered some damage to the exposed panel corners resulting from the inadequate packing in 1/4.inch plywood lbs rate of progrese of the job waa constantly set by the rate of arrival of the GPM. Per exemple: from 19 September 1966 to 18 October 1966 the Contractor was deleyed awaiting the arrival of the Operations Building Solex Lights, eppremimately 50 meters of chain-link fence, the water pumps and preseure tank*, and the power house unit heater; from 16 Deceither 1966 until 9 January 1967 the Contractor vas delayed on the Lower Camp wiring installation because the GPM vire had not arrived; and from 7 January 1967 until at least 15 January 1967 the Contractor vas delayed on the palletizer erection because the OM fasteners, flashing, and the eqpipment had not arrived. 2. Change Orders Change orders were Lsued. either out of engineering nece5aity or because there was a need for facilities over end above those aUed for in the basic contract. During the period of this TDY no change order requested by the COB vas ever refused. 2.1 Upper Camp 7ba final number of change orders was between ko end 50. The exact number is unknown since no formal procedure existed for itemising and controlling these work items. 2.2 Lover Camp Drizgthe period of this TD!, twenty-six change orders were 25X1C4e issued to A rigid procedure for issuing these chm:momm orders was oUowed in each case. Once it was agreed by the 25X1A2g Site Engineer and the COB that a change order was neceury1 tmal signed document was prepared and given to 25X1C4e Approved For Release 2001/93iO3 itili-RDP78-05601A000100250004-9 5X1C4e 5X1A Approved For Re!eau 2001/03/03 : CIA-RDP78-056014000100250004-9 SHCRET This document included a chaege order number, dec'j.tjye title, verbal description gpplicable gpecifications, and au engineering sketch. A $ummary Of the Lower Capp change orders issued to is given in Appendix B. In addition to the above twenty-six change orders, four Mr.Vairrig Jointed and administered directly by the These ehanego orders were for: (1) construc- tion of an indisenoue toilet in the Industrial Area; (2) inStallation of interior partitions, interior electrical work, nod heating units in the Buildings; (3) installatioa of interior palletizer plembing; and construction of a co line from the Upper to the Lower Cagp. 3 Field Swop 3.1 Station The Station logistical support was very good. The Log obtained all materiels that were requested and delivered them site vitas, the time limits epecified. (Won* occasion he wee able to completely fabricate and deliver to the site several hundred anchor bolts of widely different sizes in leas than five days. 3.2 Buie A large amount of material eepport, including gelvanized antenna hardware and special tools ehich were not available in the country, vas provided by the Base. Durieg Ulmer Capp construction this MilltCrial 145 provided only with the greatest reluctance and solicitude. However, during Lower Camp construction the situation improved and all requested support WAI freely provided. 25X1C4e 3.3 25X1C4e were cepable and the inspection provid was good. In several instances, these representutives suggested valuable engineering changes which were incorporated by change order. 25X1C4e On the other hand, support provided by the District Office was very poor. 'Or example, although the Chief of the 4Iet*ict Construc- tion Branch wee informed, in eritiug,5 as early as 11 September 1966 58es Appendix A. Approved For Release 2001/tf/Cf3!61X-RDP78-05601A000100250004-9 25X1A 25X1A 25X1C4e 25X1A 25X1A2g 25X1C4e 25X1A2g Approved For Releue 2001/03/03 : CIA-RDP78-05604A000100250004-9 SM0RST Capp drawings had been omitted frau the preliminary drawings, he failed to imam& these drawings, or other eneeted in the letter, in the final contract drawings released to the ContretO2' on 22 OetOber 1966. MO stated that there was not to make the requested Changes or include the missing a result most Of the ()Pitted work and requested Changes ed on a Change order and more expensive basis. 