ADVISORY REPORT ON EVALUATION OF REVISED PROPOSAL FOR ADDITIONAL WORK

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
CIA-RDP69B00279R000200130024-4
Release Decision: 
RIPPUB
Original Classification: 
K
Document Page Count: 
2
Document Creation Date: 
December 14, 2016
Document Release Date: 
August 22, 2002
Sequence Number: 
24
Case Number: 
Publication Date: 
March 9, 1967
Content Type: 
MEMO
File: 
AttachmentSize
PDF icon CIA-RDP69B00279R000200130024-4.pdf88.96 KB
Body: 
Approved For Release 2002/09/03 : CIA-RDP69B00279R000200130024-4 DEFENSE CONTRACT AUDIT AGENCY CAMERON STATION ALEXANDRIA, VIRGINIA 22314 STATINTL SUBJECT: Advisory Report on Evaluation of Revised Proposal for Additional Work Lockheed Aircraft Corporation (Lockheed-California Company) Burbank, California Contract No. SP-1928 TO Contracting Officer OSA-0986-67 1-67-29-7o REPLY TO: Audit Liaison Office P.O. Box 8155 S.W. Station Washington, D.C. 2002+ 9 March 1967 REF : Contractor's 27 December 1966 Revised Proposal 1. Per request, an evaluation has been performed of the reference proposal. This evaluation relates generally to the revised estimated costs of Items 1 and 2 (modification of 7 units and 4 sets conversion parts) but specifically to the proposed estimated costs for modifying three additional airplanes. It included (1) verifying that the contractor computed appro- priate midpoints of labor effort, (2) verifying that the midpoint direct labor rates used were those negotiated in May 1966, (3) verifying that the overhead and G&A rates used were those negotiated and approved in December 1966, and (!) comparing proposed material costs with those recorded and committed through 29 January 1967. 2. As a result of our evaluation, none of the proposed costs applicable to modifying the three additional airplanes is questioned. The proposed revised total estimated contract cost/price are summarized below. The auditor's equivalent recommendation with pertinent comments follows: Estimated Estimated Ceiling Contractor Cost Profit Price Price Initial seven air- planes/four sets of parts Three additional airplanes Approved For Releas - Approved For Release 2002/09/03 : CIA-RDP69B00279R000200130024-4 STATINTL STATINTL STATINTL Auditor STATINTL 3. This contract is a FPR-type contract with limited upward and unlimited downward adjustment provision at completion. The contract does not specify the estimated cost and rate of profit. However, har TATINTL using the initial profit claimed for Items 1 and 2 of IJ th initial estimated price of and the initial ceilinc`.- TINTL it appears that the contemplated profit rate was e is no incentive or formal sharing arrangement on costs to determine profit on a FPR type contract. Therefore, the auditor's profit computati aifINTL above paragraph 3, is based upon the use of a I profit rate. T `3 a preliminary computation of total price at completion for funding purposes as the final redetermination is only after completion of the contract. At completion and upon receipt of the contractor's final claim, this audit report will be issued. 4. The auditor recommends that technically qualified personnel evaluate the proposed hours, material costs, and other direct charges. This recommendation is made in view of the substantial decreases in proposed labor hours and material costs between the initial and revised estimated STATINTL proposal for Items 1 and 2, approximating espectively. It is recommended that these costs applicable to the three airplanes be evaluated for a determination of reasonableness. ARTHUR G. HANLEY DCAA Representative - APL Approved For Release 2002/09/03 : CIA-RDP69B00279R000200130024-4