TRIP REPORT - CHIGOE - LTV, GREENVILLE 13 APRIL 1966

Document Type: 
Collection: 
Document Number (FOIA) /ESDN (CREST): 
05751068
Release Decision: 
RIPPUB
Original Classification: 
U
Document Page Count: 
3
Document Creation Date: 
March 9, 2023
Document Release Date: 
February 10, 2021
Sequence Number: 
Case Number: 
F-2011-01575
Publication Date: 
April 14, 1966
File: 
AttachmentSize
PDF icon TRIP REPORT - CHIGOE - LT[15864301].pdf142.83 KB
Body: 
Approved for Release: 2021/01/13 C05751068. � \cto tj 1.. MEMORANDUM 14 April 1966 SUBJECT Trip Report - CHIGOE - LTV, Greenville 13 April 1966 1. Met with Dave Lane, C. F. Wilson, Jud Ray, Contractor Personnel, and Audit Liaison Representative, Discussed Phase II Cost Analysis Objective and wired into Project CHIGOE. He will complete probably in a matter of days (b)(3) (b)(3) (b)(1) (b)(3) 10 USC 130 3. Arrangements were also made with Roy Ferguson for to review the LTV Grand Prairie proposal within the same general time span of the other two proposals, if at all possible. when 4. Negotiation of all three proposals will be done completes. 5. &FE & CFE property schedules, inadvertently ommitted from the already submitted PH II proposal, were mailed to Hqs, the first of the week. (11 April) agreed to supplement the GFE list with priority indicators. 6. Send a L/I for Phase II to LTV. Cover: Long lead; continuity of engrg/Program Mgment personnel; GFP additions (Verdan computers). 7. 'Dave has talked to Bill about DX necessity; he feels priority assignments will be necessary, pproved for Release: 2021/01/13 C05751068 (b)(3) Approved for Release: 2021/01/13 C05751068 8, Amend PH I contract with date of 1 April completion. 9. Contractor (C. F. Wilson) will submit data on IR film: quantity, specs., source, etc. 10. Regarding Phase II contract type, Dave asserted that even trying to split out LTV portion and place on a FP basis (placing material (CFE) on a cost basis) would be too risky, There are too many unknowns. Stated that several of the major pieces of equipment (TV; FLIR; APQ-110; and the LN-15 (INS) are R&D type procurement, in some cases pushing the state-of-the-art. Possible delays from these sources he felt would make the contractor's position untenable, certainly within the presently contemplated target completion date of approximately 1 December 1966. Accordingly, in the circumstances, Harlan will cost review the proposal as CPFF. (NOTE: It was pointed out that in the CHIGOE competition, the second contractor had proposed on an FP (25% ceiling) basis as a step toward jarring the proposal loose from a cost type and pave the way for FP consideration. Dave felt however, irrespective of how the competitor had proposed, the circumstances now encountered were identical to both contractors and would force some change in contract terms to accommodate these circumstances. He also pointed out that the signals had been changed since the original criteria for the first proposal: Much -of the peculiar gear was to be GFP whereas the-items are now to be CFE with the burden of procurement placed on the contractor. Subject to confirmation with Dr. Brewer, the contractor's position appears valid. 11. Schedule of time of delivery requirement - CFE & GFE, see p. 18, Report No. G-4000.01.145 (Fig. 4-1). GFE must be completely delivered by week of 26 June 66. 12. Detailed GFE and CFE are set forth in PH I, Engineering Study Report on SP-211 Mod., Report No. G-8853.01.02, 1 April 66, Revised 7 April 66. Approved for Release: 2021/01/13 C05751068 Approved for Release: 2021/01/13 C05751068 Post Office Box 490 Greenville, Texas I March 1966 In Reply Refer To: 53-0014.04 REGISTER-0 SUBJECT Long Lead Time Procurement TO Post Office Box 6057 MideltY,Statton Washington, O. C. ATTENTION Mr, Walter G. We are becoMing increasingly concerned with the possibility of delays in the program due to bong lead time Contractor Furnished Equipment. DiscutsiOns with manufacturers Indicate that in same cases serious problems will be encountered if we do not place firm orders in the immediate future. The below list with a very rough estimate of-atouisitbon 0011st has been extracted from material lists. These items are firm insofar as the technical people are concerned and represent those which are very bong lead time. We therefore request you consider giving an immediate 90"aMead to Piecing the orders with suppliers. AN/APW193 Doppler Radar AN/AS*45 Computer AN/AP*0167 Radar Altimeter AN/APQ0.110 Terrain Following Radar $ 20,000. �4,000. 7,000. 200,000. Not included in the above :re Items for whj.ch complete technical work has not been accomplished and therefore are not firm enough to place on procurement. An example of such an item is the Inertial Navigation System which will cost in the neighborhood of $300,000. If so desired, funds could he allocated and actual go-ahead at such future time as there is resolution of the technical questiens. If we can be of further assistance or supply additional information, please advise, GROUP EXCLUDED FROM AUTOMATIC DOWNGRADING OD DECLASSIFICATION ORLIN D. R. Lan Program Manager Thls'Document contains Information affecting the National Defense of the United States within the meaning of the Espionage Laws, Title 18 U. S. C., Sections 793 and 794. Its transmission or the revelation of Its contents In any manner to an unauthorized person is prohibited by law. 7 a Approved for Release: 2021/01/13 C05751068