25X1A des and guard hauae. Although they agreed to provide these services, they actually provided only drafting Services and the EnSiteers then at the site had to do the complete de?ign including all details. third instatce following Upper COM completion visited the :site and at on the lover e I change orders must be be him for approval and that he it turn would immediately the order to proceed On the Change Order to the Contractor. flowerer although twenty-six Change 'orders were forwarded to the in the period 14 October 1966 through 25 December 1966, of 29 December had not received the first order to on this Ohm& Order work. Letters and messages inquiring about these change orders were never the Contractor in practice began working on Asubp basie of caebot copies of signed correspond- the 111E1 Site &silo-leer to a final example, repreeentatives of etated on 11 December 1966 that a design for the Upper-Lower Camp it OM week for change order eatedly answerB were e Engineer requested another instance, a scope cr was requested to generator building Line would be re ions. Although requested information on the fortMoming. On 29 December 1 e by mornge that change order negotiation on the Como Line be initiated immediately. On 30 December an ameverwas received at the site stating that the design would be ready ou 2 January 1967. On 15 January Praimimary COIMM0 Line draVings were finally received at the site and vire unsatiefactory. The drawinge were Standard details using hardwire only available in the U.S. and using steel poles burled 6 feet in solid rock. On 18 January 1967 a meeting wee held with repreientatives to discuss the design. At this meeting it was decided that a eogpletely underground lime 'would be the most economical. Melly, on the afternoon of 18 January 1967 the Contractor was ippromehed officially concerning this work. SXCR3 T Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 25X1A2g 25X1C4e 25X1C4e 25X1C4e 25X1C4e 25X1C4e 25X1A5a1 25X1A5a1 Approved For Releage 2001/03/03 : CIA-RDP78-05604A000100250004-9 4. -49,r aluation 4,1 Peri 1 The project See SECRET and site invert ;Aga were perm Other on en, employees with limited skill levels hired for the dura- Although the COntractor was able to realize a finan- through the use of largs nuMbers of indigenous eMployees, of the work and adequacy of the supervision sufrered WOrkmanship Ths workmanship wea? cxce13.nt by local stntadz, but was ObZY average by U.S. or European standards. 4.3 Financial Resources The Contractor was cepa and willing to continue the job .v* wtiexi PlYnents were Wit forthcoming. As a case and point, the Contractor received the first artial payment for the t.er Cmmlo oonstruction on 24 October at a time when construct on Wee over 98 permit coMPlete. 4.4 Organisation The Contractor's headquarters organization is divided into nein diviiions: (1) Tolustriel; (2) Highwaya and Roads; (3) MudiahiP4 end (4) HeevY Construction. The head of the Buildings Division is in charge of all overseas operations. Overseas operations are in turn broken down geographically. Each overseas fice apparently has a large measure of autonomy and only depends on the headquarters element for financial and some logistical support. The Site Superintendent on this job had rull authority to accept for the company any Change orders. /he Project Manager had contracting euthority in the neighborhood of one million dollars. SECRET Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 R B T Field itiiam of the PnetFactdon Proolect ticisms of the conotruction project are iwen below. plplatineplitaKplir trip, but are particularly impor- represent a breakdown in communications which influenced the COB's conduct towards those who represented adquarters element. 5.1 Project Management The COB was of the opinion that although he was responsible for all field activities in his area' he was neither sufticientlY sonsulted nor kept adequately advised of the plans, schedules, and Beadquarters actions connected with the construction project. 5.2 Construction Commitments The COB felt that varioua RECDpersomael had. made construe- on commitments which they had tailed to halm. Ay wt17 of example: he states that he was assured that the final plans would include a security fence around the entire Lover Camp area ani a commnnicattons line from the fter to the Lover Camp. These items were not included in the final plans. 6. Recomoepdations 6.1 Technical a. The use of local materials, and meth should be stressed on all projects where cons primary consideration. of conatruction tion time is the b. When local materials ond methods of construction are inadequate and time permits, prefab metal buildings should be used in preference to palletizer type construction for all purposes including housing. c. Xf palletizer type construction is d.? it should be restricted to the "basic" housing units only. The use of erected units and units requiring flaehing or pluMbingwork should be eliminated. The only exception to this would be the use of palletizer construction whicE is campletel,y transported, erected, and sold erected-at-site by the manufacturer. d. No prefab units of any type should