ELECTRICAL POWER STUDIES (Sanitized)
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP78-04720A000100030037-6
Release Decision:
RIPPUB
Original Classification:
K
Document Page Count:
5
Document Creation Date:
November 17, 2016
Document Release Date:
July 6, 2000
Sequence Number:
37
Case Number:
Publication Date:
April 30, 1953
Content Type:
MEMO
File:
Attachment | Size |
---|---|
![]() | 175.63 KB |
Body:
Approved For Release 2000/08/04: CIA-RDP78-0472OA000100030037-6
30 April 1953
I~idliDd~ASI~Ii
TO z Assistant Deputy Di rector / Administration
!'Stall
S U B J E C T : Bleetrical Power Studies
a. The auxiliary generator is not adequate to carry the load
nscasasaary in tame of pourer failure.
b. The present facilities provided by the Paver Cc psny are
oat sufllelsnt to carry any additional normal load and definitely
t4 j41 omn t provide the load required during emergency operations.
25X1A6a
25X1A6a
25X1A6a
25X1A6a
OQ a. 8lmetrie power is supplied to by s single phase, 25X1A6a
50 in tr nefoanssr. Aiizillary standby power consists c a 60 K V, single
Phase 8m ' rotor. The present connected station load is approximste3y
31.7 Tit and addttioeeal cctmcanic attcrns *Suipment and an enlarged meter
supp3 y system viii add to the poser demand. Present demand under for
operating coodltiaar is a xirtely 65 &V.
b. The Virginia Electric and Power Ccspany will provide sddit-
ta si $ingle pbuae power to the transformer at no cost to the Gorerfament.
C. It is mderstood that the Commuoic*tio ns Office could sane a
6aims, ~ ~ diesel ~ available ~s 0, if the 25X1 A6a
3s,
- MI generator is now 25X1 A6a
25X1 A6a
being used at the
i W~~ffi ~ ~ ~
0
3. t:talllvl,USI03r8
V) der emergsucy conditions, vben the loud mould be sateria3.ly increased.
b. "at the atealwas requirements for standby power for operation
sakrowld be incraaaed 100%.
a. The preseent sj Bator is inadetgeate for providing
c,*) pvtrsr ootveder existing conditions and could not begin to supply parer
Approved For Release 2000/08/04: CIA-RDP78-0472OA000100030037-6
Approved For Release 2000/08/04: CIA-RDP78-0472OA000100030037-6
25X1A6a
c. That the power facilities now provided by the Virginia
Electric and Power Cc pang are not adequate for Operation.
4. RECOmanKTION8
a. That an additional 60 KW generator be provided and installed.
b. That the Power Company be requested to provide additional
1. PROBLEM
a. Auxilia standby power is not presently available for all
facilities at
b. The diesel generator which bas a capacity of 250 KW bas a
present load of 100 Kit and, therefore, does not operate at maximum
efficiency.
2. DISCUSSION
25X1A6a
is 25X1A6a
a. The 250 KW diesel generator installed at
connected only to Station buildings and not to the REP our points
of power distribution. There is no standby power for the main pump-
ing station, the eraser c 'rater pump at the city reservoir and the
25X1 A
tower Area where the Building are located. See Annex "A".
b. Standby power at all points on the Station could be provided
by purchasing the transmission facilities of the Utility Companies
and the purchase of additional wire and transformers. The Utility
dcmpanies have estimated the cost of these facilities to be $12,000.00.
See Annex "B". By providing individual standby generators at the
points indicated above the cost would be approxiaatel.y $15.500-00-
The 250 KW generator will give the total necessary emergency power,
will require only one attendant at one point, and will provide more
steady and reliable current for longer periods of time than can be
supplied by individual generators.
3. CONCLUSIONS
a. That the buildings at the tower site, the water pumping
station and emergency water pump
critical nature and should be provided with auxiliary powam of a er.
b. That the most economical and practical method of providing
of the t e~sting electrical
this needed protection would be the purchase
transmission lines and providing necessary
Approved For Release 2000/08/04: CTA-RDP78-04720A000100030037-6
-2-
Approved For Release 2000/08/04: CIA-RDP78-0472OA000100030037-6
4. P=mzmTIf
a. That action be initiated to purebaae the transmission
facilities from the Utilit Companies and provide standby`poteer to
all facilities at by maxim= use of the presently
installed 250 XW genera r.
Enclosures (2)
25X1A6a
25X1A9a
Approved For Release 2000/08/04 : CIA-RDP78-04720A000100030037-6
25X1A6a
Approved For Release 2000/08/04: CIA-RDP78-0472OA000100030037-6
Approved For Release 2000/08/04: CIA-RDP78-0472OA000100030037-6
Approved For Release 200 W. CIA- K" , 100030037-6
Security Snforr:,,
? 1uthL "B"
Estimated cost of all electrical transmission facilities,
less transformers, from property line on
owned by Power Company
Cost estimates submitted by Virginia Electric and Power Company and The
Chesapeake and Pot mac Telephone Company for Electrical. Transmission Lines
at
25X1A6a
25X1A6a
25X1A6a
Estimated cost of Transformers at Sewage Disposal Plant
at Reservoir
$ 3,696.30
619.32
Estimated cost of all Transformers at less
M
those at Sewage Disposal Plant and at
rvo r
2,811.52
Total estimated cost of all Power Company equipment and
facilities
$ 7,12I.1A
Estimated cost of poles owned by Telephone Company
77%.566
Total estimated cost of all facilities
$ 7,911.70
Total estimated cost of additional transformers and wire
li,088.30
TOTAL ESTIMATED COST
$12,000.00
ivriu;:iY I IHL
N DE IJ\L
C==0
Approved For Release 2000/08/04: CIA-RDP78-0472OA000100030037-6