PROGRESS REPORT - SPECIAL PROJECTS
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
CIA-RDP78-04718A001000030003-6
Release Decision:
RIPPUB
Original Classification:
S
Document Page Count:
4
Document Creation Date:
December 9, 2016
Document Release Date:
June 7, 2001
Sequence Number:
3
Case Number:
Publication Date:
November 26, 1954
Content Type:
REPORT
File:
Attachment | Size |
---|---|
![]() | 213.78 KB |
Body:
Approved For Release 2001/08/10 : CIA-RDP78-04718AO01000030003-6
Logistics Office
Real Estate & Construction Division
Space, Maintenance & Facilities Branch
Pro ect
PROGRESS REPONT - SPECIAL PROJECTS
Estimated
Estimated Completion Percent
Cost Date Completed
1. Alterations - South Building $101:950.
Removal and erection of partitions;
provide air conditioning; increase
electrical service for entire building
including installation of new power
panels, switches and feeder lines;
special treatment in certain rooms to
include wall covering, fluorescent
lighting, furred ceilings, sound-
proofing, wire raceways, etc.; install
kitchen equipment and plumbing fix-
tures in private toilet; plastering
and painting.
No M In Class- ^
15 Feb-1955 22%
Ument No- ------Q.23> ---------
Date: --- 1Byl
Aut o: Hlt 10-2
Gam's, 0tzwi ;Ed To: S (3) .1
2. Tunnel - Between Administration and $19,500
South Buildings
Construct reinforced concrete tunnel
connecting basements of Administration
and South Buildings; relocate emergency
generator and related electrical
equipment; reroute utility lines;
1 Jan. 1955
55%
No: 30
Date: 26 November 1954
Remarks
All work in priority area No. 1
completed except for minor clean-
up and installation of telephone
service. Priority areas 2 and 3
are scheduled for painting the week
of 29 November. Requirements for
Building Receptionist's suite have
been established and are being for-
warded to GSA for estimate by the
contractor. Upon selection of
desired paneling for the DCI and
DDCI Suites, PBS Group Forces will
proceed to order this and other
materials preparatory to commencing
work; duct work for central air
conditioning has been fabricated.
Window type air conditioners
completely installed in accessible
areas, except the wiring. Plumbing
work in DCI toilet and kitchen to
start immediately following oc-
cupancy of priority area No. 1 space
by ONE.
Concrete pouring of tunnel walls
and roof was accomplished on 24
November; approximately 14 days
will be required for proper setting
before forms can be removed. At
that time, the GPO operation at
the South Buildi
t
ng
unnel entrance
Approved For Release 2001 -RDP78-04718A00100030003-6
Approved For Release 2001/08/10 : CIA-RDP78-04718AO01000030003-6
0C .rIDF,WTIl
Page #2
Project
Tunnel {cont'd)
relocate toilet in Administration
Building; erect partitions, plaster,
paint, etc.; restore grounds, trees,
shrubs, etc.
Estimated
Estimated Completion
Cost Date
3? Renovations - East Elevator South
Bu-1 *20,900.
l
4.
5.
Modernize cab interior; install new
automatic cab and corridor doors; in-
t
P umbing; Painting; soundproofing;
construction of security barriers and
reception booths; enlargement of mail
loading platforms.
$75,000
(tentative)
15 April 1955
31 Jan. 1955
.1
and door
grilles; electrical service;
air conditioning (special areas)
s
all new automatic leveling and
control equipment.
Alterations - M & Buildings
Removal and erection. of par-
titions; shoring, vaulting window
Utility Wirin
and Curie
Install 396 . receptacles; provide
branch panel capacity for complete
air conditioning; install 245 window
and 7 package type air conditioning
units. Install 300 KVA transformer
and enlarge transformer vault at
$71,348. 15 Dec. 1954
25X1A6a
Percent
Cpleted Remarks
Iwill relocate to per-
mitting additio unne work
within South Building. Final in-
spection on emergency generator
installation will be made week of
29 November, allowing PBS to con-
tinue with automatic changeover
gear installation.
30% All phases of work on schedule; in-
- stall.ation to start 2 January, or
shortly thereafter, with completion
by 15 April.
32% All alterations in connection with
DDI move are progressing satis-
factorily. Phase five of moving
schedule has been completed. Three
additional Job orders started
during current week. Further re-
novations will be delayed pending
completion of barrier reception
booths and turn stiles.
96% Final in
s
ti
y
Electrical service for Staff D Coxrnn0
has been made temporary available
pec
on of package unit
installations on original contract
delayed until next week. In-
stallation of transformer and
enlargement of transformer vault at
M progressing satisfactoril
Approved For Release 2001/0-RDP78-04718A001000030003-6
Approved For Release 2001/08/10 : CIA-RDP78-04718AO01000030003-6
CONFIDE \TTIA
Page #3
25X1A6a Project
Utility Wiring cont'd
Building (To be., acccmiplished
as an addition to, the initial air
conditioning contract).
*re
Estimated
Estimated Completion Percent
,Cost Date Completed
Remarks
pending installation of 300 KVA
transformer. Bids have been.re-
ceived at GSA for balance of
required air conditioning equipment
for Staff D.
6. Alterations - R & S Building $27,813. 29 Nov. 195+
Installation of approximately 450
lineal feet of partitions; vaulting;
air conditioning; ventilation; heating;
floor leveling, asphalt tile flooring,
fluorescent lighting.
25X1A6a
7?
Alterations - $375,000.
Extensive alterations neluding
erection of partitions; vaulting;
soundproofing; reinforcing floors;
painting; plastering; plumbing;
air conditioning, etc.
Approved
Jan. 1955
57%
Alterations and renovations, in
eluding air conditioning has been
completed. Inspection made by GSA
Inspector 4 November reveals that
miscellaneous items amounting to
$100. must be accomplished before
final inspection is made. Have
been advised by GSA Inspector that
approximately 75 percent of this
work has been accomplished, expect
remaining work to be completed in
a few days.
Erection of vault walls on 2nd
floor complete. Erection of cinder
block walls around air-handlers
and other equipment rooms continuing,
Installation of metal framework for
hung ceilings on second floor
continuing. Carpenters erecting
stud and sheetrock partitions on
first floor. Repair of windows
and mechanical installations
continuing. Several addendums in
process of acceptance. Duct work
on second floor 98 per cent complete,
and in basement, approximately
35 per cent. Vault doors requisit-
441111 in July are expected to arrive
For Release 2001/08/10: CI - DP78-04718A001000036b93f61rst week in December.
Approved For Release 2001/08/10 : CIA-RDP78-04718AO01000030003-6
Page ##
25X1A6a
25)IA Utility
Project
Estimated
Estimated Completion Percent
Cost Date Completed
*55,0009 30 Nov. 195+
tall equipment to
insure satisfactory performance of
heating: air conditioning., ventilating
and hot water system.
Main electrical breaker received
this date. Proposal from
Cc2nbustionaire., contractor assigned
to project., past due for en-
largement of transformer facilities.
The lack of available heavy duty
Wire is causing concern to the
contractor.