be purchased without, as a minimum, an inspection as to the adequacy of the packing. SECRET Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 25X1C 25X1A2g 25X1A2g Approved For Releass.2001/03/03 : CIA-RDP78-056014000100250004-9 SECRET On all jobs involving 4 great deal or 07M a Supply be assigned to RECD to advise on lead times, re, verify the adeemecy of all peekine, follow nts and function as the final authority on procurement matters. forailliru prepared by se eaticjagi be cet,e1y revi eve before they are released for construction. afr , 6.2 Mansaertal CL jtu a. Cue engine &Auldbe&Wald al 1**Igact eadinfter" CrQ-11)/ for eseh Job from its ,conseption to its ccupletion. %hie indivi- , 7 levject coordiaation.. Be should be assigned regardless of dual should be responsible for all M externa D l as well as internal yirk enansering branch for hes, 461 "prOjeCt engineee, wOULd be serving in a stanagerial rather than technical capacity. Be ver, continue tO serve in las area of technical VocialitY. Such a procedure would issure continuity, fix responsibility, and improve project coordination. b. When aey RECD representative has conversations with field personnel which might be construed to *omit RECD to some course of action, a Simoraztdxsu of Conversation should be written and sent to the tieldZon coneurrenee. %his would prevent misunderstandings concerning RECD construction commitments. e. Prior to the= of am RECD engineer to the field, he and his supervipor should prepare a guideline outlining hie field 4144i404 functions, and authorities. A copyjof this guideline would then be forwarded to the area division and CDS. The prepare- tion or this document would Insure that the ludividual and his supervisor agree 46 to. the ;Individual's intended field activities. Pb? the COSA this document would nerve am an introduction to the individual and insure that there would eat be any mieunderstandimge regarding the individuel'e future actions. d. radependent relatbicsaihips should be astialished with several vorId.wide contractors capable of performing "turn-key" 3ob? Such relationships, restricted to the highest members of ths convany? would provide amens whereby jobs requirilu; mini- NOM teentruction times could. be "controlled" directly blY RECD iiiiiratherthanthroughathirdparty.Suchanarreenentwould 25X1C Amtwed For Release 2001ema RCIA-RDP78-05601A000100250004-9 25X1C 25X1A2g 25X1C4e 25X1A2g Approved For Re!ewe 2001/03/03 : CIA-RDP78-056Q4A000100250004-9 SECRET 11 Septnber 1966 De (Chief, Attsabed are the comments by personnel here concerning the Lower CamP preliminary drawings. Two points are of particular concern to (COB). First) the possible contamination of the spring from our case poolo (Comment a, Sleet 114441-).c1), and seeond, the need for more room for expansion hftris(partstudexitecainent g, Sheet 16-06-10-2C). (COB), gad T will cheek into these two items and forward our comments to you as soon as possible. I hoe 0111111tElectrical Engineer) found time to review theae drawings vbile in (Capital City). If not, he cen do so here. einaer.41 SECRET Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 25X1A2g 25X1A9a Approved For Relel,?e 2001/03/03 : CIA-RDP78-056Q4A000100250004-9 SECRET Sheet Comment 11 Septedber 1966 11+01-01 a. Dip section should be indicated on plan view. 1C b. WIN in the Dip slab and temperature steel in the Dip Dige Beam are required. c. Rip rap Should be used on both sides of the Dip section. d. Steel dowels Should be used at the transverse contraction joints to prevent differential settlement when cracking occurs. 16-06-01 a. Structural details of the culverts of and 1C culvert headwalls should be provided. b. Rip rap should be provided at the downstream end of all culverts to prevent undermining. c. An (Eastern) washcar shouldte provided in the Industrial Area near the (Western) waahcar (GFE). d. An "A" frame for unloading cargos should be provided Lear the warehouse. (Di trict Office) has SketChes. e. There mmst be. facilities either inside or near the Motor Pool for washing vehicles. 16-06-01 a. The Como car must be moved to a location on a 2C hill.slightlY to the south of the site. It will be neeesSary to eonetruct several antenna founds,- tics* and a Comm cable system between the Upper and Lower Cps. b. The Recreation Building should face the roadway. e. Bldgs. 110 through 114 should exit on a walkway running between these Bides. and Bldg. 115 through 118. Approved For Release 2001/0%/83C:tWiRDP78-05601A000100250004-9 Approved For Release 2001/03/03 : CIA-RDP78-05604A000100250004-9 Meet 16-06-01 2C SECRET d. Bldg:R. 115 through 118 all face Bldg'. 