TRIP TO LTV ELECTROSYSTEMS, GREENVILLE, TEXAS 7 DEC - 8 DEC 1966
Document Type:
Collection:
Document Number (FOIA) /ESDN (CREST):
05752603
Release Decision:
RIPPUB
Original Classification:
U
Document Page Count:
1
Document Creation Date:
March 9, 2023
Document Release Date:
February 10, 2021
Sequence Number:
Case Number:
F-2011-01575
Publication Date:
December 14, 1966
File:
Attachment | Size |
---|---|
TRIP TO LTV ELECTROSYSTEM[15858483].pdf | 34.63 KB |
Body:
Approved for Release: 2020/12/28 C05752603
ORD-5555-66
14 December 1966
MEMORANDUM FOR THE RECORD
SUBJECT: Trip to LTV Electrosystems, Greenville, Texas
7 Dec - 8 Dec 1966
1. On December 7, I went to LTV to observe the pro-
gress of the modificatipn of the SP-211 Multisensor System
and finish off the test schedule with Dave Lane and Chuck
Michelsen.
2. I brought back a somewhat optimistic project test
schedule of what LTV plans to do on CHIGOE from now until
the end of January. The schedule has already slipped a
week since I was down at LTV. The reason for the slippage
is Litton's inability to solve a voltage sensitivity pro-
blem in their LN-15 inertial platform. Without the LN-15
no integrated navigation flight tests can be performed.
3. I discussed with Cliff Slagle the addition of a
data annotation block on the D-5 camera. The only camera
that now has a data block on the film is the KA-53 which
is primarily a day time camera. Seeing that many of our
missions will be at night, I believe it will be advanta-
geous to have a data block on the D-5 or D-10 if we use
it.
4. The main problems confronting CHIGOE at this time
are the LN-15 and the unresolved problem of Dalmo-Victor's
LLLTV.
0/ORD/DD/S&T