110 through U. Bence the walkway behind Bldga. 115 through ila should be eliminated. e. The drive between Bldg.. 118 and 119 is for garbage pickup only. The walkway between Bldgs. 122 and 123 should extend 004 only to Bldgs. 120 and 121, but also to the front of Bldg. 119, and thence down steps to the roadway and parking area. g. It msy be necesiarY to increase the area between Bldg*. (115 - 112) and Bldg. (109 - 114) to provide for expansion of the student area. 16-06-01 a. Culvert encaaement should indicate reinforcement. 5C b. CUIvert should have rip rap at downstream face to prevent undercutting. c. Nanholo base should indicate reinforcement. 11-04.01 The cesspools appear to be located near the la source of the spring which will be used for water supply. Contamination of the spri result. Beecomendstions will be made to 11..04-01 a. Bldis. should be grounded. 25X1C 1E3 26-03-02 a. A buil line trench should be provided. 1S1 b. Pad bolt spacing is incorrect. See OCE Dwg. G. 346-91 3/17/66. 26-03-02 a. Generator sizes indicated are incorrect. See OCE Dwg. No. 346-9, 3/17/66. Apparently, the wrong OCE powerhouse drawing was copied. In addition to the above comment:, the following OCE dr a have not been incorporated in the plan: Naintenance Bldg. Layout Warehouse Layout OCT 346.12 4/8/66 OCE 346-13 4/8/66 SECRET Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 Approved For Release 2001/03/03 : CIA-RDP78-05684A000100250004-9 SECRET Motor Poo3.. Electrical OCE 346-11A 10/66 Warehouse rlectrical OCE 346-13A 4/8/66 Maintenance Bldg. Electrical OCE 345-12A 4/8/66 Motor Pool Bldg. Layout OCE 346-11 4/5/66 Lover Coup Plumbing OCE 346-4B 6/5/66 SECRET Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 Approved For Releasa2001/03/03 : CIA-RDP78-05601A000100250004-9 25X1A2g 3" SECANT of Industrial Area Bldgs. and iome roads liPProxinatekv 15.0m west, 5.0m south, 14 Oct 66. 2. Relocation of some Rousing Area pelletisers, 16 Nov 66. Complete 3. Addition or reinforcement to Roadway Dip Section and Cancelled revision of generator pad anohor bolt*, 16 Nov 66. Complete 4 Addition of tie-down hooks to center palletixer support Cnp1ete an all palletisers, 17 Nov 66. 5. Installation Q: drop manholes at Manholes No. 5 and 6 Complete Lower Camp Rousing Area, 17 Nov 66. 6 Construction of foundation for WM "A" frmse, 20 Nov 66. In Progreas 7. Construction of vehicle wash stand to be located mear 31 Progress Industrial Area Motor POol, 20 Nov 66. (As amended) 8. 20 Nov 66. Elimination or one the Industrial Area Leaching Cesspools, Complete Realinement ot the site access road so ea to terminate Complete at the (Main) Road, 27 Nov 66, 10. Construction or two additional single culverts on the Complete site access road, 27 Nov 66. U. Constrution of four CM antenna foundatioos, 27 Nov 66. Complete 12. Oorrection of ratter fabrication error 1'oill11111111 Complete Maintenance 314., 28 Nov 66. 13. Dilation of water connection to Bldg. No. 116, Lab, Cancelled 5 Deo 66. 14. Addition of Manholes NO. 7, 8, and 9 to Rousing Area Complete sow llme, 5 Dec 66. ONCRNT Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9 25X1A Approved For Relwe 2001/03/03 : CIA-RDP78-056WA000100250004-9 SECRET 441.1 Status 15. Deletion of two Street ",&" culverts and one Acceas Complete Road culvert, 5 Dec 66. 16 installation of two drop manholes in Industrial Area Complete sewer lima, 8 Dec 66. 17. Installation of Grease Trap for both Mess Bldgs., Complete 10 Dec 66. 18. Removal of four, 4-71 Genarator Sets from Upper Camp Complete Powerhouse and installetipn of said generators in Lower Comp Pewerhouse, 10 Dec 66. 19. installation of GPM 10,000 liter fuel tank at Lower CalMD /n Progress Powerhouae, 15 Dec 66. 20. Installation of GPM 4,000. liter fuel tank and 50m Of In Progress COntreet fUrmithed distribution liue in Housing Area, 15 Dec (As amended) 21. Construction of 1353m of 7-strand barbed wire fence with It Progress drop-bar gate, 20 Dec 66. 22. Erection of am Chain link fence around Commo Palletizer In Progress N. 1231 21 Dec 66. 23. increase in length of GPM chain link fence around Mater Cancelled Supply Area, 21 Dec 66. 24. Construction of 200m of protective rip-zap drainage in Progress ditches around the Industrial Area, 25 Dec 66. (As amended) 25. Construction of Motor P001 ?mace Pit wall voids for Complete future light and receptatile installation, 25 Dec 66. 26. imetellotion of A/C water lines up to bine Housing Complete Area Buildings, 25 Dec 66. SECRET Approved For Release 2001/03/03 : CIA-RDP78-05601A000100250004-9